Generated on: 21/06/2026 04:02 AM
| District Name | Aligarh | Agnecy Name | Pravin Electrical PVT |
|---|---|---|---|
| Scheme ID | 4681105 | Scheme Name | Rehsupur Water Supply Scheme |
| Population Base Year | 2025 | Population Design Year | 2055 |
| Base Year Population | 2440 | Design Year Population | 4850 |
| OHT New | OHT New (Capacity in KL) | OHT New (Staging in m) | OHT New (Cost in m) |
|---|---|---|---|
| No data available | |||
| OHT Old (Repair) | OHT Old (Capacity in KL) | OHT Old (Staging in m) | OHT Old (Cost in m) |
|---|---|---|---|
| OHT-1 | 125.00 | 12.00 | 3.75 |
| Tubewell New | Tubewell New (Discharge in LPM) | Tubewell New (Cost in Lakhs) |
|---|---|---|
| No data available | ||
| Tubewell Old (Repair) | Tubewell Old Repair (Discharge in LPM) | Tubewell Old Repair (Cost in Lakhs) |
|---|---|---|
| No data available | ||
| Tubewell Old (Rebore) | Tubewell Old (Discharge in LPM) | Tubewell Old Ribore (Cost in Lakhs) |
|---|---|---|
| No data available | ||
| PUMP HOUSE New | PUMP HOUSE New (Cost in Lakhs) |
|---|---|
| No data available | |
| PUMP HOUSE Old (Repair) | PUMP HOUSE Old Repair (Cost in Lakhs) |
|---|---|
| PUMP HOUSE-1 | 1.04 |
| Staff Quarter New | Staff Quarter New (Cost in Lakhs) |
|---|---|
| No data available | |
| Staff Quarter Old (Repair) | Staff Quarter Old Repair (Cost in Lakhs) |
|---|---|
| No data available | |
| Boundary Wall New | Boundary Wall New (Cost in Lakhs) |
|---|---|
| No data available | |
| Boundary Wall Old (Repair) | Boundary Wall Old Repair (Cost in Lakhs) |
|---|---|
| Boundary Wall-1 | 3.35 |
| Pumping Plant New | Pumping Plant New (Discharge in LPM) | Pumping Plant New (Cost in Lakhs) |
|---|---|---|
| No data available | ||
| Pumping Plant Old (Repair) | Pumping Plant Old Repair (Discharge in LPM) | Pumping Plant Old Repair (Cost in Lakhs) |
|---|---|---|
| Pumping Plant-1 | 700.00 | 6.15 |
| Rising Main Material | Rising Main (M) | Rising Main Cost (in lacs) |
|---|---|---|
| No data available | ||
| No's | Cost in Lakhs | |
|---|---|---|
| Total FHTC |
[Formula = Serviceable + Repair + New]
487
|
[Formula = Repair + New Cost]
4.47
|
| Serviceable | 242 | 0 |
| Repair | 170 | 1.70 |
| New | 75 | 2.77 |
| Type Of Roads | Cost in Lakhs |
|---|---|
| Bituminous | 1.14 |
| CC | 11.50 |
| BOE | 0.00 |
| Interlocking | 5.54 |
| Total | 18.18 |
| Campus New | Campus New (Cost in Lakhs) |
|---|---|
| No data available | |
| Campus Old Repair | Campus Old Repair (Cost in Lakhs) |
|---|---|
| No data available | |
| CWR/GLR New | Capacity (in KL) | CWR/GLR New (Cost in Lakhs) |
|---|---|---|
| No data available | ||
| CWR/GLR Old Repair | Capacity (in KL) | CWR/GLR Old Repair (Cost in Lakhs) |
|---|---|---|
| No data available | ||
| Name of Work | Cost in Lakhs |
|---|---|
| No data available | |
| Capacity in Kw | Cost in Lakhs |
|---|---|
| No data available | |
| Departments | Cost in Lakhs |
|---|---|
| Railways | 0.00 |
| PWD/NHIA | 0.00 |
| Forest | 0.00 |
| Irrigation | 0.00 |
| Other | 0.00 |
| Total | 0.00 |