Sr No. Scheme Code Scheme Name District Block Panchayat Village Code Village Issue Type Issue Date Expected Issue Resolve Date Remark
1 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 01-Jul-2026 PWD has damaged the pipeline from last 2.5 years. Work started on 01-05-2026 due to the intervention of ACS sir and DM Jhansi. However the same has been stopped due to rainy season.
2 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 01-May-2026 PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD at Arjar and Rampura. Work at Ninaura will be started after completion of above two villages.
3 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 10-Jan-2024 Pwd has damaged the pipeline from last 1.5 years and still not repaired it till now.
4 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 10-Jan-2024 PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD on 01-05-2026. However the work has been stopped due to rainy season for two months. Due to the intervention of MD-UPJN and DM Jhansi on 01-09-2026. Work at Ninaura will be started after completion of water supply to Arjar & Rampura. The completion date will be finalised during the meeting called by DM Jhansi on 23-09-2026.
5 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 10-Jan-2024 PWD has damaged the pipeline from last 2.5 years. As per the instruction of ACS sir, joint meeting was conducted by DM Jhansi. There after joint site inspection was conducted by CE- UPJN and CE- PWD and there after work has been started by PWD on 01-05-2026. However the work has been stopped due to rainy season for two months. Due to the intervention of MD-UPJN and DM Jhansi on 01-09-2026 work at Arjar & Rampura started. Work at Ninaura will be started after completion of water supply to above two villages. The completion date will be finalised during the meeting called by DM Jhansi on 23-09-2026.
6 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 10-Jan-2024 PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm. Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. Repair woks will be started in this village after completion of works at Arjar & Rampura Villages The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026.
7 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 10-Jan-2024 31-Oct-2026 PWD has damaged the pipeline, and the issue has remained unresolved for the last 2.5 years. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm. Accordingly, PWD started the work on 01.05.2026. However, the work was stopped due to the rainy season and was not resumed thereafter. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. The work is currently in progress. The completion date will be finalized during the meeting convened by the DM, Jhansi, on 23.09.2026.In this meeting DM has directed to PWD remaining works would be completed as soon as possible.In complaince PWD stated that the remaining works will take 1 month for complaince .
8 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 10-Jan-2024 1. PWD has damaged the pipe line during road widening in 2024. and the issue has remained unresolved. 2. After the intervention of the ACS Sir, a joint meeting of both departments was conducted by the DM, Jhansi. 3. Thereafter, a joint site inspection was carried out by the Chief Engineer (CE), UPJN, and CE, PWD. 4. It was mutually agreed that the pipeline-laying work would be carried out by PWD under the supervision of UPJN and the firm. 5. Accordingly, PWD started the work on 01.05.2026. 6. The work was stopped due to the rainy season and was not resumed thereafter. 7. Following the intervention of the MD sir - UPJN (R), the DM - Jhansi, convened a meeting with both departments, and the work was resumed on 01.09.2026. But, once again stopped by PWD from 20.09.2026. 8. In the meeting convened by the DM, Jhansi, on 23.09.2026, DM directed PWD to complete remaining works immediately. PWD stated that the remaining works will be completed by 15.10.2026. 9. However, thereafter, the work has not been resumed and no work is in progress at present.
9 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 10-Jan-2024

The pipeline work in Village Ninaura remains incomplete, resulting in the non-restoration of the full water supply to the village.


Key Details and Timeline

2024: The Public Works Department (PWD) damaged the pipeline during road-widening work.

May 1, 2026: The PWD commenced repair work under the supervision of UPJN but subsequently stopped the work due to the rainy season.

September 1, 2026: Work resumed following the intervention of the District Magistrate (DM), Jhansi. However, the PWD stopped the work again on September 20, 2026.

September 23, 2026: The DM directed the PWD to complete the work immediately, and the PWD assured completion by October 15, 2026.

Current Status (as of October 16, 2026)

The 150 mm diameter pipeline gap-closing work between Rampura and Arjar villages remains incomplete. The pending pipeline connection is essential to ensure that water reaches Village Ninaura and to restore the full water supply. Despite the assurance given by the PWD, the stipulated completion date of October 15, 2026, has passed, and no work is currently in progress at the site.

10 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 10-Jan-2024

The pipeline work in Village Ninaura remains incomplete, resulting in the non-restoration of the full water supply to the village.Key Details and Timeline2024: The Public Works Department (PWD) damaged the pipeline during road-widening work.May 1, 2026: The PWD commenced repair work under the supervision of UPJN but subsequently stopped the work due to the rainy season.September 1, 2026: Work resumed following the intervention of the District Magistrate (DM), Jhansi. However, the PWD stopped the work again on September 20, 2026.September 23, 2026: The DM directed the PWD to complete the work immediately, and the PWD assured completion by October 15, 2026.Current Status (as of October 16, 2026)The 150 mm diameter pipeline gap-closing work between Rampura and Arjar villages remains incomplete. The pending pipeline connection is essential to ensure that water reaches Village Ninaura and to restore the full water supply. Despite the assurance given by the PWD, the stipulated completion date of October 15, 2026, has passed, and no work is currently in progress at the site.


11 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 10-Jan-2024

The pipeline work in Village Ninaura remains incomplete, resulting in the non-restoration of the full water supply to the village.Key Details and Timeline2024: The Public Works Department (PWD) damaged the pipeline during road-widening work.May 1, 2026: The PWD commenced repair work under the supervision of UPJN but subsequently stopped the work due to the rainy season.September 1, 2026: Work resumed following the intervention of the District Magistrate (DM), Jhansi. However, the PWD stopped the work again on September 20, 2026.September 23, 2026: The DM directed the PWD to complete the work immediately, and the PWD assured completion by October 15, 2026.Current Status (as of October 16, 2026)The 150 mm diameter pipeline gap-closing work between Rampura and Arjar villages remains incomplete. The pending pipeline connection is essential to ensure that water reaches Village Ninaura and to restore the full water supply. Despite the assurance given by the PWD, the stipulated completion date of October 15, 2026, has passed, and no work is currently in progress at the site.

12 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 10-Jan-2024

The pipeline work in Village Ninaura remains incomplete, resulting in the non-restoration of the full water supply to the village.Key Details and Timeline2024: The Public Works Department (PWD) damaged the pipeline during road-widening work.May 1, 2026: The PWD commenced repair work under the supervision of UPJN but subsequently stopped the work due to the rainy season.September 1, 2026: Work resumed following the intervention of the District Magistrate (DM), Jhansi. However, the PWD stopped the work again on September 20, 2026.September 23, 2026: The DM directed the PWD to complete the work immediately, and the PWD assured completion by October 15, 2026.Current Status (as of October 16, 2026)The 150 mm diameter pipeline gap-closing work between Rampura and Arjar villages remains incomplete. The pending pipeline connection is essential to ensure that water reaches Village Ninaura and to restore the full water supply. Despite the assurance given by the PWD, the stipulated completion date of October 15, 2026, has passed, and no work is currently in progress at the site.

13 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 10-Jan-2024

The pipeline was damaged by the PWD during road-widening work in 2024. Despite repair work commencing on 01.05.2026 and the DM, Jhansi’s directions dated 23.09.2026 to complete the work by 15.10.2026, the 150 mm dia. pipeline gap-closing work between Rampura and Arjar remains incomplete. Work has been stopped since 20.09.2026, and the full water supply to Village Ninaura has not been restored.

14 8010037 Kuraicha GOV Jhansi Bangra Ninaura 424230 Ninaura Road Widening[PWD] 19-Sep-2026 Pwd has damaged the pipeline from last 1.5 years and still not repaired it till now.