Total Visitors April 2023 - Till Date
Login
Jal Jeevan Mission-Agency Dashboard
Agency
Select Agency
AFCONS
Banko Ganga
BGCCPL-Ramky JV
Brija Banco Pvt. Ltd
DARA ENGINEERING
Dara- Eco Protection JV
Eagle Infra - Sudhakara Infra JV
East India Udhyog- Kaveri JV
ECO PROTECTION ENGINEER
GA INFRA
GA INFRA - BABA JV
GA INFRA-VPL
GAJA - GAIPL JV
GAJA - SGIPL JV
Gayatri Projects LTD
GVPR
HFCL- JWIL JV
Indian Hume Pipe
ION EXCHANGE
Jain Const.
JAKSON
JAKSON - VISHVARAJ JV
JMC - Lakshmi JV
JMC-JWIL JV
JWIL
KLSR - RAYS JV
Larsen and Toubro Ltd
LC INFRA
Megha
Ms Sudhakara Infratech Pvt. Ltd
Multiurban
N.K. Gupta and K.B. Gupta Contractors
NCC Ltd
NCC-APCO JV
NKG-PRIMUS JV
OMIL-JWIL JV
PNC-SPML-JV
Power Mech Projects Ltd
Ramky baba
Rithwik-Koya JV
SIEPL – BRCCPL JV SKYLARK
SLC-SMC JV
SPML Infra
Unipro
UNIVERSAL MEP
VIKRAN-VPRPL (JV)
Vindhya-GAJA (JV)
VISHVARAJ
VPRPL
VSA
Welspun Kaveri Infraprojects JV
District
All District
Ambedkar Nagar
Amethi
Bulandshahr
Jaunpur
Sant Ravidas Nagar
01
Track Scheme
02
Track Village-
Heirarchy Details
Assign District:
1
Assign Scheme :
62
Assign Villages :
247
Physical Progress
Households :
39117
FHTC :
38527
FHTC(%) :
98%
Total HGJ :
158
Total Certified :
76
HO Villages :
0
Incoming Complaints Received
All Complaints :
410
Close Complaints :
342
Pending Complaints :
68
Feedback from Gram Pradhan On Call
All Complaints :
97
Close Complaints :
54
Pending Complaints :
43
Estimated Cost and Expenditure Detaile(In Lacs)
Estimated Cost :
24095.79
Expenditure :
18546.49
Expenditure(%) :
76.97
Agency Progress Details
Sr.No.
District
No Of Scheme
No Of Village
households
FHTC
FHTC %
Har Gar Gal
Certified
1
2
3
4
5
6
7
8
9
1
Ambedkar Nagar
62
247
39117
38527
98.49%
158
76
Components Wise Physical Progress
Sr.No.
Components
Taget
Achivement
%
1
2
3
4
5
1
Tubewell
62
62
100.00
2
Pump House
62
62
100.00
3
Chlorination system
58
42
72.41
4
OHT
62
62/46
100.00
5
Distribution (Line Laying in Km.)
1152
1150
99.83
6
Solar Plant
62
62
100.00
7
F.H.T.C.
39117
38527
98.49
8
W.T.P.
0
0
0.00
9
ROAD DISMENTLING/RESTORATION(KM)
258
250
96.90
10
Villages where 100 % road restoration completed
97070
61309
63.16
11
Comissioning of Village
247
218
88.26
12
Regular water supply
247
204
82.59
;