Scheme Information - Print Version

Generated on: 21/06/2026 04:19 AM

Scheme Information

District Name Lalitpur Agnecy Name M/S C.K Enterprises
Scheme ID 4937777 Scheme Name Natthikhera Group of Village water Supply scheme
Population Base Year 2025 Population Design Year 2055
Base Year Population 26396 Design Year Population 44277

OHT Details

1. OHT Details
OHT New OHT New (Capacity in KL) OHT New (Staging in m) OHT New (Cost in m)
No data available
OHT Old (Repair) OHT Old (Capacity in KL) OHT Old (Staging in m) OHT Old (Cost in m)
OHT-1 300.00 18.00 0.66
OHT-2 300.00 16.00 0.66
OHT-3 350.00 16.00 0.66
OHT-4 200.00 14.00 2.32
2. Tubewell
Tubewell New Tubewell New (Discharge in LPM) Tubewell New (Cost in Lakhs)
No data available
Tubewell Old (Repair) Tubewell Old Repair (Discharge in LPM) Tubewell Old Repair (Cost in Lakhs)
No data available
Tubewell Old (Rebore) Tubewell Old (Discharge in LPM) Tubewell Old Ribore (Cost in Lakhs)
No data available
3. PUMP HOUSE
PUMP HOUSE New PUMP HOUSE New (Cost in Lakhs)
No data available
PUMP HOUSE Old (Repair) PUMP HOUSE Old Repair (Cost in Lakhs)
No data available
4. Staff Quarter
Staff Quarter New Staff Quarter New (Cost in Lakhs)
No data available
Staff Quarter Old (Repair) Staff Quarter Old Repair (Cost in Lakhs)
No data available
5. Boundary Wall
Boundary Wall New Boundary Wall New (Cost in Lakhs)
No data available
Boundary Wall Old (Repair) Boundary Wall Old Repair (Cost in Lakhs)
Boundary Wall-1 1.39
Boundary Wall-2 0.69
Boundary Wall-3 0.69
Boundary Wall-4 0.69
6. Pumping Plant
Pumping Plant New Pumping Plant New (Discharge in LPM) Pumping Plant New (Cost in Lakhs)
No data available
Pumping Plant Old (Repair) Pumping Plant Old Repair (Discharge in LPM) Pumping Plant Old Repair (Cost in Lakhs)
Pumping Plant-2 5800.00 3.30
7. Rising Main
Rising Main Material Rising Main (M) Rising Main Cost (in lacs)
No data available
8A Distribution System (Excluding FHTC and Road Works)
91077.00
1.31
799.00
6.45
13503.00
91.39
8B. FHTC
No's Cost in Lakhs
Total FHTC [Formula = Serviceable + Repair + New]
4106
[Formula = Repair + New Cost]
43.68
Serviceable 2336 0
Repair 970 14.55
New 800 29.13
8C. Road Dismantling and Restoration
Type Of Roads Cost in Lakhs
Bituminous 5.95
CC 18.37
BOE
Interlocking 11.62
Total 35.94
8D. Total D/System Cost
Formula: Sum of Distribution System, FHTC, and Road Dismantling costs
178.77
9. Approach Road and Campus Development
Campus New Campus New (Cost in Lakhs)
No data available
Campus Old Repair Campus Old Repair (Cost in Lakhs)
Campus Old-1 2.93
10. For Surface Source Schemes
CWR/GLR New Capacity (in KL) CWR/GLR New (Cost in Lakhs)
No data available
CWR/GLR Old Repair Capacity (in KL) CWR/GLR Old Repair (Cost in Lakhs)
CWR/GLR Old Repair-1 400.00 0.17
CWR/GLR Old Repair-2 100.00 0.17
CWR/GLR Old Repair-3 200.00 0.17
CWR/GLR Old Repair-4 100.00 0.17
11. Chlorination Dozing Pump and Minor Wiring Works
4.02
12. Other Works not listed above
Name of Work Cost in Lakhs
survey 4.60
booster pumphouse 3 no of 10.15
htvcb pannel 11kva 3 phase for intake well 13.84
stabilizer for intake well 150 kva 4.32
solar dual pump for zone 1 11.32
stabilizer for wtp 150 kva 4.32
stabilizer 10 kva for boosterpump 1.26
stabilizer 20 kva for cwr 1.89
solar dual pump 2 no of at zone 3 22.63
booster pumping palnt at zone 3 -600 lpm 3.50
stabilizer for booster pump 10 kva 1.26
stabilzer zone 3- 60 kva 3.39
stabilzer zone 4- 30 kva and cable supply 2.36
booster pump 450 lpm at zone 2 3.00
13. Works Related to other Departments
13.A) New Power Connection and other Appurtenant works
Capacity in Kw Cost in Lakhs
10.00 4.70
25.00 4.75
13.B) NOC Related
Departments Cost in Lakhs
Railways
PWD/NHIA
Forest
Irrigation
Other
Total 0.00

Part A - Work Cost

285.30
5.71
52.38
27.65
9.45
380.48

Part B - Solar Cost

0.00
0.00
0.00
0.00

Part C - Automation Cost

169.79
3.40
31.17
16.45
220.81

Per Capita Cost

Formula = (Work Cost Part A (a+ b + c)) / Population Base
0.0130
Formula = Work Cost Part A(a)
0.0064