| 1 | 
                                    8134904 | 
                                    Amlikaur GOV and Tubewell Scheme 28 Nos. | 
                                    OHT-5 | 
                                    Banda | 
                                    Badokhar Khurd | 
                                    Goyara Mugali | 
                                    426284 | 
                                    Goyara Mugali | 
                                    Power/Electrical Issue | 
                                    30-Jul-2025 | 
                                    31-Jul-2025 | 
                                    Due to heavy rain, Network Issue | 
                                
                                
                                    | 2 | 
                                    8134904 | 
                                    Amlikaur GOV and Tubewell Scheme 28 Nos. | 
                                    OHT-5 | 
                                    Banda | 
                                    Badokhar Khurd | 
                                    Goyara Mugali | 
                                    426284 | 
                                    Goyara Mugali | 
                                    Power/Electrical Issue | 
                                    31-Aug-2025 | 
                                    01-Sep-2025 | 
                                    yesterday data  could not be updated on the jjm portal due to power outages at wtp | 
                                
                                
                                    | 3 | 
                                    8134904 | 
                                    Amlikaur GOV and Tubewell Scheme 28 Nos. | 
                                    OHT-5 | 
                                    Banda | 
                                    Badokhar Khurd | 
                                    Goyara Mugali | 
                                    426284 | 
                                    Goyara Mugali | 
                                    Power/Electrical Issue | 
                                    04-Sep-2025 | 
                                    05-Sep-2025 | 
                                    water is being physically supplied but due to power outages at the wate treatment plant(WTP) The actual water supply data has not been updated at JJM Portal | 
                                
                                
                                    | 4 | 
                                    8134904 | 
                                    Amlikaur GOV and Tubewell Scheme 28 Nos. | 
                                    OHT-5 | 
                                    Banda | 
                                    Badokhar Khurd | 
                                    Goyara Mugali | 
                                    426284 | 
                                    Goyara Mugali | 
                                    Power/Electrical Issue | 
                                    02-Oct-2025 | 
                                    03-Oct-2025 | 
                                    33 KV Power outage from wtp and intake well locations |