Scheme Information - Print Version

Generated on: 21/06/2026 04:20 AM

Scheme Information

District Name Siddharth Nagar Agnecy Name Jayantisuper Construction PVT LTD
Scheme ID 5102539 Scheme Name Roman Dei WSS
Population Base Year 2025 Population Design Year 2040
Base Year Population 4021 Design Year Population 4695

OHT Details

1. OHT Details
OHT New OHT New (Capacity in KL) OHT New (Staging in m) OHT New (Cost in m)
No data available
OHT Old (Repair) OHT Old (Capacity in KL) OHT Old (Staging in m) OHT Old (Cost in m)
OHT-1 200.00 14.00 5.33
2. Tubewell
Tubewell New Tubewell New (Discharge in LPM) Tubewell New (Cost in Lakhs)
No data available
Tubewell Old (Repair) Tubewell Old Repair (Discharge in LPM) Tubewell Old Repair (Cost in Lakhs)
No data available
Tubewell Old (Rebore) Tubewell Old (Discharge in LPM) Tubewell Old Ribore (Cost in Lakhs)
Tubewell-1 800.00 19.21
3. PUMP HOUSE
PUMP HOUSE New PUMP HOUSE New (Cost in Lakhs)
No data available
PUMP HOUSE Old (Repair) PUMP HOUSE Old Repair (Cost in Lakhs)
PUMP HOUSE-1 1.39
4. Staff Quarter
Staff Quarter New Staff Quarter New (Cost in Lakhs)
No data available
Staff Quarter Old (Repair) Staff Quarter Old Repair (Cost in Lakhs)
Staff Quarter-1 2.13
5. Boundary Wall
Boundary Wall New Boundary Wall New (Cost in Lakhs)
No data available
Boundary Wall Old (Repair) Boundary Wall Old Repair (Cost in Lakhs)
Boundary Wall-1 3.32
6. Pumping Plant
Pumping Plant New Pumping Plant New (Discharge in LPM) Pumping Plant New (Cost in Lakhs)
Pumping Plant-1 800.00 5.20
Pumping Plant Old (Repair) Pumping Plant Old Repair (Discharge in LPM) Pumping Plant Old Repair (Cost in Lakhs)
No data available
7. Rising Main
Rising Main Material Rising Main (M) Rising Main Cost (in lacs)
DI 0.71
8A Distribution System (Excluding FHTC and Road Works)
1383.00
0.00
13741.00
60.20
8B. FHTC
No's Cost in Lakhs
Total FHTC [Formula = Serviceable + Repair + New]
869
[Formula = Repair + New Cost]
30.97
Serviceable 0 0
Repair 20 0.26
New 849 30.71
8C. Road Dismantling and Restoration
Type Of Roads Cost in Lakhs
Bituminous 9.19
CC 36.98
BOE 3.35
Interlocking 6.63
Total 56.15
8D. Total D/System Cost
Formula: Sum of Distribution System, FHTC, and Road Dismantling costs
147.32
9. Approach Road and Campus Development
Campus New Campus New (Cost in Lakhs)
No data available
Campus Old Repair Campus Old Repair (Cost in Lakhs)
Campus Old-1 4.82
10. For Surface Source Schemes
CWR/GLR New Capacity (in KL) CWR/GLR New (Cost in Lakhs)
No data available
CWR/GLR Old Repair Capacity (in KL) CWR/GLR Old Repair (Cost in Lakhs)
No data available
11. Chlorination Dozing Pump and Minor Wiring Works
1.01
12. Other Works not listed above
Name of Work Cost in Lakhs
SOFT STARTER,CHAIN PULLY,SOLAR STREET LIGHT,STAND POST,FHTC LOGO,FHTC ROAD CUTTING ,FHTC LOGO,SERVO VOLTAGE STEBILIZER 14.81
13. Works Related to other Departments
13.A) New Power Connection and other Appurtenant works
Capacity in Kw Cost in Lakhs
No data available
13.B) NOC Related
Departments Cost in Lakhs
Railways
PWD/NHIA
Forest
Irrigation
Other
Total 0.00

Part A - Work Cost

205.25
4.11
37.68
19.89
0.00
266.93

Part B - Solar Cost

25.00
21.54
0.43
3.95
2.09
28.01

Part C - Automation Cost

18.27
0.37
3.35
1.77
23.76

Per Capita Cost

Formula = (Work Cost Part A (a+ b + c)) / Population Base
0.0614
Formula = Work Cost Part A(a)
0.0437