| District Name | Prayagraj | Agnecy Name | LC Infra Project Limited |
|---|---|---|---|
| Scheme ID | 5011908 | Scheme Name | PURAB NARA |
| Population Base Year | 2025 | Population Design Year | 2055 |
| Base Year Population | 11109 | Design Year Population | 23427 |
| OHT New | OHT New (Capacity in KL) | OHT New (Staging in m) | OHT New (Cost in m) |
|---|---|---|---|
| OHT-1 | 200.00 | 18.00 | 42.08 |
| OHT Old (Repair) | OHT Old (Capacity in KL) | OHT Old (Staging in m) | OHT Old (Cost in m) |
|---|---|---|---|
| OHT-1 | 350.00 | 13.00 | 5.10 |
| Tubewell New | Tubewell New (Discharge in LPM) | Tubewell New (Cost in Lakhs) |
|---|---|---|
| Tubewell-1 | 1200.00 | 18.68 |
| Tubewell Old (Repair) | Tubewell Old Repair (Discharge in LPM) | Tubewell Old Repair (Cost in Lakhs) |
|---|---|---|
| Tubewell-1 | 1240.00 | 2.10 |
| Tubewell Old (Rebore) | Tubewell Old (Discharge in LPM) | Tubewell Old Ribore (Cost in Lakhs) |
|---|---|---|
| No data available | ||
| PUMP HOUSE New | PUMP HOUSE New (Cost in Lakhs) |
|---|---|
| PUMP HOUSE-1 | 6.36 |
| PUMP HOUSE Old (Repair) | PUMP HOUSE Old Repair (Cost in Lakhs) |
|---|---|
| PUMP HOUSE-1 | 1.01 |
| Staff Quarter New | Staff Quarter New (Cost in Lakhs) |
|---|---|
| No data available | |
| Staff Quarter Old (Repair) | Staff Quarter Old Repair (Cost in Lakhs) |
|---|---|
| No data available | |
| Boundary Wall New | Boundary Wall New (Cost in Lakhs) |
|---|---|
| Boundary Wall-1 | 12.19 |
| Boundary Wall Old (Repair) | Boundary Wall Old Repair (Cost in Lakhs) |
|---|---|
| Boundary Wall-1 | 0.20 |
| Pumping Plant New | Pumping Plant New (Discharge in LPM) | Pumping Plant New (Cost in Lakhs) |
|---|---|---|
| Pumping Plant-1 | 1200.00 | 4.52 |
| Pumping Plant Old (Repair) | Pumping Plant Old Repair (Discharge in LPM) | Pumping Plant Old Repair (Cost in Lakhs) |
|---|---|---|
| Pumping Plant-1 | 1240.00 | 2.94 |
| Rising Main Material | Rising Main (M) | Rising Main Cost (in lacs) |
|---|---|---|
| DI | 65.00 | 1.43 |
| No's | Cost in Lakhs | |
|---|---|---|
| Total FHTC |
[Formula = Serviceable + Repair + New]
1591
|
[Formula = Repair + New Cost]
41.04
|
| Serviceable | 310 | 0 |
| Repair | 293 | 4.96 |
| New | 988 | 36.08 |
| Type Of Roads | Cost in Lakhs |
|---|---|
| Bituminous | 37.88 |
| CC | 18.91 |
| BOE | 14.44 |
| Interlocking | 72.34 |
| Total | 143.57 |
| Campus New | Campus New (Cost in Lakhs) |
|---|---|
| No data available | |
| Campus Old Repair | Campus Old Repair (Cost in Lakhs) |
|---|---|
| No data available | |
| CWR/GLR New | Capacity (in KL) | CWR/GLR New (Cost in Lakhs) |
|---|---|---|
| No data available | ||
| CWR/GLR Old Repair | Capacity (in KL) | CWR/GLR Old Repair (Cost in Lakhs) |
|---|---|---|
| No data available | ||
| Name of Work | Cost in Lakhs |
|---|---|
| E&M Miss. | 3.01 |
| Survey | 4.43 |
| Solar | 29.58 |
| Capacity in Kw | Cost in Lakhs |
|---|---|
| No data available | |
| Departments | Cost in Lakhs |
|---|---|
| Railways | |
| PWD/NHIA | |
| Forest | |
| Irrigation | |
| Other | |
| Total | 0.00 |