1
|
Baghpat
|
LC INFRA
|
Basi W/S Scheme
|
Basi
|
20014085/01
|
Electricity Connection Pending
|
01-Jul-2024
|
-
|
Resolved
|
Electrical connection paper pending at Gram Pradhan
|
|
2
|
Etah
|
JMC - Lakshmi (JV)
|
Bahadurpur kasimpur Water supply scheme
|
Bahadurpur Kasimpur
|
20098697/01
|
Electricity Connection Pending
|
04-Aug-2026
|
15-Sep-2026
|
Resolved
|
Public hindrance
|
|
3
|
Etah
|
JMC - Lakshmi (JV)
|
Loya Badshapur Water supply scheme
|
Loya Badshahpur Peetam Singh
|
20099319/01
|
Electricity Connection Pending
|
04-Aug-2026
|
15-Sep-2026
|
Resolved
|
work not started by UPPCL
|
|
4
|
Etah
|
JMC - Lakshmi (JV)
|
Nagaria Urf Sikandarpur Doga water supply scheme
|
Nagaria Urf Sikandarpur Duga
|
20100049/01
|
Electricity Connection Pending
|
04-Aug-2026
|
15-Sep-2026
|
Resolved
|
work not started by UPPCL
|
|
5
|
Etah
|
Power Mech Projects Ltd
|
SHITALPUR WATER SUPPLY SCHEME
|
Shitalpur
|
20086111/01
|
Electricity Connection Pending
|
03-Aug-2026
|
03-Oct-2026
|
Resolved
|
Payment has to be done.
|
|
6
|
Etawah
|
OMIL-JWIL (JV)
|
KISHONPUR JADONPUR
|
Kishonpur Jadonpur
|
20099912/01
|
Electricity Connection Pending
|
04-Jun-2026
|
04-Sep-2026
|
Resolved
|
Electric connection pending.
|
|
7
|
Hathras
|
BGCCPL-Ramky (JV)
|
DHANDAULI WSS
|
Dhandholi
|
20071579/01
|
Electricity Connection Pending
|
06-Feb-2026
|
03-Sep-2026
|
Resolved
|
Dhandauli TW payment done on 06.02.2026. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month
|
|
8
|
Hathras
|
BGCCPL-Ramky (JV)
|
MITANPUR WATER SUPPLY SCHEME
|
Bhogaon Nagla Jayas
|
20087362/01
|
Electricity Connection Pending
|
17-Sep-2024
|
03-Sep-2026
|
Resolved
|
Mitanpur TW payment done on 17.09.2024. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month
|
|
9
|
Hathras
|
BGCCPL-Ramky (JV)
|
KARAIYA WATER SUPPLY SCHEME
|
Karaiya
|
20061070/01
|
Electricity Connection Pending
|
16-Sep-2024
|
03-Sep-2026
|
Resolved
|
Karaiya TW payment done on 16.09.2024. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month
|
|
10
|
Hathras
|
BGCCPL-Ramky (JV)
|
DHANOTI WATER SUPPLY SCHEME
|
Dhanothi
|
20098363/01
|
Electricity Connection Pending
|
17-Aug-2024
|
03-Sep-2026
|
Resolved
|
Dhanoti TW payment done on 17.08.2024. Connection still pending. expected issue resolve Date Given By concern Officer DVVNL in 1 Month
|
|
11
|
Hathras
|
BGCCPL-Ramky (JV)
|
TONDA WATER SUPPLY SCHEME
|
Tonda
|
20092744/01
|
Electricity Connection Pending
|
14-Mar-2024
|
-
|
Resolved
|
Tonda TW payment done on 14.03.2024. Connection still pending
|
|
12
|
Hathras
|
ION EXCHANGE
|
RASGAWAN WSS
|
Chamarpur
|
ZONE03
|
Electricity Connection Pending
|
04-Aug-2026
|
15-Sep-2026
|
Resolved
|
Electric estimation was paid on 6/09/2024. Connection still pending
|
|
13
|
Hathras
|
ION EXCHANGE
|
SHEIKHUPUR AJIT WSS
|
Tataarpur
|
ZONE04
|
Electricity Connection Pending
|
04-Aug-2026
|
15-Sep-2026
|
Resolved
|
Connection payment was done on 27.06.2023. Connection still pending
|
|
14
|
Hathras
|
ION EXCHANGE
|
RASGAWAN WSS
|
Kheria
|
ZONE04
|
Electricity Connection Pending
|
04-Aug-2026
|
15-Sep-2026
|
Resolved
|
Connection payment was done on 16.02.2024. Connection still pending
|
|
15
|
Hathras
|
ION EXCHANGE
|
SALEMPUR WSS
|
Madhapithu
|
ZONE02
|
Electricity Connection Pending
|
04-Aug-2026
|
15-Sep-2026
|
Resolved
|
For Borewell No 1 connection was paid on 19.12.2023. Connection still pending
|
|
16
|
Hathras
|
ION EXCHANGE
|
TASINGA WSS
|
Tasinga
|
ZONE01
|
Electricity Connection Pending
|
04-Aug-2026
|
20-Sep-2026
|
Resolved
|
Tasinga BW 1 payment done on 21.08.2021. Connection still pending
|
|
17
|
Hathras
|
ION EXCHANGE
|
TASINGA WSS
|
Tasinga
|
ZONE01
|
Electricity Connection Pending
|
04-Aug-2026
|
16-Sep-2026
|
Resolved
|
Tasinga TW 2 connection payment was done on 21.08.2024. Connection still pending
|
|
18
|
Hathras
|
ION EXCHANGE
|
TASINGA WSS
|
Tasinga
|
ZONE01
|
Electricity Connection Pending
|
04-Aug-2026
|
17-Sep-2026
|
Resolved
|
Tasinga TW 3 connection payment was done on 06.09.2024. Connection still pending
|
|
19
|
Kushi Nagar
|
NCC Ltd.
|
GANGAULI GOGP
|
Gangauli
|
20080227-OHT1
|
Electricity Connection Pending
|
30-Jun-2025
|
10-Nov-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
20
|
Kushi Nagar
|
NCC Ltd.
|
AMDARIA
|
Amadaria
|
20073033-OHT1
|
Electricity Connection Pending
|
30-Jun-2025
|
15-Sep-2026
|
Resolved
|
Electricity conection Pending Yet
|
|
21
|
Kushi Nagar
|
NCC Ltd.
|
CHANDARPUR
|
Chandarpur
|
20082193-OHT1
|
Electricity Connection Pending
|
30-Jun-2025
|
10-Sep-2026
|
Resolved
|
Electricity Connection Pending.
|
|
22
|
Kushi Nagar
|
NCC Ltd.
|
INDERSENWA
|
Ramkola
|
20097181-OHT1
|
Electricity Connection Pending
|
30-Jun-2025
|
11-Nov-2026
|
Resolved
|
Electricity Connection Pending yet.
|
|
23
|
Kushi Nagar
|
NCC Ltd.
|
Bharsar Khas
|
Bharsar Khas
|
20040237-OHT1
|
Electricity Connection Pending
|
30-Jun-2025
|
10-Oct-2026
|
Resolved
|
Electricity Connection Pending Yet.
|
|
24
|
Kushi Nagar
|
NCC Ltd.
|
BADAHARA BABU-K GOGP
|
Badahara
|
20078366-OHT1
|
Electricity Connection Pending
|
30-Jun-2025
|
10-Sep-2026
|
Resolved
|
Electricity Connection Pending yet.
|
|
25
|
Kushi Nagar
|
NCC Ltd.
|
SIDHAWE
|
Sidhawe
|
20082263-OHT1
|
Electricity Connection Pending
|
30-Jun-2025
|
10-Sep-2026
|
Resolved
|
Electricity Connection Pending Yet.
|
|
26
|
Kushi Nagar
|
NCC Ltd.
|
AHIROULI RAJA GOGP
|
Ahirauli Raja
|
20078933-OHT1
|
Electricity Connection Pending
|
30-Jun-2025
|
15-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
27
|
Kushi Nagar
|
NCC Ltd.
|
CHARGAHA
|
Chara Gaha
|
20078970-OHT1
|
Electricity Connection Pending
|
30-Jun-2025
|
15-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
28
|
Kushi Nagar
|
NCC Ltd.
|
GAURI SHRIRAM
|
Gauri Shri Ram
|
20082320-OHT1
|
Electricity Connection Pending
|
30-Jun-2025
|
20-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
29
|
Kushi Nagar
|
NCC Ltd.
|
RAMPUR BAGAHA
|
Rampur Bagaha
|
20082305-OHT1
|
Electricity Connection Pending
|
03-Jun-2025
|
15-Sep-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
30
|
Kushi Nagar
|
NCC Ltd.
|
AWARAHI KRITPURA
|
Awarahi Kritpura
|
20082087-OHT1
|
Electricity Connection Pending
|
03-Jun-2025
|
10-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
31
|
Kushi Nagar
|
NCC Ltd.
|
MORWAN
|
Morwan
|
20073407-OHT1
|
Electricity Connection Pending
|
03-Jun-2025
|
15-Oct-2026
|
Resolved
|
Electricaity Connection Pending yet.
|
|
32
|
Kushi Nagar
|
NCC Ltd.
|
BINDUAR
|
Binduar
|
20081809-OHT1
|
Electricity Connection Pending
|
03-Jun-2025
|
15-Sep-2026
|
Resolved
|
Electricity connection Pending yet.
|
|
33
|
Kushi Nagar
|
NCC Ltd.
|
SAURAHA BUZURG
|
Saurha Buzurg
|
20073432-OHT1
|
Electricity Connection Pending
|
03-Jun-2025
|
15-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
34
|
Kushi Nagar
|
NCC Ltd.
|
POKHAR BHINDA
|
Pokhar Bhinda
|
20101611-OHT1
|
Electricity Connection Pending
|
16-Dec-2024
|
10-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
35
|
Kushi Nagar
|
NCC Ltd.
|
NAKATAHA BASDILA
|
Nakataha Basdila
|
20097035-OHT1
|
Electricity Connection Pending
|
04-Oct-2024
|
15-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
36
|
Kushi Nagar
|
NCC Ltd.
|
KATAURA
|
Kataura
|
20101609-OHT1
|
Electricity Connection Pending
|
04-Jun-2024
|
10-Nov-2026
|
Resolved
|
Electricity connection not done yet.
|
|
37
|
Kushi Nagar
|
NCC Ltd.
|
MATHIA MAFI RO
|
Mathiamafi Urf Dukhi Ganeshpur
|
20102430-OHT1
|
Electricity Connection Pending
|
04-Jun-2024
|
20-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
38
|
Kushi Nagar
|
NCC Ltd.
|
GAURI SHUKUL
|
Gauri Sukul
|
20102417-OHT1
|
Electricity Connection Pending
|
04-Jun-2024
|
20-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
39
|
Kushi Nagar
|
NCC Ltd.
|
KHAIRATIYA
|
Jalal Chhapra
|
20106713-OHT1
|
Electricity Connection Pending
|
04-Jun-2024
|
30-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
40
|
Kushi Nagar
|
NCC Ltd.
|
RAKBAJUNGLI PATTI R
|
Rakbajunglli Patti
|
20098913-OHT1
|
Electricity Connection Pending
|
04-Jun-2024
|
15-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
41
|
Kushi Nagar
|
NCC Ltd.
|
BHIURA
|
BHIURA
|
20106858-OHT1
|
Electricity Connection Pending
|
04-Jun-2024
|
16-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
42
|
Kushi Nagar
|
NCC Ltd.
|
AHIRAULI
|
Ahiraule
|
20106859-OHT1
|
Electricity Connection Pending
|
04-Jun-2024
|
15-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
43
|
Kushi Nagar
|
NCC Ltd.
|
PATERHA
|
Paterha
|
20102431-OHT1
|
Electricity Connection Pending
|
06-Apr-2024
|
10-Sep-2026
|
Resolved
|
Electricity connection pending yet
|
|
44
|
Kushi Nagar
|
NCC Ltd.
|
PAKRI BRIJLAL
|
Pakari Brijlal No.2
|
8386824-OHT1
|
Electricity Connection Pending
|
20-Feb-2024
|
15-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
45
|
Kushi Nagar
|
NCC Ltd.
|
SISWA GOPAL
|
Siswa Gopal
|
20050914-OHT1
|
Electricity Connection Pending
|
20-Feb-2024
|
15-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
46
|
Kushi Nagar
|
NCC Ltd.
|
BRINDABAN
|
Brindaban
|
20040280-OHT1
|
Electricity Connection Pending
|
20-Feb-2024
|
15-Sep-2026
|
Resolved
|
Electrical Connection Pending
|
|
47
|
Kushi Nagar
|
NCC Ltd.
|
GANGRAI
|
Gangrai
|
20102428-OHT1
|
Electricity Connection Pending
|
20-Feb-2024
|
15-Sep-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
48
|
Kushi Nagar
|
NCC Ltd.
|
VIJAIPUR
|
Vijaipur
|
20051261-OHT1
|
Electricity Connection Pending
|
20-Feb-2024
|
10-Oct-2026
|
Resolved
|
electricity connection pending yet.
|
|
49
|
Kushi Nagar
|
NCC Ltd.
|
PADRI MEHDIA
|
Padri Mehdia
|
20101619-OHT1
|
Electricity Connection Pending
|
16-Feb-2024
|
25-Sep-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
50
|
Kushi Nagar
|
NCC Ltd.
|
KUCHAYA RO
|
KUCHAYA
|
20098937-OHT1
|
Electricity Connection Pending
|
16-Feb-2024
|
10-Sep-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
51
|
Kushi Nagar
|
NCC Ltd.
|
RAHASUJANUBI PATTI R
|
Rahasujanubi Patti
|
20098931-OHT1
|
Electricity Connection Pending
|
16-Feb-2024
|
15-Sep-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
52
|
Kushi Nagar
|
NCC Ltd.
|
CHAKIA SOBHMAL
|
Chakia
|
8388387-OHT1
|
Electricity Connection Pending
|
03-Feb-2024
|
15-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
53
|
Kushi Nagar
|
NCC Ltd.
|
PARSADPUR
|
Parsadpur
|
20101605-OHT1
|
Electricity Connection Pending
|
03-Feb-2024
|
10-Nov-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
54
|
Kushi Nagar
|
NCC Ltd.
|
BIRWAT KOMWALIA R
|
Birwat Komwalia
|
20098928-OHT1
|
Electricity Connection Pending
|
03-Feb-2024
|
15-Oct-2026
|
Resolved
|
Electricty Connection not done Yet.
|
|
55
|
Lucknow
|
NCC Ltd.
|
Narendi Water Supply Scheme
|
Narendi
|
20070143/01
|
Electricity Connection Pending
|
25-Mar-2026
|
-
|
Resolved
|
Due to Non Providing of Estimate, we are unable to supply the water to villages
|
|
56
|
Lucknow
|
NCC Ltd.
|
Dedhari, Rampur Garhi Jamuni & Bramhdas Pur
|
Bramhedas Pur
|
20070391/01
|
Electricity Connection Pending
|
20-Mar-2026
|
-
|
Resolved
|
Due to Non Providing of Electricity power, we are unable to supply the water to villages
|
|
57
|
Lucknow
|
NCC Ltd.
|
Lonha
|
Lonha
|
8360588/01
|
Electricity Connection Pending
|
06-Mar-2026
|
-
|
Resolved
|
Due to Non Providing of Estimate, we are unable to supply the water to villages
|
|
58
|
Lucknow
|
NCC Ltd.
|
Papnamau
|
Papnamau
|
20015648/01
|
Electricity Connection Pending
|
03-Mar-2026
|
-
|
Resolved
|
Due to Non Providing of Estimate, we are unable to supply the water to villages
|
|
59
|
Lucknow
|
NCC Ltd.
|
Bhadeshwa & Dhanuwa Sand
|
Bhadeshwa
|
20070387/01
|
Electricity Connection Pending
|
13-Feb-2026
|
-
|
Resolved
|
Due to Non Providing of Electricity power, we are unable to supply the water to villages.
|
|
60
|
Lucknow
|
NCC Ltd.
|
Pahiaajampur
|
Pahiaajampur
|
20070064/01
|
Electricity Connection Pending
|
07-Feb-2026
|
-
|
Resolved
|
Due to Non Providing of Estimate, we are unable to supply the water to villages
|
|
61
|
Rampur
|
SPML Infra
|
BALPURA VILL W/S SCHEME
|
Balpura
|
20096263
|
Electricity Connection Pending
|
04-Aug-2026
|
-
|
Resolved
|
Pending after TC amount deposited to UPPCL
|