State Mission For Clean Ganga

Weekly progress report of Namami Gange Projects



Sr Name of Project Funding Mode No. of STP/FSTP/DSTP Capacity of STP (MLD) No. of drains to be tapped AA&ES and date Date of completion Previous Progress Weekly Progress Overall Progress Remarks
Physical Progress Financial Progress Physical Progress Financial Progress Physical Progress Financial Progress
Sanction cost Work Cost Centage O& M Cost (5/10/15 Years) Sanction date Upto 29.04.2023 (Total) Upto 29.04.2023 (Total) 29.04.2023 to 06.05.2023 29.04.2023 to 06.05.2023 Upto 06.05.2023 (Total) Upto 06.05.2023 (Total)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18=14+16 19=15+17 20
Completed Projects
1 Sewerage and non sewerage project at District - B, E Prayagraj Non-EAP DBOT 3 85 4 207.39 187.53 19.86 0 06.05.2010/ 03.01.2019 March-2016 1 175.48 - 0 1 175.48 Work has been completed
2 Sewerage and non sewerage project at District - A Prayagraj EAP DBOT 1 20 - 97.95 97.95 0 0 06.05.10/ 03.01.2019 March-2016 1 89.07 - 0 1 89.07 Work has been completed
3 Sewerage Project at District - E, Prayagraj EAP DBOT 0 0 - 142 126.7 6.57 8.73 22.02.2011 June-2016 1 138.25 - 0 1 138.25 Work has been completed
4 14 MLD STP at Salori, Prayagraj EAP DBOT 1 14 - 42.4 23.7706 1.9016 16.7246 27.11.2013 Sep-2016 1 34.93 - 0 1 34.93 Work has been completed
5 Sewerage Network at District - E, Prayagraj (Additional Works) EAP DBOT 0 0 - 52.78 48.9 3.88 0 28.09.2016 March-2018 1 50.43 - 0 1 50.43 Work has been completed
6 Sewerage Project at Kannauj Non-EAP DBOT 0 0 3 43.66 38.37 3.03 2.26 24.02.2011 March-2018 1 40.665 - 0 1 40.665 Work has been completed
7 Sewerage Project at Narora, Bulandshahar EAP DBOT 1 4 - 48.45 39.73 2.26 6.46 04.03.2014/ 09.05.2018 May-2018 1 47.69 - 0 1 47.69 Work has been completed
8 Sewerage Project at Garhmukteshwar Non-EAP DBOT 2 9 - 46.51 40.68 3.25 2.58 24.02.2011 May-2018 1 44.21 - 0 1 44.21 Work has been completed
9 Sewerage Project at Anupshahahr, Bulandshahar EAP DBOT 2 2.5 - 75.79 67.12 5.27 3.4 19.05.2014 March-2019 1 69.82 - 0 1 69.82 Work has been completed
10 Sewerage Project at District - C, Prayagraj EAP DBOT 0 0 - 170.95 154.009 9.8685 7.0725 27.11.2013/ 13.09.2019 June-2020 1 166.31 - 0 1 166.31 Work has been completed
11 Sewerage Project at District - B, Prayagraj EAP DBOT 0 0 - 300.8425 278.2669 18.8158 3.7598 31.12.2014/ 11.11.2019 June-2020 1 293.02 - 0 1 293.02 Work has been completed
12 I & D of Sisamau Drain, Kanpur NGP DBOT 0 0 5 63.8 57.64 4.61 1.55 03.10.2016 Feb-2019 1 60.36 - 0 1 60.36 Work has been completed
13 Sewerage Project at District - A, Prayagraj EAP DBOT 0 0 - 299.3956 269.1072 19.7504 10.538 20.02.2014/ 11.11.2019 June-2020 1 288.33 - 0 1 288.33 Work has been completed
14 I & D works at Ayodhya NGP DBOT 0 0 5 37.67 16.25 1.0955 20.32 11.06.2018 Dec-2019 1 16.82 - 0 1 16.82 Work has been completed
15 I & D and STP works at Bithoor, Kanpur NGP DBOT 1 1.3 7 13.4 10.25 0.7 2.45 10.10.2017 Jan-2020 1 10.73 - 0 1 10.73 Work has been completed
16 Rehabilitation and augmentation works at Vrindavan, Mathura NGP DBOT 0 0 3 42.82 26.74 1.19 14.89 11.12.2019 Feb-2020 1 21.06 - 0 1 21.06 Work has been completed
17 Sewerage works in District -1, Kanpur EAP DBOT 0 0 - 430.49 395.2 23.81 11.48 18.10.16/ 10.12.2019 March-2021 1 456.41 - 0 1 456.41 Work has been completed
18 Construction of 50 MLD STP at Ramna, Varanasi NGP HAM 1 50 3 161.31 102 8.16 51.15 23.12.2016/21.09.2017 March-2021 1 122.23 - 0 1 122.23 Work has been completed
19 I&D and STP works at Ramnagar, Varanasi NGP DBOT 1 10 5 72.91 23.88 1.75 47.28 28.07.2017 March-2021 1 26.32 - 0 1 26.32 Work has been completed
20 Rehabilitation of existing facilities including 15 year O&M at Prayagraj NGP HAM 0 0 - 904 58.15 0 845.85 09.03.2018 March-2021 1 261.05 - 0 1 261.05 Work has been completed
21 Faecal management works at Chunar, Mirzapur NGP DBOT 1 0.01 - 2.7 2.1556 0.069 0.48 07.03.2019 March-2021 1 1.98 - 0 1 1.98 Work has been completed
22 I&D works at Firozabad NGP DBOT 0 0 2 51.08 23.92 1.635 25.53 01.03.2019 July-2021 1 25.77 - 0 1 25.77 Work has been completed
23 Ramganga sewerage scheme, Moradabad Non-EAP DBOT 1 58 14 330.05 278.85 19.03 32.17 24.02.2011/ 31.07.2020 Sep-2021 1 277.21 - 0 1 277.21 Work has been completed
24 I&D and STP works at Kasganj NGP DBOT 1 15 2 76.73 36.6 2.49 37.64 24.12.2018 Dec-2021 1 39.28 - 0 1 39.28 Work has been completed
25 I&D and STP works at Etawah NGP DBOT 1 21 2 140.6 56.86 3.89 79.85 28.02.2019 Feb-2022 1 51.79 - 0 1 51.79 Work has been completed
26 Rehabilitation and augmentation of existing facilities at Mathura NGP HAM 1 30 20 460.45 264.4 8.78 187.27 11.06.2018 June-2022 1 295.23 - 0 1 295.23 Work has been completed
27 JICA assisted sewerage project, Varanasi JICA DBOT 1 140 1 659.62 633.41 26.21 0 14.07.2010/ 23.07.2020 June-2022 1 597.67 - 0 1 597.67 Work has been completed
28 I&D and STP works at Baghpat NGP DBOT 1 14 4 77.36 38.72 2.6616 35.98 19.02.2019 Dec-2022 1 29.63 - 0 1 29.63 Work has been completed
Sub Total (A) 20 473.81 80 5053.1081 3397.1593 200.5374 1455.4149 3731.745 0 3731.745
Ongoing Projects
29 I&D and STP works at Shuklaganj, distt. Unnao NGP HAM 1 5 5 65.18 25.93 1.9 37.35 28.07.17 Jun-2023 0.65 19.82 0.00% 0 0.65 19.82 Work is in progress
30 I&D and STP works at Unnao NGP HAM 1 15 1 102.2 43.73 3.22 55.25 28.07.17 May-2023 0.945 52.01 0.00% 0 0.945 52.01 Work is in progress
31 Rehabilitation and O&M of Sewage Infrastructure at Kanpur and STP at Panka NGP HAM 1 30 3 967.23 248.39 0 718.84 12.03.18 May-2023 0.96 220.73 0.00% 0 0.96 220.73 Work is in progress
32 I&D works & STP work for Naini, Phaphamau and Jhunsi in Prayagraj NGP HAM 3 72 18 767.6 280.14 21.67 465.79 19.05.17 May-2023 0.9785 276.97 0.13% 0 0.9798 276.97 Work is in progress
33 I&D and STP works at Sultanpur NGP DBOT 3 17 5 70.18 43.6778 2.5922 23.91 04.12.2019 Jun-2023 0.960299999999999 40.26 0.07% 0 0.960999999999999 40.26 Work is in progress
34 I&D and STP works at Jaunpur NGP DBOT 1 30 14 206.05 132.89 9.2536 63.91 12.02.2019 Jun-2023 0.985 131.89 0.00% 0 0.985 131.89 Work is in progress
35 I&D and STP works at Muzaffarnagar NGP HAM 2 54.5 8 234.03 108.32 7.33 118.38 02.01.2019 Jun-2023 0.7956 94.19 0.66% 0 0.8022 94.19 Work is in progress
36 I&D and STP works at Budhana town, Distt. Muzaffarnagar NGP HAM 1 10 3 48.76 25.1 1.7 21.96 18.02.2019 Jun-2023 0.8963 19.5 0.06% 0 0.8969 19.5 Work is in progress
37 I&D and STP works at Moradabad NGP HAM 1 25 5 118.69 53.53 3.52 61.64 23.07.18 Dec-2024 0.01 1.76 0.00% 0 0.01 1.76 Work is in progress
38 I&D and STP works at Lucknow NGP DBOT 2 40 4 213.91 101.31 6.97 105.63 02.03.2019/ 06.05.2020 Dec-2023 0.3025 27.44 0.83% 0 0.3108 27.44 Work is in progress
39 Sewerage works at Ghazipur NGP HAM 1 21 - 152.83 53.5973 3.0627 96.17 16.11.2017 / 06.05.2020 Jan-2024 0.46 28.64 1.00% 0 0.47 28.64 Work is in progress
40 I&D and STP works at Mirzapur NGP HAM 2 17 12 129.08 51.9825 4.04 73.05 14.11.2017/ 28.05.2020 Jan-2024 0.54 31.58 1.00% 0 0.55 31.58 Work is in progress
41 I&D and STP works at Bareilly NGP HAM 3 63 15 271.39 139.44 10.7 121.25 03.01.2019 Áug-2024 0.5903 59.32 3.00% 0 0.6203 59.32 Work is in progress
42 I&D and STP works at Kairana NGP DBOT 1 15 1 78.42 35.97 3.94 38.51 07.12.2020 May-2023 0.6203 15.41 0.45% 0 0.6248 15.41 Work is in progress
43 I&D and STP works at Fatehgarh - Farrukhabad NGP HAM 3 45 7 261.12 181.73 6.98 72.41 16.10.17/ 12.01.2021 Jun-2024 0.42 69.96 6.00% 0 0.48 69.96 Work is in progress
44 I&D and STP works at Ayodhya NGP HAM 1 33 15 221.66 109.03 7.62 105.01 06.05.2021 Dec-2024 0.085 3.81 1.50% 0 0.1 3.81 Work is in progress
45 Rehabilitation/Renovation of Agra Sewerage Scheme (I&D works) EAP HAM 13 177.6 23 842.25 371.29 25.4 445.56 24.12.2018/ 06.05.2020 Mar-2025 0.02 12.7 0.00% 0 0.02 12.7 Work is in progress
Sub Total (B) 40 670.1 139 4750.58 2006.0576 119.8985 2624.62 1105.99 0 1105.99
Projects under tendering stage
46 Pollution Abatement works for River Kali at Meerut town EAP HAM 1 220 2 690.71 384.21 26.31 280.19 19.02.2019/ 06.05.2020 Dec-2025 0 13.34 - 0 0 13.34 Instruction has been issued to field officer for issuing LOA to (JV) M/s GA Infra Private Ltd, Rajasthan and, M/s SSG Infratech Pvt. Ltd. New Delhi on 26.04.2023.
47 I&D and STP works at Saharanpur EAP HAM 1 135 61 577.23 266.34 20.55 290.34 15.06.2022 Dec-2025 0 10.27 - 0 0 10.27 Tender was invited on 27.03.23. 06 bid have been received, which are under evaluation.
48 I & D works of balance drains at Distt. Mathura NGP HAM 1 60 4 292.56 149.85 9.61 133.1 07.09.2022 Dec-2025 0 0 - 0 0 0 Tender was invited on 03.04.23. 04 bid have been received, which are under evaluation.
49 I&D of Assi Nala and additional construction of STP at Ramna, Varanasi NGP DBOT 1 55 2 308.09 116.46 7.8 183.83 19.10.2022 Dec-2025 0 0 - 0 0 0 Tender was invited on 06.03.23. 09 bid recived.Technical bid under evaluation.
50 I & D works for Chhata NP at Distt. Mathura NGP DBOT 1 6 11 56.15 34.52 2.22 19.41 25.10.2022 Dec-2025 0 0 - 0 0 0 NIT has been issued on 06.04.2023. Last date of bid submission is 26.05.2023.
51 I & D works for Kosi Kalan NP at Distt. Mathura NGP DBOT 1 12 1 66.59 31.23 2.03 33.33 25.10.2022 Dec-2025 0 0 - 0 0 0 NIT has been issued on 06.04.2023. Last date of bid submission is 26.05.2023.
52 I & D of Vrindavan town at Distt. Mathura NGP DBOT 1 13 2 77.7 39.9 2.56 35.24 25.10.2022 Dec-2025 0 0 - 0 0 0 NIT has been issued on 06.04.2023. Last date of bid submission is 26.05.2023.
53 I & D and STP works at Hathras NGP DBOT 1 24 10 128.91 70.47 4.55 53.88 30.01.2023 Dec-2025 0 0 - 0 0 0 NIT has been issued on 06.04.2023. Last date of bid submission is 26.05.2023.
54 I&D of 7 drains and augmentation of Rajapur STP at Prayagraj NGP DBOT 1 90 7 475.98 242.85 15.24 217.89 27.01.2023 Dec-2025 0 0 - 0 0 0 NIT has been issued on 29.03.2023. Last date of bid submission is 15.05.2023.
55 I&D and STP works at Lucknow, Phase-II, Part-I NGP DBOT 1 50 3 264.67 137.55 8.52 118.6 30.01.2023 Dec-2025 0 0 - 0 0 0 NIT has been issued on 18.03.2023. Last date of bid submission is 17.05.2023.
56 I & D of 13 drains and augmentation of Salori STP at Prayagraj NGP DBOT 1 43 13 331.75 180.27 11.22 140.26 14.03.23 Dec-2025 0 0 - 0 0 0 Project has been sanctioned vide NMCG letter dated 14.03.2023. Bid documents have been submitted to NMCG on 01.04.2023.
Sub Total (C) 11 708 116 3270.34 1653.65 110.61 1506.07 23.61 0 23.61
Grand Total (A+B+C) 71 1851.91 335 13074.0281 7056.8669 431.0459 5586.1049 4861.345 0 4861.345