1
|
Shahjahanpur
|
NCC Ltd.
|
KHIRIA RATAN
|
Khiria Ratan
|
20016531/01
|
NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL)
|
14-Aug-2026
|
30-Jun-2028
|
Pending
|
NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
|
|
2
|
Shahjahanpur
|
NCC Ltd.
|
Sikenderpur afganan
|
Sikenderpur Afgnan
|
20018427/01
|
NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL)
|
14-Aug-2026
|
30-Jun-2028
|
Pending
|
NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
|
|
3
|
Shahjahanpur
|
NCC Ltd.
|
SIRKHIRI & BHARTAPUR WSS
|
Bhartapur
|
20058392/01
|
NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL)
|
14-Aug-2026
|
30-Jun-2028
|
Pending
|
NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
|
|
4
|
Shahjahanpur
|
NCC Ltd.
|
AMANPUR WSS
|
Amanpur
|
20071368/01
|
NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL)
|
14-Aug-2026
|
30-Jun-2028
|
Pending
|
NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
|
|
5
|
Shahjahanpur
|
NCC Ltd.
|
CHAUKHUTIA & KAKRALA & ATIWARA WSS
|
Kakrala
|
20073329/01
|
NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL)
|
14-Aug-2026
|
30-Jun-2028
|
Pending
|
NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
|
|
6
|
Shahjahanpur
|
NCC Ltd.
|
ABHAIN & BARUA BUZURG MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME
|
Abhain
|
20084188/01
|
NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL)
|
14-Aug-2026
|
30-Jun-2028
|
Pending
|
NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
|
|
7
|
Shahjahanpur
|
NCC Ltd.
|
ATHKONA & RAMPUR KALAN & RAUTAPUR KALAN MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME
|
Madhaupur
|
20084322/01
|
NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL)
|
14-Aug-2026
|
30-Jun-2028
|
Pending
|
NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
|
|
8
|
Shahjahanpur
|
NCC Ltd.
|
KEWAL RAMPUR CHILAUA, KOYALAGYANPUR, RAMPUR MULTI GP WSS
|
Kewal Rampur Chilaua
|
20089062/01
|
NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL)
|
14-Aug-2026
|
30-Jun-2028
|
Pending
|
NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
|
|
9
|
Shahjahanpur
|
NCC Ltd.
|
KUTUAPUR ELAQUA SAHERAMAU GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME
|
Kutuapur Elaqua Saheramau
|
20096533/01
|
NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL)
|
14-Aug-2026
|
30-Jun-2028
|
Pending
|
NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
|
|
10
|
Shahjahanpur
|
NCC Ltd.
|
PATNA WSS
|
Patna
|
20078973/01
|
NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL)
|
14-Aug-2026
|
30-Jun-2028
|
Pending
|
NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
|
|
11
|
Shahjahanpur
|
NCC Ltd.
|
FIROZPUR GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME
|
Vilhara
|
20084338/01
|
NOC Pending (NHAI/Railway/Forest/Irrigation/State Highway/IOCL/IGL/HPCL/UPEIDA/UPPCL/GAIL)
|
14-Aug-2026
|
30-Jun-2028
|
Pending
|
NOCs from NHAI is pending , it take additional time to get cleared. Therefore, additional time is required for the completion of the scheme
|
|
12
|
Shahjahanpur
|
NCC Ltd.
|
DADIURA & NIYAMATPUR MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME
|
Dadiura
|
20084170/01
|
Water Logged / Flood-Prone Area / Natural Calamity
|
05-Aug-2026
|
30-Oct-2028
|
Pending
|
The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme
|
|
13
|
Shahjahanpur
|
NCC Ltd.
|
VIKRAMPUR CHAKAURA Nigohi W/s
|
Vikrampur Chakaura
|
20015058/01
|
Water Logged / Flood-Prone Area / Natural Calamity
|
05-Aug-2026
|
31-Oct-2028
|
Pending
|
The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme
|
|
14
|
Shahjahanpur
|
NCC Ltd.
|
Dhubla Karimnagar
|
Dhuvla Karimnagar
|
20019783/01
|
Water Logged / Flood-Prone Area / Natural Calamity
|
05-Aug-2026
|
30-Jun-2028
|
Pending
|
The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme
|
|
15
|
Shahjahanpur
|
NCC Ltd.
|
BENIPUR WSS
|
Benipur
|
20058760/01
|
Land Dispute / Litigation
|
05-Aug-2026
|
30-Jun-2028
|
Pending
|
Local issues of land dispute is there, Therefore, additional time is required to resolve the issue and complete the scheme.
|
|
16
|
Shahjahanpur
|
NCC Ltd.
|
DOSHPUR THOK GRAM PANCHAYAT WATER SUPPLY SCHEME
|
Doshpur Thok
|
20101596/01
|
Saline Water / Poor Water Source(Salinity/Fluoride/Iron)
|
05-Aug-2026
|
30-Jun-2028
|
Pending
|
Tubewell has been drilled once/ twice/thrice, saline water was encountered. Additional land is required for another bore and acquisition of the same is under process therefore. additional time is required for the completion of the scheme
|
|
17
|
Shahjahanpur
|
NCC Ltd.
|
JAITIPUR GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME
|
Jaitipur
|
8361729/01
|
Water Logged / Flood-Prone Area / Natural Calamity
|
05-Aug-2026
|
31-Oct-2028
|
Pending
|
The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme
|
|
18
|
Shahjahanpur
|
NCC Ltd.
|
VAIDAPUR MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME
|
Paidapur
|
20084382/01
|
Water Logged / Flood-Prone Area / Natural Calamity
|
05-Aug-2026
|
31-Oct-2028
|
Resolved
|
The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme
|
|
19
|
Shahjahanpur
|
NCC Ltd.
|
VAIDAPUR MULTI GRAM PANCHAYAT MULTI VILLAGE WATER SUPPLY SCHEME
|
Paidapur
|
20084382/01
|
Water Logged / Flood-Prone Area / Natural Calamity
|
05-Aug-2026
|
30-Jun-2028
|
Pending
|
The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme
|
|
20
|
Shahjahanpur
|
NCC Ltd.
|
BEHTI GP MULTI VILLAGE WSS
|
Behti
|
20093768/01
|
Land Dispute / Litigation
|
05-Aug-2026
|
31-Oct-2028
|
Pending
|
A legal dispute concerning the land for the water works is pending. Therefore, additional time is required for the completion of the scheme.
|
|
21
|
Shahjahanpur
|
NCC Ltd.
|
SITHARA GP MULTI VILLAGE WSS
|
Sithara
|
20093790/01
|
Public Hindrance / Local Hindrance
|
05-Aug-2026
|
30-Jun-2028
|
Pending
|
Local issues of land dispute is there, Therefore, additional time is required to resolve the issue and complete the scheme.
|
|
22
|
Shahjahanpur
|
NCC Ltd.
|
RAMPUR GP WSS
|
Rampur
|
20099668/01
|
Water Logged / Flood-Prone Area / Natural Calamity
|
05-Aug-2026
|
31-Oct-2028
|
Pending
|
The scheme area is waterlogged and/or located in a flood-prone area. Consequently, the progress of the work will be hampered during the rainy season/flood. Therefore, additional time is required for the completion of the scheme
|
|
23
|
Shahjahanpur
|
NCC Ltd.
|
MAU VASAK GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME
|
Mau Vasak
|
20096496/01
|
Land Dispute / Litigation
|
05-Aug-2026
|
30-Jun-2028
|
Pending
|
A legal dispute concerning the land for the water works is pending. Therefore, additional time is required for the completion of the scheme.
|
|
24
|
Shahjahanpur
|
NCC Ltd.
|
SHAHVEGNAGAR GRAM PANCHAYAT VILLAGE WATER SUPPLY SCHEME
|
Shahvegpur
|
20097898/01
|
Public Hindrance / Local Hindrance
|
05-Aug-2026
|
31-Oct-2027
|
Pending
|
Local issues of land dispute is there, Therefore, additional time is required to resolve the issue and complete the scheme.
|