Under Construction CETP in Uttar Pradesh Under Namami Gange Programme

S No Project Name Executive Agency  Contractor / Firm Name Date of Sanction Date of Completion Sanction cost(Cr) Agreement Cost(Cr) Financial Progress Physical Progress Remarks
1 2 3 4 5 6 7 8 9 10 11
1 Jajmau 20MLD CETP JTETA Va Tech Wabag 2/11/2019 12:00:00 AM 617 520.04 370.0000 87.0000 Construction for 10 MLD treatment capacity is Complete. Commisioning is under progress.
2 Banther CETP BIPCC (SPV) M/S EMS Infracon 2/21/2020 12:00:00 AM 108.96 111.96 24.5800 38.0000 under construction
3 Jajmau 20MLD CETP JTETA Va Tech Wabag 2/11/2019 12:00:00 AM 617 520.04 353.0000 89.0000 Construction for 10 MLD treatment capacity is Complete. Commisioning is under progress.
4 Banther CETP BIPCC (SPV) M/S EMS Infracon 2/21/2020 12:00:00 AM 108.96 111.96 38.2400 40.0000 under construction