1 |
Construction of 7.5 MLD CETP at GIDA, Gorakhpur |
NMCG |
M/S GIDA CETP Foundation |
-- |
11-Jan-2022 |
|
|
93.52 |
0.00 |
+0
0.00
|
+0
0.00
|
4 MLD CETP DPR Preparation complete. |
2 |
Upgrdation of 4.5 MLD CETP at Banther , Unnao |
NMCG |
Banther Industrial Pollution Control company |
M/S EMS infracon |
21-Feb-2020 |
07-Feb-2022 |
31-Jul-2025 |
108.96 |
111.96 |
+0
42.00
|
+0
63.00
|
Work Under Progress |
3 |
Construction of 20 MLD CETP at Jajmau Kanpur |
NMCG |
Jajamau Tanners and effluent treatment |
Va Tech Wabag |
11-Feb-2019 |
11-Apr-2019 |
01-Apr-2024 |
617.00 |
520.14 |
+0
353.00
|
+0
94.00
|
CETP is operational and complaint. 151 tanneries have been connected to piping network out of total 340 tanneries.All 340 tannery connnection targeted to be completed by August 25 |
4 |
Upgradation of 2.15 MLD CETP to 2.15 MLD CETP at Unnnao |
NMCG |
Unnao Tanners and pollution control company |
M/s JV UTIPL-Oasis-SIMA |
26-Jun-2022 |
|
|
127.00 |
172.00 |
+0
0.00
|
+0
0.00
|
Agreement signing pending at level of SPV. In compliance of NMCG instructions SMCG -UP vide its letter dated 19/06/2025 has written to DM Unnao and MS UPPSB for doing necessary actions for agreement signing including action against defaulting tanneries. |