| Sr No. | Scheme Code | Scheme Name | District | Block | Panchayat | Village Code | Village | Issue Type | Issue Date | Expected Issue Resolve Date | Remark |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 8152383 | Dhawarra GOV | Mahoba | Jyotpur | Akauna | 425866 | Akauni | Theft | 01-Aug-2025 | 15-Aug-2025 | Solar Panel with Battery Theft along with Cables. |
| 2 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Chandao | 426020 | Chandao | Road Widening[NHAI] | 02-Feb-2026 | 15-Oct-2026 | Pipe line damaged during road widening |
| 3 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Chandao | 426020 | Chandao | Road Widening[NHAI] | 02-Feb-2026 | 05-Oct-2026 | Meetings held with ADM/XEN Sir with NHAI PM. He assured repairing with in 2 week time. |
| 4 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Mirtala | 426041 | Rahelia | Local Repairing | 02-Feb-2026 | 10-Mar-2026 | trauma center Contractor damaged Pipe Line and shifting work is in progress |
| 5 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426047 | Pachpahara | Local Repairing | 02-Feb-2026 | 10-Mar-2026 | trauma center Contractor damaged Pipe Line and shifting work is in progress. |
| 6 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426047 | Pachpahara | Road Widening[NHAI] | 02-Feb-2026 | 30-Sep-2026 | Damaged by NHAI during road widening |
| 7 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426047 | Pachpahara | Road Widening[NHAI] | 02-Feb-2026 | 05-Oct-2026 | Meetings held with ADM/XEN Sir with NHAI PM. He assured repairing with in 2 week time. |
| 8 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Majhalwara | 426050 | Majhalwara | Road Widening[NHAI] | 05-Jan-2026 | 09-Jan-2026 | Pipe line damaged by NHAI contractor |
| 9 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426047 | Pachpahara | Road Widening[NHAI] | 05-Oct-2025 | 12-Nov-2026 | Meetings held with ADM/XEN Sir with NHAI PM. He assured repairing with in 2 week time. |
| 10 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Bilkhi | 426067 | Bilkhi | Theft | 06-Aug-2025 | 31-Aug-2025 | Battery Theft |
| 11 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Chandao | 426021 | Chand Pura | Theft | 09-Oct-2025 | 25-Oct-2025 | Battery Theft |
| 12 | 8152383 | Dhawarra GOV | Mahoba | Jyotpur | Akauna | 425866 | Akauni | Theft | 10-Oct-2025 | 25-Oct-2025 | Battery along with solar panel theft |
| 13 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Dhikwaha | 426073 | Dhikwaha | Theft | 11-Aug-2025 | 31-Aug-2025 | Battery Theft |
| 14 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426045 | Bania Tala Mahanpura | Road Widening[Other] | 11-Oct-2025 | 31-Oct-2025 | Pipe Line damaged due to Road widening (Electrical Pole Shifting) |
| 15 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Mirtala | 426041 | Rahelia | Road Widening[Other] | 11-Oct-2025 | 31-Oct-2025 | Pipe Line damaged due to Road widening (Electrical Pole Shifting) |
| 16 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426047 | Pachpahara | Road Widening[Other] | 11-Oct-2025 | 31-Oct-2025 | Pipe Line damaged due to Road widening (Electrical Pole Shifting) |
| 17 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426047 | Pachpahara | Theft | 14-Aug-2025 | 31-Aug-2025 | Battery Theft |
| 18 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Mirtala | 426041 | Rahelia | Road Widening[RES] | 15-Jul-2026 | 05-Nov-2026 | Trauma center Contractor damaged Pipe Line. |
| 19 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Mirtala | 426041 | Rahelia | Road Widening[NHAI] | 15-Jul-2026 | 05-Oct-2026 | Meetings held with ADM/XEN Sir with NHAI PM. He assured repairing with in 2 week time. |
| 20 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Mirtala | 426041 | Rahelia | Road Widening[NHAI] | 15-Jul-2026 | 04-Nov-2026 | Meetings held with ADM/XEN Sir with NHAI PM. He assured repairing with in 2 week time. |
| 21 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Pawa | 426048 | Pawa | Road Widening[Other] | 19-Feb-2026 | 11-Feb-2026 | Pipeline damaged by road widening |
| 22 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Pawa | 426049 | Murani | Road Widening[PWD] | 22-Feb-2026 | 08-Oct-2026 | Pipe line Pipeline damaged during road widening |
| 23 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Pawa | 426048 | Pawa | Road Widening[PWD] | 22-Jan-2026 | 08-Oct-2026 | Pipe line Pipeline damaged during road widening |
| 24 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Pawa | 426048 | Pawa | Road Widening[PWD] | 22-Jan-2026 | 16-Nov-2026 | Pipe line Pipeline damaged during road widening |
| 25 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Pawa | 426049 | Murani | Road Widening[Other] | 22-Jan-2026 | 10-Feb-2026 | Pipe lim ne Pipeline damaged by road widening |
| 26 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Chandao | 426020 | Chandao | Road Widening[NHAI] | 27-Oct-2026 | 04-Nov-2026 | Meetings held with ADM/XEN Sir with NHAI PM. He assured repairing with in 2 week time. |
| 27 | 8152383 | Dhawarra GOV | Mahoba | Jyotpur | Mudhari | 425801 | Mudhari | Theft | 28-Jul-2025 | 20-Aug-2025 | EMF Meter cable theft, due to cable cut at last point of EMF meter we were unable reconnect with new cable and we need to install with another EMF Meter. |
| 28 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Dhikwaha | 426073 | Dhikwaha | Theft | 28-Jul-2025 | 05-Aug-2025 | EMF Meter Cable theft. |
| 29 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426047 | Pachpahara | Local Repairing | 30-Jul-2025 | 31-Aug-2025 | NH Contractor damaged pipeline and rectification work is in progress. |
| 30 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Chandao | 426021 | Chand Pura | Local Repairing | 30-Jul-2025 | 03-Aug-2025 | NH Contractor damaged pipeline and rectification work is in progress. |
| 31 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Mirtala | 426041 | Rahelia | Local Repairing | 30-Jul-2025 | 31-Aug-2025 | NH Contractor damaged pipeline and rectification work is in progress. |
| 32 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Mirtala | 426041 | Rahelia | Road Widening[Other] | 30-Jul-2025 | 30-Sep-2025 | Damaged due to road widening |
| 33 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Mirtala | 426042 | Bamhaori Gusai | Local Repairing | 30-Jul-2025 | 02-Aug-2025 | NH Contractor damaged pipe Line and rectification work is in progress |
| 34 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426045 | Bania Tala Mahanpura | Local Repairing | 30-Jul-2025 | 02-Aug-2025 | NH Contractor damaged Pipe Line and repair work is in progress. |
| 35 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426045 | Bania Tala Mahanpura | Local Repairing | 30-Jul-2025 | 31-Aug-2025 | NH Contractor damaged pipeline and rectification work is in progress. |
| 36 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426045 | Bania Tala Mahanpura | Road Widening[Other] | 31-Jul-2025 | 30-Sep-2025 | Damaged due to road widening |
| 37 | 8152383 | Dhawarra GOV | Mahoba | Kabrai (mahoba) | Raipura Kalan | 426047 | Pachpahara | Road Widening[Other] | 31-Jul-2025 | 30-Sep-2025 | Damaged due to road widening |