Regular Water Supply Supply Disruptions

Sr No. Scheme Code Scheme Name District Block Panchayat Village Code Village Issue Type Issue Date Expected Issue Resolve Date Remark
1 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 01-Jul-2026 PWD has damaged the pipeline from last 2.5 years. Work started on 01-05-2026 due to the intervention of ACS sir and DM Jhansi. However the same has been stopped due to rainy season.
2 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 01-Jul-2026 PWD Repairing work stopped due to rainy season
3 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 01-May-2026 PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD.
4 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 01-May-2026 PWD has started attending repairs after intervention of DM Jhansi
5 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 12-Jan-2024 Pwd has damaged the pipeline from last 1.5 years and not repaired it till now.
6 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 12-Jan-2024 PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD on 01-05-2026. However, the work has been stopped due to rainy season for two months. Due to the intervention of MD-UPJN and DM Jhansi on 01-09-2026 work re-started. The completion date will be finalised during the meeting called by DM Jhansi on 23-09-2026.
7 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 12-Jan-2024 PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm. Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. The work is currently in progress. The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026.
8 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 12-Jan-2024 31-Oct-2026 PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm. Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. The work is currently in progress. The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026.In this meeting DM has directed to PWD remaining works would be completed as soon as possible.In complaince PWD stated that the remaining works will take 1 month for complaince .
9 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 12-Jan-2024 1. PWD has damaged the pipe line during road widening in 2024. and the issue has remained unresolved. 2. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi. 3. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. 4. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm. 5. Accordingly, PWD started the work on 01.05.2026. 6. The work was stopped due to the rainy season and was not resumed thereafter. 7. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. But, once again stopped by PWD from 20.09.2026. 8. In the meeting convened by the DM, Jhansi, on 23.09.2026, DM directed PWD to complete remaining works immediately. PWD stated that the remaining works will be completed by 15.10.2026. 9. However, thereafter, the work has not been resumed and no work is in progress at present.
10 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 12-Jan-2024

The pipeline repair work in Village Arjar remains incomplete, resulting in the continued disruption of the full water supply to the village and causing inconvenience to the residents.


Key Details and Timeline


2024: The Public Works Department (PWD) damaged the pipeline during road-widening work.


May 1, 2026: The PWD commenced repair work under the supervision of UPJN but subsequently stopped the work due to the rainy season.


September 1, 2026: Work resumed following the intervention of the District Magistrate (DM), Jhansi. However, the PWD stopped the work again on September 20, 2026.


September 23, 2026: The DM directed the PWD to complete the work immediately, and the PWD assured completion by October 15, 2026.


Current Status (as of October 16, 2026)


Approximately 600 metres of 150 mm DI pipeline, 2,000 metres of 50 mm GI pipeline, and the required interconnections remain incomplete. The water supply to the village has not been restored.


Despite the assurance given by the PWD to complete the work by October 15, 2026, the stipulated deadline has expired, and no repair work is currently in progress at the site

11 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 12-Jan-2024

The pipeline repair work in Village Arjar remains incomplete, resulting in the continued disruption of the full water supply to the village and causing inconvenience to the residents.Key Details and Timeline2024: The Public Works Department (PWD) damaged the pipeline during road-widening work.May 1, 2026: The PWD commenced repair work under the supervision of UPJN but subsequently stopped the work due to the rainy season.September 1, 2026: Work resumed following the intervention of the District Magistrate (DM), Jhansi. However, the PWD stopped the work again on September 20, 2026.September 23, 2026: The DM directed the PWD to complete the work immediately, and the PWD assured completion by October 15, 2026.Current Status (as of October 16, 2026).Approximately 600 metres of 150 mm DI pipeline, 2,000 metres of 50 mm GI pipeline, and the required interconnections remain incomplete. The water supply to the village has not been restored.Despite the assurance given by the PWD to complete the work by October 15, 2026, the stipulated deadline has expired, and no repair work is currently in progress at the site.


12 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 12-Jan-2024

The pipeline repair work in Village Arjar remains incomplete, resulting in the continued disruption of the full water supply to the village and causing inconvenience to the residents.Key Details and Timeline2024: The Public Works Department (PWD) damaged the pipeline during road-widening work.May 1, 2026: The PWD commenced repair work under the supervision of UPJN but subsequently stopped the work due to the rainy season.September 1, 2026: Work resumed following the intervention of the District Magistrate (DM), Jhansi. However, the PWD stopped the work again on September 20, 2026.September 23, 2026: The DM directed the PWD to complete the work immediately, and the PWD assured completion by October 15, 2026.Current Status (as of October 16, 2026).Approximately 600 metres of 150 mm DI pipeline, 2,000 metres of 50 mm GI pipeline, and the required interconnections remain incomplete. The water supply to the village has not been restored. Despite the assurance given by the PWD to complete the work by October 15, 2026, the stipulated deadline has expired, and no repair work is currently in progress at the site.

13 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 12-Jan-2024

The pipeline repair work in Village Arjar remains incomplete, resulting in the continued disruption of the full water supply to the village and causing inconvenience to the residents.Key Details and Timeline2024: The Public Works Department (PWD) damaged the pipeline during road-widening work.May 1, 2026: The PWD commenced repair work under the supervision of UPJN but subsequently stopped the work due to the rainy season.September 1, 2026: Work resumed following the intervention of the District Magistrate (DM), Jhansi. However, the PWD stopped the work again on September 20, 2026.September 23, 2026: The DM directed the PWD to complete the work immediately, and the PWD assured completion by October 15, 2026.Current Status (as of October 16, 2026).Approximately 600 metres of 150 mm DI pipeline, 2,000 metres of 50 mm GI pipeline, and the required interconnections remain incomplete. The water supply to the village has not been restored. Despite the assurance given by the PWD to complete the work by October 15, 2026, the stipulated deadline has expired, and no repair work is currently in progress at the site.

14 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 12-Jan-2024

PWD damaged the pipeline during road widening in 2024. Despite work commencing on 01.05.2026 and the DM, Jhansi’s direction dated 23.09.2026 to complete it by 15.10.2026, the work remains incomplete and has stopped again. Approximately 600 m of 150 mm DI pipeline, 2,000 m of 50 mm GI pipeline, and interconnections are pending

15 8010037 Kuraicha GOV Jhansi Bangra Arjar 424226 Arjar Road Widening[PWD] 19-Sep-2026 PWD-damaged pipeline has remained unresolved for the last 1.5 years. Repair work is now in progress. DM meeting is scheduled on 23-09-2026 with PWD officers for review.