| 1 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424226 |
Arjar |
Road Widening[PWD] |
12-Jan-2024 |
|
PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi.
Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm.
Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter.
Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. The work is currently in progress.
The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026. |
| 2 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Arjar |
424227 |
Rampura |
Road Widening[PWD] |
16-Jan-2024 |
|
PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi.
Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm.
Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter.
Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. Water supply has been started partially and the work is currently in progress.
The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026. |
| 3 |
8010037 |
Kuraicha GOV |
Jhansi |
Bangra |
Ninaura |
424230 |
Ninaura |
Road Widening[PWD] |
10-Jan-2024 |
|
PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi.
Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm.
Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter.
Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. Repair woks will be started in this village after completion of works at Arjar & Rampura Villages
The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026. |