Drains Details

S.No District River Drain Name Drain Type Total Discharge (MLD) Remarks Last Update Date
1 Chitrakoot Mandakini 'Nala near Shaheed Baba, Taronha, Kachhi Chhawni, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:17 AM
2 PrayagRaj Ganga A.D.A. Colony Nala / Jwaladevi Untapped Drains 4.28 Work is under progress 26-Mar-2025 03:23 PM
3 Saharanpur Harnandi (Hindon) Abdulla Colony Untapped Drains 0.21 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
4 Meerut Kali AbuNallah-1 Untapped Drains 39.22 Action to be taken 01-Jul-2024 12:00 AM
5 Meerut Kali AbuNallah-2 Untapped Drains 116.00 CA signed on 05.09.2023. Payment for1st and 2nd MS have been released.Work in progress at only 1 front of STP, Concessionaire need to open multiple working fronts. Inadequate Manpower deployment at site, Manpower deployment to be increased. 09-Jun-2025 05:23 PM
6 Saharanpur Harnandi (Hindon) Aggarwal Dharamshala - 1 Untapped Drains 0.15 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
7 Saharanpur Harnandi (Hindon) Aggarwal Dharamshala - 2 Untapped Drains 0.70 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
8 Sitapur Sarayan Alam Nagar Nala Untapped Drains 0.22 DPR preparation work is in progress. 15-Jul-2025 11:17 AM
9 Hathras Karvan Algarji Drain-I Untapped Drains 0.24 Proposed to be tapped in 24 MLD STP under I&D and STP works at Hathras project. Tendering in progres 01-Jul-2024 12:00 AM
10 Hathras Karvan Algarji-II Untapped Drains 0.23 Proposed to be tapped in 24 MLD STP under I&D and STP works at Hathras project. Tendering in progres 01-Jul-2024 12:00 AM
11 Aligarh Aligarh Drain ( Irrigation ) Aligarh Drain Untapped Drains 97.39 NMCG provided observations on DPR on 15.01.2024 and reply from CE Ganga sent to SMCG on 06.2.2024. SMCG asked for further clarifications on 04.04.2024. Clarification has been given on 07.06.2024 01-Jul-2024 12:00 AM
12 Agra Yamuna Almirah Factory Untapped Drains 0.04 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:42 PM
13 Mathura Kosi Arterial Channel Ambedkar Nagar Jatav Basti Nala Untapped Drains 0.49 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
14 Agra Yamuna Ambedkar Park Untapped Drains 0.78 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 01-Aug-2025 06:44 PM
15 Mathura Yamuna Annyor Untapped Drains 0.94 DPR for tapping of said drain is being prepared by UPJN(Urban) under SBM 2.0 04-Jul-2024 03:59 PM
16 Saharanpur Harnandi (Hindon) Ansari road Near Dr. Neha Clinic Untapped Drains 0.29 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
17 Agra Yamuna Aqua Cool Water Treatment Untapped Drains 0.02 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:55 PM
18 Mahoba NA Arimandan Nala Untapped Drains 1.66 Discharge of this drain falling to nearby Dariba sewage pond 29-Sep-2025 12:06 PM
19 Kanpur Nagar Pandu Arra Nala Untapped Drains 3.54 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:41 AM
20 Ghaziabad Harnandi (Hindon) Arthala Mohan Nagar Drain Untapped Drains 5.41 DPR for I&D and STP (68 MLD) has been sanctioned in AMRUT 2.0 11-Jul-2024 10:49 AM
21 Agra Yamuna Artoni Untapped Drains 0.21 Construction of 0.35 MLD capacity DSTP at Artoni village is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
22 Mathura Yamuna Aurangabad Downstream Nala Untapped Drains 0.73 Proposed to be tapped in 60 MLD STP Gokul Barrage under Mathura Sewerage Scheme. LOA issued. 01-Jul-2024 12:00 AM
23 Mathura Yamuna Aurangabad Upstream Nala Untapped Drains 1.02 Proposed to be tapped in 60 MLD STP Gokul Barrage under Mathura Sewerage Scheme. LOA issued. 01-Jul-2024 12:00 AM
24 Ambedkar Nagar Ghaghara Azra Nala Untapped Drains 2.37 DPR submitted to NMCG vide letter dated 31.03.2022. Observations intimated by NMCG vide letter dated 18.05.2022. Revised DPR was submitted to SMCG vide letter no. 420/012-0272(18)/2022 dated 03.09.2022. DPR submitted to NMCG vide letter no. 1054/0736/SMCG 19-Jun-2024 05:30 PM
25 Shamli Krishni Babari - Banti Kheda Nala Untapped Drains 3.00 BEP, Layout and HFD approved for 05 MLD STP. work is haulted due land issue. 09-Jun-2025 05:19 PM
26 Mathura Kosi Arterial Channel Bada Nala Untapped Drains 0.12 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
27 Pratapgarh Ganga Badri Vishal Nala (Manihari Nala) (Manikpur Nagar Panchayat) Untapped Drains 0.03 DPR Preparation is being done by U.P.J.N (Urban) under SBM 2.0 01-Jul-2024 12:00 AM
28 Saharanpur Harnandi (Hindon) Badshahi Masjid Untapped Drains 0.07 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
29 Ayodhya Saryu Bahadurganj A Untapped Drains 1.00 Will be tapped at 33 MLD Ayodhya STP 01-Jul-2024 12:00 AM
30 Ayodhya Saryu Bahadurganj B Untapped Drains 0.23 Will be tapped at 33 MLD Ayodhya STP 01-Jul-2024 12:00 AM
31 Agra Yamuna Bahadurpur Gaon Untapped Drains 0.04 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 01-Aug-2025 06:45 PM
32 Gorakhpur Rapti Bahrampur Nalla Untapped Drains 4.33 DPR for I&D of 8 drains and STP works (44 MLD) has been submitted to NMCG vide SMCG letter no.1030/0 26-Mar-2025 08:57 AM
33 Deoria Ghaghra Bairahna Baba Nala(Azad Nagar South) Untapped Drains 0.01 NA 04-Jul-2024 04:06 PM
34 Mirzapur Ganga Balaji temple Untapped Drains 2.20 Work in progress. 01-Jul-2024 12:00 AM
35 Kanpur Nagar Ganga Bangali Ghat Drain Untapped Drains 0.06 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:44 AM
36 Ghaziabad Yamuna Banthala Canal Drain Untapped Drains 17.00 Industrial Drain. To be taken up by UPPCB. 11-Jul-2024 10:54 AM
37 Gorakhpur Rohini Bargadwa Gao Jalan Nalla Untapped Drains 8.16 D.P.R. for “Gorakhpur Sewerage Scheme Zone-C, Part-2” amounting Rs. 566.15 Cr has been sanctioned under AMRUT 2.0. GO is awaited. 03-Jul-2024 04:55 PM
38 Lucknow Gomti Barikala Drain Untapped Drains 1.80 Date of start of 3.5 MLD Barikala STP is given on dt. 07.09.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Construction of Boundary wall work is in progress. SBR Basin-2 Selector Zone wall 4th lift, decantar wall 2nd lift and Partition wall walkway reinforcement, shuttering and casting work is in progress. CCT wall 2nd lift reinforcement, shuttering and casting work is in progress. MPS - wall 5th lift reinforcement, shuttering and casting work is in progress. 08-Sep-2025 11:59 AM
39 Mathura Kosi Arterial Channel Barsana Chowk Nagar Panchayat Nala Untapped Drains 0.25 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
40 Rae Bareli Ganga Barudha Ghat ka Nala/(Sherandajpur) Untapped Drains 0.15 Re-tendering work is in progress. Bid Document uploaded at e-tender portal on dt. 27.06.2025. Pre-bid Meeting dt. 04.07.2025 at 12:00 PM. Pre-bid reply sent to NMCG for review and approval on dt. 07.07.2025. NMCG sent final pre-bid replies on dt. 05.08.2025. Final pre-bid replies uploaded on e-tender portal on dt. 07.08.2025 Bid Submission date 22.08.2025. Technical Bid open on dt. 22.08.2025. TBER sent to NMCG for review and approval. 29-Sep-2025 03:43 PM
41 Gorakhpur Rapti Basantpur Narkatiya Nalla Untapped Drains 1.76 DPR for I&D of 8 drains and STP works (44 MLD) has been submitted to NMCG vide SMCG letter no.1030/0 01-Jul-2024 12:00 AM
42 Gorakhpur Rohini Basiyadih Nalla Untapped Drains 5.84 Work is in progress under AMRUT. Proposed Date of completion is 31.03.2023 03-Jul-2024 04:54 PM
43 Lalitpur Betwa Bayana Nala Untapped Drains 20.00 Bioremediation is being done by Nagar Palika in dry season. 29-Sep-2025 11:54 AM
44 Azamgarh Tamsa Before Kundanghat Bridge Drain Untapped Drains 0.09 Action to be taken 01-Jul-2024 12:00 AM
45 Azamgarh Tamsa Behind By pass raidarpur drain Untapped Drains 2.25 Action to be taken 01-Jul-2024 12:00 AM
46 Chitrakoot Mandakini Behind Janseva Inter College, Basti Nala, Shankar Bazar, Khatkana Mohalla, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:15 AM
47 Chitrakoot Yamuna Bekal Baba nala Untapped Drains 5.00 Action to be taken 01-Jul-2024 12:00 AM
48 Agra Yamuna Belanganj Bridge Untapped Drains 0.38 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 01-Aug-2025 06:47 PM
49 Agra Yamuna Belanganj Kali Mandir Untapped Drains 0.00 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 01-Aug-2025 06:47 PM
50 Agra Yamuna Belanganj Police Chowki Untapped Drains 0.21 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 01-Aug-2025 06:47 PM
51 Saharanpur Harnandi (Hindon) Below Railway Line Untapped Drains 0.05 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
52 Saharanpur Harnandi (Hindon) Beri Bagh drain Untapped Drains 0.50 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
53 Saharanpur Harnandi (Hindon) Bhagat Singh chowk ke samne Untapped Drains 0.25 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
54 Agra Yamuna Bhalla ji Wali Drain Untapped Drains 0.01 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 01-Aug-2025 06:48 PM
55 Chitrakoot Mandakini Bhauna Nala Tarunha, Chhiptahri, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:18 AM
56 Lakhimpur Kheri Sarayan Bhootnath Nala Untapped Drains 4.67 DPR has been prepared by U.P. Jal Nigam (Urban) in SBM 2.0 and submmited for approval. 01-Jul-2024 12:00 AM
57 Mathura Kosi Arterial Channel Bihari Ji Ka Nala Untapped Drains 0.06 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
58 Saharanpur Harnandi (Hindon) Bijli Ghar Nala Untapped Drains 0.70 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
59 Mahoba NA Boddh Math Nala Untapped Drains 1.24 Discharge of this drain falling to nearby Dariba sewage pond 29-Sep-2025 12:05 PM
60 Saharanpur Harnandi (Hindon) Brahmpuri Drain Untapped Drains 0.11 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
61 Saharanpur Harnandi (Hindon) Braj Transport Nala Untapped Drains 8.73 CA signed on 27.09.2023 27-May-2025 03:03 PM
62 Ghazipur Ganga Budenath Mahadew Ghat Drain Untapped Drains 0.80 City Sanitation action Plan has been submitted under SBM -2.0 by UPJN (Urban), SLTC awaited. 01-Jul-2024 12:00 AM
63 Mathura Yamuna Chaitanya Vihar Nala (Sunrakh Nala -1) Untapped Drains 3.34 Proposed to be tapped in 13 MLD STP under I&D and STP project Vrindavan. LoA has been issued 01-Jul-2024 12:00 AM
64 Mathura Yamuna Chaitanya Vihar Nala (Sunrakh Nala -2) Untapped Drains 0.56 Proposed to be tapped in 13 MLD STP under I&D and STP project Vrindavan. LoA has been issued 01-Jul-2024 12:00 AM
65 Moradabad Ram ganga Chandausi Road left side Untapped Drains 0.85 • DPR sent to NMCG vide L.no. 1474/032/SMCG-UP/11 dt 19.12 23 for approval. 35 MLD for Z-3 & 45 MLD 22-May-2024 06:10 PM
66 Chandauli Ganga Chandhasi Nala/Railway Nala Untapped Drains 21.07 Revised DPR sent to SMCG by CE(Ganga) on 13.08.2024. Funds to be allocated for purchase of land 28-Aug-2024 05:53 PM
67 Aligarh Aligarh Drain ( Irrigation ) Chherrat/Lehtoi Drain Untapped Drains 39.50 NMCG provided observations on DPR on 15.01.2024 and reply from CE Ganga sent to SMCG on 06.2.2024. SMCG asked for further clarifications on 04.04.2024. Clarification has been given on 07.06.2024 01-Jul-2024 12:00 AM
68 Saharanpur Harnandi (Hindon) Chilkana Nalla (Dhobi Ghat) Untapped Drains 17.41 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
69 Agra Yamuna Chini Ka Roza - I Untapped Drains 1.03 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 01-Aug-2025 06:48 PM
70 Agra Yamuna Chini Ka Roza - II Untapped Drains 0.03 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 01-Aug-2025 06:49 PM
71 Kannauj Ganga Chintamani Drain Untapped Drains 6.00 Pre Feasibility Report (PFR) for Interception & Diversion Work of Chintamani Drain, Construction of 12 MLD STP has been send to Head Quarter, UPJN(Rural) , Lucknow on dated 29.07.2025 29-Sep-2025 11:53 AM
72 Ambedkar Nagar Ghaghara Chintora Drain Untapped Drains 2.00 DPR submitted to NMCG vide letter dated 31.03.2022. Observations intimated by NMCG vide letter dated 18.05.2022. Revised DPR was submitted to SMCG vide letter no. 420/012-0272(18)/2022 dated 03.09.2022. DPR submitted to NMCG vide letter no. 1054/0736/SMCG 19-Jun-2024 05:41 PM
73 Mirzapur Ganga Chorawa Untapped Drains 0.25 Work in progress. 01-Jul-2024 12:00 AM
74 Mathura Kosi Arterial Channel Chuli Nagla Nala Untapped Drains 0.27 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
75 Ambedkar Nagar Tamsa chuna bhatti ke pass Untapped Drains 3.04 Action to be taken 03-Jul-2024 01:03 PM
76 Azamgarh Tamsa Collectorate Office Nala Untapped Drains 0.35 Action to be taken 01-Jul-2024 12:00 AM
77 Kanpur Nagar Ganga Dabka Nala Untapped Drains 2.14 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:37 AM
78 Azamgarh Tamsa Dalal ghat Jama masjid Drain Untapped Drains 0.52 Action to be taken 01-Jul-2024 12:00 AM
79 Azamgarh Tamsa Dalalghat Hathiya pul ke Untapped Drains 0.69 Action to be taken 01-Jul-2024 12:00 AM
80 Saharanpur Harnandi (Hindon) Dalmandi Pumping station Untapped Drains 0.44 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
81 PrayagRaj Yamuna Dariyabad Kakahraghat Drain Meerapur Untapped Drains 2.11 Work is under progress 26-Mar-2025 03:26 PM
82 PrayagRaj Yamuna Dariyabad Pipalghat Drain Untapped Drains 0.12 Work is under progress 26-Mar-2025 03:26 PM
83 Auraiya Yamuna Dayalpur Nala Untapped Drains 5.39 DPR for Interception and diversion works and construction of STP is approved under SBM-2. Tendering work in progress by UPJN Urban. 29-Sep-2025 12:03 PM
84 Agra Yamuna Dayanand Ashram Untapped Drains 0.21 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:43 PM
85 Moradabad Ram ganga Delhi road (L) Untapped Drains 1.05 DPR sent to NMCG vide L.no. 1474/032/SMCG-UP/11 dt 19.12 23 for approval. 35 MLD for Z-3 & 45 MLD Z- 22-May-2024 06:14 PM
86 Moradabad Ram ganga Delhi road(L) Untapped Drains 0.32 • DPR sent to NMCG vide L.no. 1474/032/SMCG-UP/11 dt 19.12 23 for approval. 35 MLD for Z-3 & 45 MLD 01-Jul-2024 12:00 AM
87 Moradabad Ram ganga Delhi road(R) Untapped Drains 1.32 DPR sent to NMCG vide L.no. 1474/032/SMCG-UP/11 dt 19.12 23 for approval. 35 MLD for Z-3 & 45 MLD Z- 01-Jul-2024 12:00 AM
88 Hathras Karvan Dhakpura Drain Untapped Drains 5.50 Proposed to be tapped in 24 MLD STP under I&D and STP works at Hathras project. Tendering in progres 01-Jul-2024 12:00 AM
89 Saharanpur Harnandi (Hindon) Dhamola Nadi ka Pul Sapna Takies Untapped Drains 1.09 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
90 Azamgarh Tamsa Dharmu drain Untapped Drains 2.85 Action to be taken 01-Jul-2024 12:00 AM
91 Agra Yamuna Dharwale Baba - I Untapped Drains 0.17 Construction of 1.10 MLD capacity DSTP at Islam Nagar is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
92 Agra Yamuna Dharwale Baba - II Untapped Drains 0.00 Construction of 1.10 MLD capacity DSTP at Islam Nagar is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
93 Sant Ravidas Nagar Varuna Dhaurahara/ Mamdevpur Drain Untapped Drains 5.00 DPR for 18 MLD, 5 MLD and 3 MLD STP approved by NMCG on 06.03.2025 10-Mar-2025 03:21 PM
94 Sitapur Sarayan Dhobi Ghat Nala Untapped Drains 0.85 DPR preparation work is in progress. 15-Jul-2025 11:16 AM
95 Chitrakoot Mandakini Dhobin Ghat drain Tarunha, Deyodhi Tola, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:18 AM
96 Gorakhpur Rapti Domingarh Nalla Untapped Drains 9.03 DPR for I&D of 8 drains and STP works (44 MLD) has been submitted to NMCG vide SMCG letter no.1030/0 26-Mar-2025 08:57 AM
97 Chitrakoot Mandakini Drain in front of Balaji Temple, Purani Bazaar, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:15 AM
98 Chitrakoot Mandakini Drain located at Raja Saheb Ghat, Near Old Bazar Ghus Maidan, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:16 AM
99 Chitrakoot Mandakini Drain next to NH, Purani Bazaar, Karvi (Near Indane Gas Agency) Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:16 AM
100 Mau Ghaghara Drain No. 10 (Ward-10) Untapped Drains 0.29 DPR for 3.5MLD STP submitted to NMCG, on which NMCG suggested to go for FSTP. DPR for FSTP submitted to SMCG on 10.10.2024. Observations received to which compliance shall be sent by 15.05.2025 06-May-2025 04:01 PM
101 Saharanpur Kali West Drain no. 4 Untapped Drains 0.15 Technical bid open on dated 25.01.2025, Bid Evaluation report send to NMCG on 28.04.2025. 27-May-2025 03:07 PM
102 Mau Ghaghara Drain No. 4 (Ward-4) Untapped Drains 1.76 DPR for 3.5MLD STP submitted to NMCG, on which NMCG suggested to go for FSTP. DPR for FSTP submitted to SMCG on 10.10.2024. Observations received to which compliance shall be sent by 15.05.2025 06-May-2025 04:00 PM
103 Chitrakoot Mandakini Drain towards the temple behind Bethel School, Shankar Bazar, Shankarganj, Mohalla, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:15 AM
104 Pilibhit Gomti Drain-2 Untapped Drains 30.00 tapped to Test STP 09-Sep-2024 11:33 PM
105 Saharanpur Harnandi (Hindon) Dukhi Bagh Untapped Drains 0.06 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
106 Varanasi Varuna Durga Drain Untapped Drains 37.00 DPR for construction of 60 MLD STP approved by NMCG on 06.03.2025 10-Mar-2025 03:19 PM
107 Mau Ghaghara Durga Mata Mandir drain Untapped Drains 0.09 DPR for 3.5MLD STP submitted to NMCG, on which NMCG suggested to go for FSTP. DPR for FSTP submitted to SMCG on 10.10.2024. Observations received to which compliance shall be sent by 15.05.2025 06-May-2025 04:01 PM
108 Azamgarh Tamsa Durga Talkies Thandi Road ka nala Untapped Drains 0.60 Action to be taken 01-Jul-2024 12:00 AM
109 Sitapur Sarayan Durgapurwa Nala Nai Basti Untapped Drains 0.17 DPR preparation work is in progress. 15-Jul-2025 11:13 AM
110 Sitapur Sarayan Fat Fata Nala Untapped Drains 0.25 DPR preparation work is in progress. 15-Jul-2025 11:18 AM
111 Lucknow Gomti Fazullaiganj Downstream Untapped Drains 0.77 Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed and handed over to UPJN (Urban). BEP of the STP is approved and design & drawing work is in progress. SBR Basin - Excavation, Dressing & Shoring work is in progress. Design & Drawing of proposed IPS is in progress. Site submerged with sewage water due to leakage of UPJN (Urban) SPS Inlet pipeline. Dewatering work is in progress. 21-Jul-2025 11:01 AM
112 Lucknow Gomti Fazullaiganj Upstream Untapped Drains 8.96 Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed and handed over to UPJN (Urban). BEP of the STP is approved and design & drawing work is in progress. SBR Basin - Excavation, Dressing & Shoring work is in progress. Design & Drawing of proposed IPS is in progress. Site submerged with sewage water due to leakage of UPJN (Urban) SPS Inlet pipeline. Dewatering work is in progress. 21-Jul-2025 11:01 AM
113 Ambedkar Nagar Tamsa gadaya Untapped Drains 1.79 Action to be taken 03-Jul-2024 01:07 PM
114 Saharanpur Harnandi (Hindon) Gaddhe Wali Gali Untapped Drains 2.71 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
115 Agra Yamuna Gailana Untapped Drains 0.24 Construction of 3.00 MLD capacity DSTP at Transport Nagar is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
116 Agra Yamuna Gali Amanat Ram Bagichi-I Untapped Drains 0.08 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:43 PM
117 Agra Yamuna Gali Amanat Ram Bagichi-II Untapped Drains 0.01 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:44 PM
118 Agra Yamuna Gali Subedar Nagar Untapped Drains 0.15 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:45 PM
119 Agra Yamuna Ganesh Nagar Untapped Drains 0.24 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:45 PM
120 Unnao Ganga Ganga Vishnu Drain Untapped Drains 0.10 I&D and STP works at Shuklaganj is ongoing under Namami Gange, likely to be completed by Dec.-25 29-Sep-2025 09:38 AM
121 Deoria Ghaghra Gaura Nala-1(near peepal tree) Untapped Drains 0.02 NA 04-Jul-2024 04:15 PM
122 Gorakhpur Rapti Ghasiyari Nalla Untapped Drains 0.30 DPR for I&D of 8 drains and STP works (44 MLD) has been submitted to NMCG vide SMCG letter no.1030/0 01-Jul-2024 12:00 AM
123 Ambedkar Nagar Ghaghara Ghasiyari Tola Untapped Drains 1.30 DPR submitted to NMCG vide letter dated 31.03.2022. Observations intimated by NMCG vide letter dated 18.05.2022. Revised DPR was submitted to SMCG vide letter no. 420/012-0272(18)/2022 dated 03.09.2022. DPR submitted to NMCG vide letter no. 1054/0736/SMCG 19-Jun-2024 05:33 PM
124 Mirzapur Ganga Ghoreshahid Drain Untapped Drains 5.00 Work in progress. 01-Jul-2024 12:00 AM
125 Sitapur Sarayan GIC Nala Untapped Drains 1.17 DPR preparation work is in progress. 15-Jul-2025 11:21 AM
126 Agra Yamuna Gokul Nagar Untapped Drains 0.39 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:45 PM
127 Ambedkar Nagar Ghaghara Gola Ghat Untapped Drains 0.26 DPR submitted to NMCG vide letter dated 31.03.2022. Observations intimated by NMCG vide letter dated 18.05.2022. Revised DPR was submitted to SMCG vide letter no. 420/012-0272(18)/2022 dated 03.09.2022. DPR submitted to NMCG vide letter no. 1054/0736/SMCG 19-Jun-2024 05:34 PM
128 Kanpur Nagar Ganga Golaghat Nala Untapped Drains 1.79 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:38 AM
129 Lucknow Gomti Gomti Nagar Drain Untapped Drains 22.15 DPR has been submitted to NMCG vide letter no. 1050/0369/SMCG-UP/12 dt. 27.09.2022 for approval. CE (Ganga) again requested to SMCG for approval of DPR on dt.19.06.2024. 04-Dec-2024 01:57 PM
130 Lucknow Gomti Gomti Nagar Extension Drain Untapped Drains 2.07 DPR has been submitted to NMCG vide letter no. 1050/0369/SMCG-UP/12 dt. 27.09.2022 for approval. CE (Ganga) again requested to SMCG for approval of DPR on dt.19.06.2024. 04-Dec-2024 01:57 PM
131 Sitapur Sarayan Gopal Ghat Nala Untapped Drains 0.09 DPR preparation work is in progress. 15-Jul-2025 11:13 AM
132 Ghazipur Ganga Gorawa Drain Untapped Drains 0.60 City Sanitation action Plan has been submitted under SBM -2.0 by UPJN (Urban), SLTC awaited. 01-Jul-2024 12:00 AM
133 PrayagRaj Ganga Govindpur Colony Drain (Purani Basti) Untapped Drains 0.22 Work is under progress 26-Mar-2025 03:20 PM
134 PrayagRaj Ganga Govindpur Colony Drain No. 1 Untapped Drains 0.28 Work is under progress 26-Mar-2025 03:21 PM
135 PrayagRaj Ganga Govindpur Colony Drain No. 2 Untapped Drains 0.32 Work is under progress 26-Mar-2025 03:21 PM
136 PrayagRaj Ganga Govindpur Colony Drain No. 3 Untapped Drains 0.16 Work is under progress 26-Mar-2025 03:21 PM
137 PrayagRaj Ganga Govindpur Colony Drain No. 4 Untapped Drains 0.27 Work is under progress 26-Mar-2025 03:22 PM
138 Azamgarh Tamsa Grand Hospital Nala Untapped Drains 1.21 Action to be taken 01-Jul-2024 12:00 AM
139 Gautam Buddha Nagar Harnandi (Hindon) Greater Noida Drain Untapped Drains 13.00 Industrial Drain. To be taken up by UPPCB. 14-Aug-2024 03:24 PM
140 Gorakhpur Rohini Green City Phase-II Nalla Untapped Drains 1.61 Work is in progress under AMRUT. Proposed Date of completion is 31.03.2023 03-Jul-2024 04:54 PM
141 Azamgarh Tamsa Gulami ka pura masjid k paas Untapped Drains 0.95 Action to be taken 01-Jul-2024 12:00 AM
142 Bulandshahr Kali Gulaothi Drain Untapped Drains 6.91 The DPR has been sanctioned by NMCG in EC meeting on 13.08.2024 08-Jul-2025 05:44 PM
143 Sitapur Sarayan Habib Pur Nala Untapped Drains 0.31 DPR preparation work is in progress. 15-Jul-2025 11:21 AM
144 Azamgarh Tamsa Hadaha Mandir Ka Nala Untapped Drains 1.38 Action to be taken 01-Jul-2024 12:00 AM
145 Mathura Kosi Arterial Channel Hamir Thok Nala -I Untapped Drains 0.06 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
146 Mathura Kosi Arterial Channel Hamir Thok Nala -II Untapped Drains 0.06 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
147 Mahoba NA Hamirpur Chungi Nala Untapped Drains 2.26 Discharge of this drain falling to nearby Dariba sewage pond 29-Sep-2025 12:06 PM
148 Gorakhpur Rapti Hansupur Nalla Untapped Drains 0.82 DPR for I&D of 8 drains and STP works (44 MLD) has been submitted to NMCG vide SMCG letter no.1030/0 01-Jul-2024 12:00 AM
149 Gorakhpur Ghaghra Hanuman Garhi Nala Untapped Drains 0.06 Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 28-Aug-2024 03:33 PM
150 Mirzapur Ganga Hanumanghat Drain Untapped Drains 0.68 Work in progress. 01-Jul-2024 12:00 AM
151 Hapur Kali Hapur Drain-1 (City drain) Untapped Drains 6.00 LOI issued to M/s Satish Kumar vide SE Lt No. 196/790/10 Dt 24.08.24 28-Aug-2024 02:55 PM
152 Chitrakoot Mandakini Harijan Basti Kailash street drain, Tarouha, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:17 AM
153 Lakhimpur Kheri ULL RIVER Hidayatnagar Drain Untapped Drains 2.70 Originating from Dist Lakhimpur & falls in Ghagra river. 01-Jul-2024 12:00 AM
154 Ghaziabad Harnandi (Hindon) Hindon Vihar Drain Untapped Drains 7.46 Action to be taken 11-Jul-2024 10:48 AM
155 Gorakhpur Rapti Illahibagh Nalla Untapped Drains 20.61 DPR for I&D of 8 drains and STP works (44 MLD) has been submitted to NMCG vide SMCG letter no.1030/0 26-Mar-2025 08:57 AM
156 Agra Yamuna Indira Memorial Bridge Untapped Drains 0.15 Construction of 1.50 MLD capacity DSTP at Indira memorial is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
157 Unnao Ganga Indira Nagar Drain Untapped Drains 2.80 I&D and STP works at Shuklaganj is ongoing under Namami Gange, likely to be completed by Dec.-25 29-Sep-2025 09:38 AM
158 Rae Bareli Sai Indira Nagar Nala Untapped Drains 4.70 DPR will be prepared after acquisition of Land for I&D of 02 drains which is to be provided by NPP 18-Sep-2024 04:09 PM
159 Saharanpur Harnandi (Hindon) Indra Basti 1 drain Untapped Drains 0.04 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
160 Saharanpur Harnandi (Hindon) Indra Basti 2 drain Untapped Drains 0.15 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
161 Saharanpur Harnandi (Hindon) Indra Basti 3 drain Untapped Drains 0.18 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
162 Saharanpur Harnandi (Hindon) Indra Camp Untapped Drains 0.44 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
163 Ghaziabad Yamuna Indrapuri Drain Untapped Drains 35.00 ... 11-Jul-2024 10:48 AM
164 Agra Yamuna Islam Nagar Untapped Drains 0.49 Construction of 1.10 MLD capacity DSTP at Islam Nagar is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
165 Auraiya Yamuna Jalaun Road Nala Untapped Drains 11.07 DPR for Interception and diversion works and construction of STP is approved under SBM-2. Tendering work in progress by UPJN Urban. 29-Sep-2025 12:03 PM
166 Hathras Karvan Jalesar Road-I Untapped Drains 0.42 Proposed to be tapped in 24 MLD STP under I&D and STP works at Hathras project. Tendering in progres 01-Jul-2024 12:00 AM
167 Hathras Karvan Jalesar Road-II Untapped Drains 0.50 Proposed to be tapped in 24 MLD STP under I&D and STP works at Hathras project. Tendering in progres 01-Jul-2024 12:00 AM
168 Agra Yamuna Jalma Untapped Drains 0.52 Construction of 0.30 MLD capacity DSTP near Jalma institue is in progress under Agra Sewerage Schem 01-Jul-2024 12:00 AM
169 Barabanki Gomti Jamuriya Drain Untapped Drains 18.00 Land unavailable for STP 22-Aug-2025 01:50 PM
170 Saharanpur Harnandi (Hindon) Janta colony Untapped Drains 0.04 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
171 Agra Yamuna Jaswant Singh Ki Chatri - I Untapped Drains 0.03 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:46 PM
172 Agra Yamuna Jaswant Singh Ki Chatri - II Untapped Drains 0.02 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:46 PM
173 Agra Yamuna Jaswant Singh Ki Chatri - III Untapped Drains 0.01 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:46 PM
174 Mathura Yamuna Jatipura Drain Untapped Drains 0.60 DPR for tapping of said drain is being prepared by UPJN(Urban) under SBM 2.0 . 04-Jul-2024 04:01 PM
175 Ghazipur Ganga Jauhargaj Drain Untapped Drains 0.80 City Sanitation action Plan has been submitted under SBM -2.0 by UPJN (Urban), SLTC awaited. 01-Jul-2024 12:00 AM
176 Saharanpur Harnandi (Hindon) Jawahar Nagar, Khurana Niwas Untapped Drains 1.10 CA signed on 27.09.2023 27-May-2025 03:01 PM
177 Saharanpur Harnandi (Hindon) Jogyan Pull near Ganpati cellphone Untapped Drains 0.58 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
178 PrayagRaj Ganga Jondhwal Nala Untapped Drains 6.75 Work is under progress 26-Mar-2025 03:22 PM
179 Azamgarh Tamsa Jyoti Niketan School drain Untapped Drains 1.81 Action to be taken 01-Jul-2024 12:00 AM
180 Agra Yamuna K.K. Nagar Untapped Drains 0.60 Construction of 1.6 MLD capacity DSTP is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
181 Mau Ghaghara Kabristan drain Untapped Drains 0.03 DPR for 3.5MLD STP submitted to NMCG, on which NMCG suggested to go for FSTP. DPR for FSTP submitted to SMCG on 10.10.2024. Observations received to which compliance shall be sent by 15.05.2025 06-May-2025 04:01 PM
182 Deoria Ghaghra Kabristan Nala Untapped Drains 0.85 NA 04-Jul-2024 04:24 PM
183 Agra Yamuna Kailash Mandir Untapped Drains 0.01 Construction of 0.02 MLD capacity DSTP near Kailash Mandir is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
184 Mathura Yamuna Kala Patthar Nala Untapped Drains 7.64 Proposed to be tapped in 60 MLD STP Gokul Barrage under Mathura Sewerage Scheme. LOA issued. 01-Jul-2024 12:00 AM
185 Azamgarh Tamsa Kaleem Ganj Nala Untapped Drains 0.17 Action to be taken 01-Jul-2024 12:00 AM
186 Chandauli Ganga Kali Mohal Drain (Ganda Nala) Untapped Drains 8.26 Revised DPR sent to SMCG by CE(Ganga) on 13.08.2024. Funds to be allocated for purchase of land. 28-Aug-2024 05:53 PM
187 Mahoba NA Kalyaan Sagar Nala Untapped Drains 2.00 the discharge of kalyaan sagar drain accumulates in Kalyaan Sagar Pond. 29-Sep-2025 12:05 PM
188 Saharanpur Harnandi (Hindon) Kalyani Sales Untapped Drains 0.06 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
189 Agra Yamuna Kamayani Hospital Untapped Drains 0.40 Construction of 1.6 MLD capacity DSTP at KK Nagar is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
190 Gorakhpur Ghaghra Kango Ghat Nala - 1 Untapped Drains 1.83 Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 28-Aug-2024 03:31 PM
191 Gorakhpur Ghaghra Kango Ghat Nala - 2 Untapped Drains 0.10 Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 28-Aug-2024 03:32 PM
192 Chitrakoot Mandakini Kanji House to Shamshan Ghat Road Drain, Sitapur, Chitrakoot Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:19 AM
193 Ghazipur Ganga Kankarwa Drain Untapped Drains 1.01 City Sanitation action Plan has been submitted under SBM -2.0 by UPJN (Urban), SLTC awaited. 01-Jul-2024 12:00 AM
194 Rae Bareli Sai Kanpur Road Nala Untapped Drains 3.20 DPR will be prepared after acquisition of Land for I&D of 02 drains which is to be provided by NPP 18-Sep-2024 04:10 PM
195 Saharanpur Harnandi (Hindon) Kapil Vihar Drain Untapped Drains 0.35 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
196 Saharanpur Harnandi (Hindon) Kapil Vihar near OHT Untapped Drains 0.17 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
197 Ghaziabad Harnandi (Hindon) Karheda Drain Untapped Drains 4.72 DPR for I&D and STP (68 MLD) has been sanctioned in AMRUT 2.0 11-Jul-2024 10:45 AM
198 Banda Ken Kariya Nala Untapped Drains 6.06 Bio remediation treatment is being done by Nagar Palika, Banda 29-Sep-2025 12:00 PM
199 Ghazipur Ganga Karpurimai Ghat Drain Untapped Drains 2.80 City Sanitation action Plan has been submitted under SBM -2.0 by UPJN (Urban), SLTC awaited. 01-Jul-2024 12:00 AM
200 Moradabad Ram ganga Karula drain Untapped Drains 32.00 • DPR sent to NMCG vide L.no. 1474/032/SMCG-UP/11 dt 19.12 23 for approval. 35 MLD for Z-3 & 45 MLD 22-May-2024 06:05 PM
201 Gorakhpur Rapti Kataniya / Mahewa Nalla Untapped Drains 8.91 To be taken up under AMRUT-II. DPR has been approved in SLTC meeting dt. 10.08.2022 and approved in SHPSC dt. 30.08.2022. GO awaited. 03-Jul-2024 05:12 PM
202 Ballia Ganga Kathalr Nala Untapped Drains 12.10 STP proposed to be completed in May 2025 01-Jul-2024 12:00 AM
203 Agra Yamuna Katra Wazir Khan - I Untapped Drains 0.02 Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:47 PM
204 Agra Yamuna Katra Wazir Khan - II Untapped Drains 0.01 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:48 PM
205 Muzaffarnagar Kali West Khadarwala (Nala no-3) Untapped Drains 5.41 I&D and STP works at Muzaffarnagar is ongoing under Namami Gange, likely to be completed by Jun-25. 09-Jun-2025 05:03 PM
206 Agra Yamuna Khairati Tola Untapped Drains 1.36 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:48 PM
207 Azamgarh Tamsa Khairatpur Nala Untapped Drains 0.43 Action to be taken 01-Jul-2024 12:00 AM
208 Hamirpur Betwa Khalepur Nala Untapped Drains 0.70 DPR for I&D of these drains has been sent to SBM, Nideshalaya for approval by UPJN(U) in Oct, 2023. 29-Sep-2025 12:02 PM
209 Agra Yamuna Khemchand Tofee factory Untapped Drains 0.03 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:48 PM
210 Saharanpur Harnandi (Hindon) Khumran Pul Mandi ky Pass Untapped Drains 0.75 CA signed on 27.09.2023 27-May-2025 03:04 PM
211 Saharanpur Harnandi (Hindon) Khumran Pul Rikshaw Stand Untapped Drains 0.50 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
212 Ayodhya Saryu Khurdabad B Untapped Drains 0.19 Will be tapped at 33 MLD Ayodhya STP 01-Jul-2024 12:00 AM
213 Bulandshahr Kali Khurja Drain Untapped Drains 14.00 Action to be taken 04-Jul-2024 01:37 PM
214 Mahoba NA Kirat Sagar Nala Untapped Drains 2.00 the discharge of kirat sagar drain accumulates in Kirat Sagar Pond. 29-Sep-2025 12:04 PM
215 Saharanpur Kali West Kola Basti Drain Untapped Drains 0.50 Technical bid open on dated 25.01.2025, Bid Evaluation report send to NMCG on 28.04.2025 27-May-2025 03:08 PM
216 Azamgarh Tamsa Kolghat roadways laldiggi Nala Untapped Drains 2.42 Action to be taken 01-Jul-2024 12:00 AM
217 Ghazipur Ganga Kot Ghat Untapped Drains 0.90 City Sanitation action Plan has been submitted under SBM -2.0 by UPJN (Urban), SLTC awaited. 01-Jul-2024 12:00 AM
218 Saharanpur Harnandi (Hindon) Kotwali Nala (left side of Paondhoi) Untapped Drains 0.45 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
219 Muzaffarnagar Kali West Krishnapuri (Nala no.-4) Untapped Drains 16.83 I&D and STP works at Muzaffarnagar is ongoing under Namami Gange, likely to be completed by Jun-25. 09-Jun-2025 05:03 PM
220 Kaushambi Ganga Kubri Ghat-1 Untapped Drains 0.40 Work is proposed in SBM 2.0 by UPJN (Urban) 16-Aug-2024 11:29 AM
221 Kaushambi Ganga Kubri Ghat-2 Untapped Drains 0.10 Work is proposed in SBM 2.0 by UPJN (Urban) 16-Aug-2024 11:29 AM
222 Deoria Ghaghra Kuti Ghat Nala(Azad Nagar South) Untapped Drains 0.04 NA 04-Jul-2024 04:11 PM
223 Gorakhpur Ghaghra Kutiya Mohalla Nala Untapped Drains 1.03 Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 28-Aug-2024 03:33 PM
224 Saharanpur Kali West Kutti Rorad Drain Untapped Drains 9.00 Technical bid open on dated 25.01.2025, Bid Evaluation report send to NMCG on 28.04.2025 27-May-2025 03:07 PM
225 Rae Bareli Sai Lohanipur Rewatiram Talab Untapped Drains 1.90 DPR will be prepared after acquisition of Land for I&D of 01 drains which is to be provided by NPP 26-Mar-2025 09:48 AM
226 Agra Yamuna Lohia Nagar Untapped Drains 0.38 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:49 PM
227 Agra Yamuna Lohia Nagar Bankey Bihari Bagichi Untapped Drains 0.10 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:49 PM
228 Agra Yamuna Lohia Nagar Rathor Wali Gali Untapped Drains 0.19 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:50 PM
229 Sitapur Sarayan Loniyan Purwa Purvi Nala (Near KainchiPull) Untapped Drains 0.23 DPR preparation work is in progress. 15-Jul-2025 11:16 AM
230 Saharanpur Harnandi (Hindon) Macchali Bazar Untapped Drains 0.61 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
231 Sitapur Sarayan Machhali Mandi ka pakka nala Untapped Drains 0.74 DPR preparation work is in progress. 15-Jul-2025 11:19 AM
232 Ambedkar Nagar Ghaghara Machriawa Untapped Drains 1.57 DPR submitted to NMCG vide letter dated 31.03.2022. Observations intimated by NMCG vide letter dated 18.05.2022. Revised DPR was submitted to SMCG vide letter no. 420/012-0272(18)/2022 dated 03.09.2022. DPR submitted to NMCG vide letter no. 1054/0736/SMCG 19-Jun-2024 05:35 PM
233 Rae Bareli Sai Mahanandapur Nala Untapped Drains 7.40 DPR will be prepared after acquisition of Land for I&D of 01 drains which is to be provided by NPP 26-Mar-2025 09:32 AM
234 Ghazipur Ganga Mahaveer Ghat Drain Untapped Drains 0.60 City Sanitation action Plan has been submitted under SBM -2.0 by UPJN (Urban), SLTC awaited. 01-Jul-2024 12:00 AM
235 Lucknow Gomti Maheshganj Untapped Drains 8.22 Date of start is given on dt. 14.06.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Soil testing at STP site and construction of staff quarter is completed and handed over to UPJN (Urban). BEP of the STP is approved and design & drawing work is in progress. SBR Basin - Excavation, Dressing & Shoring work is in progress. Design & Drawing of proposed IPS is in progress. Site submerged with sewage water due to leakage of UPJN (Urban) SPS Inlet pipeline. Dewatering work is in progress. 21-Jul-2025 11:02 AM
236 Gorakhpur Rohini Mahesra Mohripur Nalla Untapped Drains 5.01 D.P.R. for “Gorakhpur Sewerage Scheme Zone-C, Part-2” amounting Rs. 566.15 Cr has been sanctioned under AMRUT 2.0. GO is awaited. 03-Jul-2024 04:55 PM
237 Deoria Ghaghra Main Bazar Nala Untapped Drains 1.60 NA 04-Jul-2024 04:25 PM
238 Kanpur Nagar Ganga Makku Sayeed Ka Bhatta Drain Untapped Drains 0.30 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:43 AM
239 Mahoba NA Malakpura Drain Untapped Drains 1.13 Discharge of this drain falling to nearby Dariba sewage pond 29-Sep-2025 12:05 PM
240 Deoria Ghaghra Malang Baba Nala(Gaura) Untapped Drains 0.00 discharge-.004MLD 04-Jul-2024 04:16 PM
241 Pratapgarh Ganga Mallahan tola drain (Manikpur Nagar Panchayat) Untapped Drains 0.09 DPR Preparation is being done by U.P.J.N (Urban) under SBM 2.0 01-Jul-2024 12:00 AM
242 Sonbhadra Sone Mallahi Tola Drain Near Bajarang Ghat Untapped Drains 1.70 As per Information provided by NP-Chopan 18-Jul-2024 12:09 PM
243 Sonbhadra Sone Mallahi Tola-1 Untapped Drains 1.70 As per information provided by NP-Chopan 26-Jul-2024 06:36 PM
244 Hathras Karvan Mandi Samiti Drain Untapped Drains 3.12 Proposed to be tapped in 24 MLD STP under I&D and STP works at Hathras project. Tendering in progres 01-Jul-2024 12:00 AM
245 Ayodhya Saryu Manja Gaon Untapped Drains 0.10 Will be tapped at 33 MLD Ayodhya STP 31-May-2024 01:32 PM
246 Sitapur Sarayan Manni Chauraha Nala Untapped Drains 2.06 DPR preparation work is in progress. 15-Jul-2025 11:14 AM
247 Unnao Ganga Manohar Nagar Nala IInd (New) Untapped Drains 0.57 I&D and STP works at Shuklaganj is ongoing under Namami Gange, likely to be completed by Dec.-25 29-Sep-2025 09:39 AM
248 Unnao Ganga Manohar Nagar Nala Ist (New) Untapped Drains 0.63 I&D and STP works at Shuklaganj is ongoing under Namami Gange, likely to be completed by Dec.-25 29-Sep-2025 09:38 AM
249 Agra Yamuna Manoharpura Untapped Drains 1.31 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:50 PM
250 Kanpur Nagar Ganga Massacre Drain Untapped Drains 1.10 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:39 AM
251 Agra Yamuna Mau Nala - I Untapped Drains 0.11 Construction of 1.13 MLD capacity DSTP at Mau is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
252 Agra Yamuna Mau Nala - II Untapped Drains 0.58 Construction of 1.13 MLD capacity DSTP at Mau is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
253 Ghaziabad Harnandi (Hindon) Meerut Road/ Kailabhatta Drain Untapped Drains 25.31 A PFR, amounting Rs. 440.68 cr. has been submitted under Smart City Programme for I&D and STP (60 and 77 MLD) 11-Jul-2024 10:49 AM
254 Ambedkar Nagar Tamsa mehrotra petrol pump Untapped Drains 6.49 Action to be taken 03-Jul-2024 01:22 PM
255 Ayodhya Saryu Mehtab Baag A Untapped Drains 1.08 Will be tapped at 33 MLD Ayodhya STP 31-May-2024 01:30 PM
256 Ayodhya Saryu Mehtab Baag B Untapped Drains 0.10 Will be tapped at 33 MLD Ayodhya STP 31-May-2024 01:31 PM
257 Ayodhya Saryu Mehtab Baag C Untapped Drains 0.35 Will be tapped at 33 MLD Ayodhya STP 31-May-2024 01:32 PM
258 Gorakhpur Rapti Mirzapur Nalla Untapped Drains 3.28 DPR for I&D of 8 drains and STP works (44 MLD) has been submitted to NMCG vide SMCG letter no.1030/0 26-Mar-2025 08:56 AM
259 Ambedkar Nagar Ghaghara Mishra Ji boundry wall Drain Untapped Drains 1.90 DPR submitted to NMCG vide letter dated 31.03.2022. Observations intimated by NMCG vide letter dated 18.05.2022. Revised DPR was submitted to SMCG vide letter no. 420/012-0272(18)/2022 dated 03.09.2022. DPR submitted to NMCG vide letter no. 1054/0736/SMCG 19-Jun-2024 05:38 PM
260 Moradabad Ram ganga MIT Drain Untapped Drains 7.50 To be tapped to 25 MLD STP. work is under progress. 01-Jul-2024 12:00 AM
261 Lakhimpur Kheri Sarayan Mohammadi Drain Untapped Drains 0.29 DPR has been prepared by U.P. Jal Nigam (Urban) in SBM 2.0 and submmited for approval. 01-Jul-2024 12:00 AM
262 Moradabad Ram ganga Moksh Dham Drain Untapped Drains 6.50 To be tapped to 25 MLD STP. work is under progress. 01-Jul-2024 12:00 AM
263 Agra Yamuna Moti Mahal - 1 Untapped Drains 0.04 Construction of 1.50 MLD capacity DSTP at Indira Memorial is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
264 Agra Yamuna Moti Mahal - 2 Untapped Drains 0.05 Construction of 1.50 MLD capacity DSTP at Indira Memorial is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
265 Agra Yamuna Moti Mahal - 3 Untapped Drains 0.01 Construction of 1.50 MLD capacity DSTP at Indira Memorial is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
266 Agra Yamuna Moti Mahal - 4 Untapped Drains 0.12 Construction of 1.50 MLD capacity DSTP at Indira Memorial is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
267 Agra Yamuna Moti Mahal - 5 Untapped Drains 0.03 Construction of 1.50 MLD capacity DSTP at Indira Memorial is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
268 Agra Yamuna Moti Mahal - 6 Untapped Drains 0.00 Construction of 1.50 MLD capacity DSTP at Indira Memorial is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
269 Agra Yamuna Moti Mahal - 7 Untapped Drains 0.27 Construction of 1.50 MLD capacity DSTP at Indira Memorial is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
270 Agra Yamuna Moti Mahal - 8 Untapped Drains 0.20 Construction of 1.50 MLD capacity DSTP at Indira Memorial is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
271 Mau Ghaghara Mukti dham drain Untapped Drains 0.04 DPR for 3.5MLD STP submitted to NMCG, on which NMCG suggested to go for FSTP. DPR for FSTP submitted to SMCG on 10.10.2024. Observations received to which compliance shall be sent by 15.05.2025 06-May-2025 04:01 PM
272 Deoria Ghaghra Mukti Dham Nala Untapped Drains 0.93 NA 04-Jul-2024 04:02 PM
273 Gorakhpur Ghaghra Muktipath Nala Untapped Drains 0.38 Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 28-Aug-2024 03:34 PM
274 Gorakhpur Ghaghra Muktipath Near Bridge Nala Untapped Drains 0.09 Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 28-Aug-2024 03:33 PM
275 Rae Bareli Ganga Muskatpal Nala Untapped Drains 0.03 Re-tendering work is in progress. Bid Document uploaded at e-tender portal on dt. 27.06.2025. Pre-bid Meeting dt. 04.07.2025 at 12:00 PM. Pre-bid reply sent to NMCG for review and approval on dt. 07.07.2025. NMCG sent final pre-bid replies on dt. 05.08.2025. Final pre-bid replies uploaded on e-tender portal on dt. 07.08.2025 Bid Submission date 22.08.2025. Technical Bid open on dt. 22.08.2025. TBER sent to NMCG for review and approval. 29-Sep-2025 03:44 PM
276 Chitrakoot Mandakini Naavghat drain, Near Old Bazar Ghus Maidan, Naavghat, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:16 AM
277 Hathras Karvan Nagla Khan Drain Untapped Drains 0.19 Proposed to be tapped in 24 MLD STP under I&D and STP works at Hathras project. Tendering in progres 01-Jul-2024 12:00 AM
278 Mathura Kosi Arterial Channel Nagla Thok Paigam road Nala -I Untapped Drains 0.07 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
279 Mathura Kosi Arterial Channel Nagla Thok Paigam road Nala -II Untapped Drains 0.32 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
280 Mathura Kosi Arterial Channel Nagla Thok pul Nala Untapped Drains 0.11 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progressss 01-Jul-2024 12:00 AM
281 Mathura Kosi Arterial Channel Nagla Thok Pul Paar Nala Untapped Drains 0.06 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
282 Saharanpur Harnandi (Hindon) Nai Basti-1 Untapped Drains 0.03 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
283 Saharanpur Harnandi (Hindon) Nai Basti-2 Untapped Drains 0.26 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
284 Sant Ravidas Nagar Varuna Nai Bazaar Drain Untapped Drains 6.50 DPR for 18 MLD, 5 MLD and 3 MLD STP approved by NMCG on 06.03.2025 10-Mar-2025 03:21 PM
285 Saharanpur Harnandi (Hindon) Najir pura Untapped Drains 0.03 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
286 Sitapur Sarayan Nala at Gadiyana - I Untapped Drains 0.03 DPR preparation work is in progress. 15-Jul-2025 11:19 AM
287 Sitapur Sarayan Nala at Gadiyana - II Untapped Drains 0.08 DPR preparation work is in progress. 15-Jul-2025 11:19 AM
288 Sitapur Sarayan Nala at Gadiyana - III Untapped Drains 0.15 DPR preparation work is in progress. 15-Jul-2025 11:19 AM
289 Sitapur Sarayan Nala At Pakka Pul Untapped Drains 0.59 DPR preparation work is in progress. 15-Jul-2025 11:20 AM
290 Sitapur Sarayan Nala At Saint Bilal School Untapped Drains 0.15 DPR preparation work is in progress. 15-Jul-2025 11:14 AM
291 Rae Bareli Ganga Nala between Bada Math - Chhota Math Untapped Drains 0.05 Re-tendering work is in progress. Bid Document uploaded at e-tender portal on dt. 27.06.2025. Pre-bid Meeting dt. 04.07.2025 at 12:00 PM. Pre-bid reply sent to NMCG for review and approval on dt. 07.07.2025. NMCG sent final pre-bid replies on dt. 05.08.2025. Final pre-bid replies uploaded on e-tender portal on dt. 07.08.2025 Bid Submission date 22.08.2025. Technical Bid open on dt. 22.08.2025. TBER sent to NMCG for review and approval. 29-Sep-2025 03:44 PM
292 Chitrakoot Mandakini Nala in front of Islamia School, Tarunha, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:17 AM
293 Sitapur Sarayan Nala Near Kaichi Pul Uttar Purwa Butsganj Untapped Drains 0.13 DPR preparation work is in progress. 15-Jul-2025 11:20 AM
294 Sitapur Sarayan Nala Near Kaichipul -II Untapped Drains 0.25 DPR preparation work is in progress. 15-Jul-2025 11:14 AM
295 Sitapur Sarayan Nala Near Sai Baba Mandir Untapped Drains 1.57 DPR preparation work is in progress. 15-Jul-2025 11:16 AM
296 Saharanpur Harnandi (Hindon) Nalla Near Irrigation Land Untapped Drains 0.04 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
297 Saharanpur Harnandi (Hindon) Nand Vatika Untapped Drains 0.23 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
298 Saharanpur Harnandi (Hindon) Nand Vihar-1 Untapped Drains 0.17 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
299 Saharanpur Harnandi (Hindon) Nand Vihar-2 Untapped Drains 0.01 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
300 Azamgarh Tamsa Narauli Ka Nala (Pahle) Untapped Drains 1.12 Action to be taken 01-Jul-2024 12:00 AM
301 Azamgarh Tamsa Narauli U/S drain Untapped Drains 0.17 Action to be taken 01-Jul-2024 12:00 AM
302 Azamgarh Tamsa Narauli U/S drain Untapped Drains 0.09 Action to be taken 01-Jul-2024 12:00 AM
303 Deoria Ghaghra Nardeshwar Ghat Nala(Gaura) Untapped Drains 0.01 NA 04-Jul-2024 04:14 PM
304 Saharanpur Harnandi (Hindon) Natraj Drycliners Untapped Drains 0.45 CA signed on 27.09.2023 27-May-2025 03:05 PM
305 Saharanpur Harnandi (Hindon) Navyug Market Untapped Drains 0.17 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
306 Hathras Karvan Naya Bans Drain Untapped Drains 0.17 Proposed to be tapped in 24 MLD STP under I&D and STP works at Hathras project. Tendering in progres 01-Jul-2024 12:00 AM
307 Shamli Krishni Near Bada Buda Talab (Drain No. 01) Untapped Drains 1.40 BEP, Layout and HFD approved for 10 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. 09-Jun-2025 05:20 PM
308 Chitrakoot Mandakini Near Brahmacharya School, Sathe Road, Kuberganj, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:14 AM
309 Shamli Krishni Near bus stand at Charthawal Road (Drain No. 04) Untapped Drains 3.20 BEP, Layout and HFD approved for 10 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. 09-Jun-2025 05:21 PM
310 Azamgarh Tamsa Near DAV Degree college Drain Untapped Drains 0.35 Action to be taken 01-Jul-2024 12:00 AM
311 Shamli Krishni Near dumping site (Drain No. 05) Untapped Drains 0.50 BEP, Layout and HFD approved for 10 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. 09-Jun-2025 05:21 PM
312 Saharanpur Harnandi (Hindon) Near Janak Hotel Untapped Drains 1.00 CA signed on 27.09.2023 27-May-2025 03:03 PM
313 Saharanpur Harnandi (Hindon) Near Janak Nagar Untapped Drains 0.62 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
314 Shamli Krishni Near Karaunda Road (Drain No. 02) Untapped Drains 1.60 BEP, Layout and HFD approved for 05 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. 09-Jun-2025 05:17 PM
315 Shamli Krishni Near Krishni River Overbridge (Drain No. 03) Untapped Drains 0.20 BEP, Layout and HFD approved for 10 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. 09-Jun-2025 05:20 PM
316 Shamli Krishni Near Muzaffarnagar Road (Drain No. 01) Untapped Drains 1.01 BEP, Layout and HFD approved for 05 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. 09-Jun-2025 05:17 PM
317 Saharanpur Harnandi (Hindon) Near Police ground behind STP Untapped Drains 0.70 CA signed on 27.09.2023 27-May-2025 03:09 PM
318 Shamli Krishni Near Shamli Adda (Drain No. 02) Untapped Drains 1.40 BEP, Layout and HFD approved for 10 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. 09-Jun-2025 05:20 PM
319 Shamli Krishni Near Shamshanghat (Drain No. 03) Untapped Drains 0.46 BEP, Layout and HFD approved for 05 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. 09-Jun-2025 05:18 PM
320 Saharanpur Harnandi (Hindon) Near Taj Nala Untapped Drains 0.13 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
321 Saharanpur Harnandi (Hindon) New Gopal Nagar-1 Untapped Drains 0.26 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
322 Saharanpur Harnandi (Hindon) New Gopal Nagar-2 Untapped Drains 0.09 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
323 Agra Yamuna New Radha Nagar Untapped Drains 0.06 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:50 PM
324 Agra Yamuna New Radha Nagar Untapped Drains 0.05 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:51 PM
325 Banda Ken Nimni Nala Untapped Drains 10.44 Bio remediation treatment is being done by Nagar Palika, Banda 29-Sep-2025 12:01 PM
326 Azamgarh Tamsa Nirankari Bhawan Nala Untapped Drains 1.64 Action to be taken 01-Jul-2024 12:00 AM
327 Ayodhya Saryu Nirmalikund Drain Untapped Drains 2.50 I&D work for this drain is being done by UPJN (Urban) 01-Jul-2024 12:00 AM
328 Bulandshahr Kali Nizampur Drain Untapped Drains 10.00 Action to be taken 04-Jul-2024 01:37 PM
329 Gautam Buddha Nagar Harnandi (Hindon) Noida Drain Untapped Drains 15.00 Industrial Drain. To be taken up by UPPCB. 14-Aug-2024 03:23 PM
330 Lakhimpur Kheri Sarayan Noori Masjid drain Untapped Drains 0.08 DPR has been prepared by U.P. Jal Nigam (Urban) in SBM 2.0 and submmited for approval. 01-Jul-2024 12:00 AM
331 Saharanpur Harnandi (Hindon) Numaish camp V-Shape Untapped Drains 0.70 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
332 Saharanpur Harnandi (Hindon) Numish camp Untapped Drains 0.50 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
333 Agra Yamuna Nursery Mandir - I Untapped Drains 0.07 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:51 PM
334 Agra Yamuna Nursery Mandir - II Untapped Drains 0.01 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:51 PM
335 Saharanpur Harnandi (Hindon) Old Police Chowki Nala Untapped Drains 0.08 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
336 Saharanpur Harnandi (Hindon) Opposite RamTirath school drain Untapped Drains 0.58 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
337 Rae Bareli Ganga Padva Nala/(Muraibagh) Shankar Nagar Untapped Drains 1.20 Re-tendering work is in progress. Bid Document uploaded at e-tender portal on dt. 27.06.2025. Pre-bid Meeting dt. 04.07.2025 at 12:00 PM. Pre-bid reply sent to NMCG for review and approval on dt. 07.07.2025. NMCG sent final pre-bid replies on dt. 05.08.2025. Final pre-bid replies uploaded on e-tender portal on dt. 07.08.2025 Bid Submission date 22.08.2025. Technical Bid open on dt. 22.08.2025. TBER sent to NMCG for review and approval. 29-Sep-2025 03:45 PM
338 Ghazipur Ganga Pakka Ghat Drain Untapped Drains 0.50 City Sanitation action Plan has been submitted under SBM -2.0 by UPJN (Urban), SLTC awaited. 01-Jul-2024 12:00 AM
339 Saharanpur Harnandi (Hindon) Paondhoi Right Side- From Dhobi Ghat IPS Untapped Drains 3.57 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
340 Jhansi Pahunch Parichha drain Untapped Drains 3.00 Industrial Drain, to be taken up by UPPCB. 29-Sep-2025 11:57 AM
341 Mahoba NA Parmanand Nala Untapped Drains 0.41 Discharge of this drain falling to nearby Dariba sewage pond 29-Sep-2025 12:06 PM
342 Hamirpur Yamuna Pataleshwar Nala Untapped Drains 1.40 DPR for I&D works of this drain has been sent to SBM nideshalay by UPJN Urban. 29-Sep-2025 12:01 PM
343 Deoria Ghaghra Patel Nagar Nala Untapped Drains 0.04 NA 04-Jul-2024 04:03 PM
344 Ayodhya Saryu Pathan Tholiya D Untapped Drains 0.12 Will be tapped at 33 MLD Ayodhya STP 31-May-2024 01:29 PM
345 Ayodhya Saryu Pathantolia A Untapped Drains 12.68 Will be tapped at 33 MLD Ayodhya STP 01-Jul-2024 12:00 AM
346 Ayodhya Saryu Pathantolia B Untapped Drains 0.18 Will be tapped at 33 MLD Ayodhya STP 01-Jul-2024 12:00 AM
347 Ayodhya Saryu Pathantolia C Untapped Drains 0.15 Will be tapped at 33 MLD Ayodhya STP 01-Jul-2024 12:00 AM
348 Rae Bareli Ganga Pathvari Ghat ka Nala/(Tikaitganj) Untapped Drains 0.23 Re-tendering work is in progress. Bid Document uploaded at e-tender portal on dt. 27.06.2025. Pre-bid Meeting dt. 04.07.2025 at 12:00 PM. Pre-bid reply sent to NMCG for review and approval on dt. 07.07.2025. NMCG sent final pre-bid replies on dt. 05.08.2025. Final pre-bid replies uploaded on e-tender portal on dt. 07.08.2025 Bid Submission date 22.08.2025. Technical Bid open on dt. 22.08.2025. TBER sent to NMCG for review and approval. 29-Sep-2025 03:45 PM
349 Agra Yamuna Peeli Pokhar Untapped Drains 0.19 Construction of 0.25 MLD capacity DSTP at Poiya village is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
350 Agra Yamuna Poia Ghat - I Untapped Drains 0.34 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:52 PM
351 Agra Yamuna Poia Ghat - II Untapped Drains 0.01 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:52 PM
352 Rae Bareli Sai Police Line Nala Untapped Drains 5.50 DPR will be prepared after acquisition of Land for I&D of 01 drains which is to be provided by NPP 26-Mar-2025 09:28 AM
353 Ghaziabad Harnandi (Hindon) Pratap Vihar Drain Untapped Drains 32.16 A PFR, amounting Rs. 440.68 cr. has been submitted under Smart City Programme for I&D and STP (60 and 77 MLD) 11-Jul-2024 10:49 AM
354 Ambedkar Nagar Ghaghara Primary School Untapped Drains 0.23 DPR submitted to NMCG vide letter dated 31.03.2022. Observations intimated by NMCG vide letter dated 18.05.2022. Revised DPR was submitted to SMCG vide letter no. 420/012-0272(18)/2022 dated 03.09.2022. DPR submitted to NMCG vide letter no. 1054/0736/SMCG 19-Jun-2024 05:38 PM
355 Saharanpur Harnandi (Hindon) Punjabi Bhag-1 Untapped Drains 0.30 CA signed on 27.09.2023 27-May-2025 03:11 PM
356 Saharanpur Harnandi (Hindon) Punjabi Bhag-2 Untapped Drains 0.90 CA signed on 27.09.2023 27-May-2025 03:10 PM
357 Saharanpur Harnandi (Hindon) Pushpanjali Vihar Nala Untapped Drains 0.05 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
358 Lucknow Sai Qila Mohammadi Drain Untapped Drains 54.78 Concessionaire Agreement signed on dt. 26.08.2025. Financial closer work is in progress. 23-Sep-2025 12:36 PM
359 Hathras Karvan R.T.O. Drain Untapped Drains 0.10 Proposed to be tapped in 24 MLD STP under I&D and STP works at Hathras project. Tendering in progres 01-Jul-2024 12:00 AM
360 Agra Yamuna Radha Nagar Untapped Drains 0.31 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:52 PM
361 Saharanpur Harnandi (Hindon) Radha vihar Untapped Drains 0.87 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
362 Azamgarh Tamsa Rahul Nagar Madya ka Nala Untapped Drains 1.55 Action to be taken 01-Jul-2024 12:00 AM
363 Ghaziabad Harnandi (Hindon) Rahul Vihar Drain Untapped Drains 5.26 A PFR, amounting Rs. 440.68 cr. has been submitted under Smart City Programme for I&D and STP (60 and 77 MLD) 11-Jul-2024 10:45 AM
364 Unnao Ganga Railway Bridge Drain Untapped Drains 0.56 I&D and STP works at Shuklaganj is ongoing under Namami Gange, likely to be completed by Dec.-25 29-Sep-2025 09:38 AM
365 Pratapgarh Ganga Raja Hela Nala (Prathmik Nala) (Manikpur Nagar Panchayat) Untapped Drains 0.61 DPR Preparation is being done by U.P.J.N (Urban) under SBM 2.0 01-Jul-2024 12:00 AM
366 Rae Bareli Ganga Raja Tiloi Ghat Nala( Gaora Ghat) Untapped Drains 0.15 Re-tendering work is in progress. Bid Document uploaded at e-tender portal on dt. 27.06.2025. Pre-bid Meeting dt. 04.07.2025 at 12:00 PM. Pre-bid reply sent to NMCG for review and approval on dt. 07.07.2025. NMCG sent final pre-bid replies on dt. 05.08.2025. Final pre-bid replies uploaded on e-tender portal on dt. 07.08.2025 Bid Submission date 22.08.2025. Technical Bid open on dt. 22.08.2025. TBER sent to NMCG for review and approval. 29-Sep-2025 03:46 PM
367 PrayagRaj Ganga Rajapur Nala Untapped Drains 27.17 Work is under progress 26-Mar-2025 03:24 PM
368 Rae Bareli Sai Rajghat Nala Untapped Drains 7.80 DPR will be prepared after acquisition of Land for I&D of 01 drains which is to be provided by NPP 26-Mar-2025 09:29 AM
369 Pratapgarh Ganga Rajghat Nala (Post office Nala) (Manikpur Nagar Panchayat) Untapped Drains 0.26 DPR Preparation is being done by U.P.J.N (Urban) under SBM 2.0 01-Jul-2024 12:00 AM
370 Chitrakoot Mandakini Rajghata Ghat's drain Taronha, Rajghata Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:18 AM
371 Sant Ravidas Nagar Morwa Rajpura Drain Untapped Drains 3.40 DPR for 18 MLD, 5 MLD and 3 MLD STP approved by NMCG on 06.03.2025 10-Mar-2025 03:21 PM
372 Agra Yamuna Rambagh - III Untapped Drains 0.78 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:53 PM
373 Chitrakoot Mandakini Rambagh Akhada Wala Nala, Taronha, Rambagh Akhada, Karvi Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:18 AM
374 Hamirpur Betwa Ramedi Nala Untapped Drains 2.10 DPR for I&D of these drains has been sent to SBM, Nideshalaya for approval by UPJN(U) in Oct, 2023. 29-Sep-2025 12:02 PM
375 Kanpur Nagar Ganga Rameshwar drain Untapped Drains 2.94 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:39 AM
376 Ghazipur Ganga Rangmahal Ghat Drain Untapped Drains 0.20 City Sanitation action Plan has been submitted under SBM -2.0 by UPJN (Urban), SLTC awaited. 01-Jul-2024 12:00 AM
377 Kanpur Nagar Ganga Ranighat drain Untapped Drains 2.39 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:38 AM
378 Unnao Ganga Ravidas Nagar Nala (New) Untapped Drains 1.30 Tender is under process by UPJN(U) under SBM 2.0) 29-Sep-2025 09:38 AM
379 Jalaun Yamuna Rayda divara nala Untapped Drains 11.00 DPR for interception and diversion works of drain and construction of 5 mld STP is sanctioned under SBM-2 . Tendering work in progress by UPJN Urban. 29-Sep-2025 12:04 PM
380 Sitapur Sarayan Roti Godam Ram nagar Nala Untapped Drains 1.92 PFR for I&D of drains amount Rs. 306.81 Cr. has been sent to NMCG for approval on dt. 07.04.2021. Observations by NMCG on dt. 12.06.2024 is raised. Presently discharge measurement and water quality test is in progress afterwards DPR will be prepared which will be submitted upto 30.04.2025 26-Mar-2025 01:38 PM
381 PrayagRaj Ganga Sadar Bazar Nala Untapped Drains 4.79 Work is under progress 26-Mar-2025 03:25 PM
382 Kanpur Nagar Pandu Sagarpuri Nala Untapped Drains 1.40 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:42 AM
383 Lucknow Gomti Sahara City Drain Untapped Drains 7.59 DPR has been submitted to NMCG vide letter no. 1050/0369/SMCG-UP/12 dt. 27.09.2022 for approval. CE (Ganga) again requested to SMCG for approval of DPR on dt.19.06.2024. 04-Dec-2024 01:57 PM
384 Agra Yamuna Sakseria Drain Untapped Drains 1.91 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:53 PM
385 Lakhimpur Kheri ULL RIVER salempur kon Drain Untapped Drains 1.50 Originating from Dist Lakhimpur & falls in Ghagra river. 01-Jul-2024 12:00 AM
386 Ghazipur Ganga Sangat Ghat Drain Untapped Drains 0.50 City Sanitation action Plan has been submitted under SBM -2.0 by UPJN (Urban), SLTC awaited. 01-Jul-2024 12:00 AM
387 Deoria Ghaghra Sant Ravidas Ghat Nala(Patel Nagar East) Untapped Drains 0.27 NA 04-Jul-2024 04:04 PM
388 Pratapgarh Ganga Saraswati ghat nala (Pakka nala) (Manikpur Nagar Panchayat) Untapped Drains 0.60 DPR Preparation is being done by U.P.J.N (Urban) under SBM 2.0 01-Jul-2024 12:00 AM
389 Chitrakoot Mandakini Saryu Nala Sitapur, Chitrakoot Untapped Drains 0.00 Fund demand has been send to Head Quarter for flow measurement 16-Aug-2024 11:19 AM
390 Kanpur Nagar Ganga Satti Chaura Untapped Drains 1.37 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:38 AM
391 Lakhimpur Kheri ULL RIVER Sethghat Drain Untapped Drains 3.80 Originating from Dist Lakhimpur & falls in Ghagra river. 01-Jul-2024 12:00 AM
392 Mathura Kosi Arterial Channel Sewage farm drain, Kosi Untapped Drains 5.64 Proposed to be tapped in 12 MLD STP under I&D and STP work project. Tendering under progress 01-Jul-2024 12:00 AM
393 Agra Yamuna Shambhunath J.H. School Untapped Drains 0.02 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:53 PM
394 Shamli Krishni Shamli Nala Untapped Drains 20.10 BEP, Layout and HFD approved for 40 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Admin Building and Sludge Handling and Dewatering Building Submitted, which clear for Vetting & Structural Design. CCT and I&D GAD Submitted, which clear for Vetting & Structural Design. Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. 09-Jun-2025 05:18 PM
395 PrayagRaj Ganga Shankarghat Colony Drain (Near Phaphamau Bridge) Untapped Drains 0.95 Work is under progress 26-Mar-2025 03:24 PM
396 PrayagRaj Ganga Shankarghat Drain -01 Untapped Drains 0.44 Work is under progress 26-Mar-2025 03:23 PM
397 PrayagRaj Ganga Shankarghat Drain -02 Untapped Drains 0.95 Work is under progress 26-Mar-2025 03:23 PM
398 Saharanpur Harnandi (Hindon) Shanti Nagar-1 Untapped Drains 0.02 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
399 Saharanpur Harnandi (Hindon) Shanti Nagar-2 Untapped Drains 0.26 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
400 Saharanpur Harnandi (Hindon) Sharab Theka ky Samny Untapped Drains 0.73 CA signed on 27.09.2023 27-May-2025 03:04 PM
401 Mathura Kosi Arterial Channel Sher Garh road Nala - I Untapped Drains 0.47 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
402 Mathura Kosi Arterial Channel Sher Garh road Nala - II Untapped Drains 0.14 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
403 Saharanpur Harnandi (Hindon) Shiv Bagula Mukhi Untapped Drains 0.35 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
404 Azamgarh Tamsa Shiv mandir saray, Mandraj, pallini Untapped Drains 1.30 Action to be taken 01-Jul-2024 12:00 AM
405 Rae Bareli Ganga Shivala Ghat Nala Untapped Drains 0.03 Re-tendering work is in progress. Bid Document uploaded at e-tender portal on dt. 27.06.2025. Pre-bid Meeting dt. 04.07.2025 at 12:00 PM. Pre-bid reply sent to NMCG for review and approval on dt. 07.07.2025. NMCG sent final pre-bid replies on dt. 05.08.2025. Final pre-bid replies uploaded on e-tender portal on dt. 07.08.2025 Bid Submission date 22.08.2025. Technical Bid open on dt. 22.08.2025. TBER sent to NMCG for review and approval. 29-Sep-2025 03:46 PM
406 Ambedkar Nagar Tamsa shivalay ghat Untapped Drains 5.05 Action to be taken 03-Jul-2024 01:04 PM
407 PrayagRaj Ganga Shivkuti Drain No. 1 Untapped Drains 1.19 Work is under progress 26-Mar-2025 03:16 PM
408 PrayagRaj Ganga Shivkuti Drain No. 2 Untapped Drains 0.16 Work is under progress 26-Mar-2025 03:16 PM
409 PrayagRaj Ganga Shivkuti Drain No. 3 (North) Untapped Drains 0.22 Work is under progress 26-Mar-2025 03:17 PM
410 PrayagRaj Ganga Shivkuti Drain No. 4 Untapped Drains 0.28 Work is under progress 26-Mar-2025 03:18 PM
411 PrayagRaj Ganga Shivkuti Drain No. 5 Untapped Drains 0.32 Work is under progress 26-Mar-2025 03:19 PM
412 PrayagRaj Ganga Shivkuti Drain No. 6 Untapped Drains 0.28 Work is under progress 26-Mar-2025 03:19 PM
413 PrayagRaj Ganga Shivkuti Drain No. 7 (East) Untapped Drains 0.77 Work is under progress 26-Mar-2025 03:20 PM
414 Agra Yamuna Shyam Lal Vidya Mandir Untapped Drains 0.14 Under Tendering, Drains to be fully tapped after completion of Tender process By EA UPJN(U) 02-Aug-2025 12:54 PM
415 Azamgarh Tamsa Sidhari Nala Purana Pul Untapped Drains 0.52 Action to be taken 01-Jul-2024 12:00 AM
416 Mathura Kosi Arterial Channel Sigu Thok Raman Bagichi Nala Untapped Drains 0.15 Proposed to be tapped in 6 MLD STP under Chhata town sewerage scheme. Tendering under progress 01-Jul-2024 12:00 AM
417 Sitapur Sarayan Slaughter House Nala Untapped Drains 1.29 DPR preparation work is in progress. 15-Jul-2025 11:13 AM
418 Rae Bareli Ganga Soarakh Ghat Muroop Nala/(Tikaitganj) Untapped Drains 0.23 Re-tendering work is in progress. Bid Document uploaded at e-tender portal on dt. 27.06.2025. Pre-bid Meeting dt. 04.07.2025 at 12:00 PM. Pre-bid reply sent to NMCG for review and approval on dt. 07.07.2025. NMCG sent final pre-bid replies on dt. 05.08.2025. Final pre-bid replies uploaded on e-tender portal on dt. 07.08.2025 Bid Submission date 22.08.2025. Technical Bid open on dt. 22.08.2025. TBER sent to NMCG for review and approval. 29-Sep-2025 03:48 PM
419 Deoria Ghaghra Sonwa Mandir Nala(Azad Nagar South) Untapped Drains 0.01 NA 04-Jul-2024 04:05 PM
420 Deoria Ghaghra Sri Ram Singh ka Nala(Gaura) Untapped Drains 0.01 NA 04-Jul-2024 04:12 PM
421 Unnao Ganga Srinagar Drain Untapped Drains 6.00 Tender is under process by UPJN(U) under SBM 2.0) 29-Sep-2025 09:38 AM
422 Ambedkar Nagar Ghaghara State Bank Drain Untapped Drains 2.05 DPR submitted to NMCG vide letter dated 31.03.2022. Observations intimated by NMCG vide letter dated 18.05.2022. Revised DPR was submitted to SMCG vide letter no. 420/012-0272(18)/2022 dated 03.09.2022. DPR submitted to NMCG vide letter no. 1054/0736/SMCG 19-Jun-2024 05:40 PM
423 Gorakhpur Rohini Stepping Stone Nalla Untapped Drains 1.89 D.P.R. for “Gorakhpur Sewerage Scheme Zone-C, Part-2” amounting Rs. 566.15 Cr has been sanctioned under AMRUT 2.0. GO is awaited. 03-Jul-2024 04:55 PM
424 Gorakhpur Rohini Subhash Chandra Bose Collony Nalla Untapped Drains 4.49 Work is in progress under AMRUT. Proposed Date of completion is 31.03.2023 03-Jul-2024 04:54 PM
425 Lakhimpur Kheri Sarayan Sugar mill Drain Untapped Drains 0.90 DPR has been prepared by U.P. Jal Nigam (Urban) in SBM 2.0 and submmited for approval. 01-Jul-2024 12:00 AM
426 Saharanpur Kali West Suger mill Road Drain Untapped Drains 6.00 Technical bid open on dated 25.01.2025, Bid Evaluation report send to NMCG on 28.04.2025 27-May-2025 03:08 PM
427 Varanasi Ganga Sujabad Drain( Ghatwari Mata Mandir Drain) Untapped Drains 2.50 Project in progress under AMRUT 2.0. 20-May-2025 02:24 PM
428 Varanasi Ganga Sujabad Drain( Shayar Mata Mandir Drain) Untapped Drains 2.00 Project in progress under AMRUT 2.0. 20-May-2025 02:24 PM
429 Deoria Ghaghra Sulabh Sauchalay Nala(Azad Nagar South) Untapped Drains 0.04 NA 04-Jul-2024 04:10 PM
430 Saharanpur Harnandi (Hindon) Swami Dental clinic Untapped Drains 0.50 CA signed on 27.09.2023 27-May-2025 03:02 PM
431 Saharanpur Harnandi (Hindon) Taj Nalla Untapped Drains 14.36 CA signed on 27.09.2023 27-May-2025 03:29 PM
432 Ambedkar Nagar Tamsa tamsa pul ke pass Untapped Drains 1.50 Action to be taken 03-Jul-2024 01:13 PM
433 Sitapur Sarayan Tapdham Mandir Nala Untapped Drains 0.47 DPR preparation work is in progress. 15-Jul-2025 11:14 AM
434 Hathras Karvan Tarfara Drain Untapped Drains 5.85 Proposed to be tapped in 24 MLD STP under I&D and STP works at Hathras project. Tendering in progres 01-Jul-2024 12:00 AM
435 Gorakhpur Ghaghra Tarkulahi Nala Untapped Drains 0.08 Observation by NMCG dated 26/06/2024 was received regarding high COD/BOD. Regarding which COD/BOD test of 7drains is being done again, whose report will be submitted before 31/08/2024 28-Aug-2024 03:32 PM
436 Moradabad Ram ganga TDI City Drain Untapped Drains 4.86 To be tapped to 25 MLD STP. work is under progress. 01-Jul-2024 12:00 AM
437 Agra Yamuna Transport Nagar Untapped Drains 1.71 Construction of 3.00 MLD capacity DSTP at Transport Nagar is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
438 Kanpur Nagar Pandu Transport Nagar Drain Untapped Drains 4.22 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:42 AM
439 Gorakhpur Rapti Transport Nagar Nalla Untapped Drains 0.92 DPR for I&D of 8 drains and STP works (44 MLD) has been submitted to NMCG vide SMCG letter no.1030/0 01-Jul-2024 12:00 AM
440 Ambedkar Nagar Tamsa udyan vibhag drain Untapped Drains 1.54 Action to be taken 03-Jul-2024 01:02 PM
441 Kanpur Nagar Ganga UPA Compound Drain Untapped Drains 0.20 • DPR has been sanctioned in the 61th EC meeting vide letter no. Pr-12012/21/2020TECH1 NMCG (Comp. No.: 263215) dated 02-05-2025 for amount 138.11 cr.for which AA&ES issued on dt. 02.05.2025 • Draft tender document was sent to NMCG on 21.05.2025 for approval. Draft tender was approved by NMCG on dated 13.06.2025. • Tender was invited vide NIT dt. 13.06.2025. • Pre bid meeting conducted on 30.06.2025. • Reply of prebid query sent on dt 07-07-2025 • last date of submission of bid was 14.07.2025 • Last date for bid submission is 21.07.2025 as per corrigendum notice vide letter no. 701/AC-9/15 dated 11.07.2025 • Technical Bid opened on date 21.07.2025. • Meeting of Tender Committee at Zonal level conducted on dated 14.08.2025. • Meeting of Tender Committee at HQ level conducted on date 21.08.2025. Meeting of Tender Sanction Committee at HQ level conducted on date 03.09.2025. Proposal forwarded to NMCG, New Delhi for review/approval of Technical Bids on 03.09.2025. Financial Bids opened on 25.09.2025. Presently financial bid evaluation is under progress. 29-Sep-2025 11:43 AM
442 Rae Bareli Sai UPSIDC Nala Untapped Drains 2.30 DPR will be prepared after acquisition of Land for I&D of 02 drains which is to be provided by NPP 18-Sep-2024 04:10 PM
443 Saharanpur Harnandi (Hindon) Valmiki Colony Untapped Drains 0.54 Price BER of I&D and STP (135 MLD) send to NMCG on dated 01.05.2024 01-Jul-2024 12:00 AM
444 Agra Yamuna Vayepur Untapped Drains 1.44 Construction of 2.35 MLD capacity DSTP at Vayepur village is in progress under Agra Sewerage Scheme 01-Jul-2024 12:00 AM
445 Ghaziabad Harnandi (Hindon) Vijay Nagar, B.S Road, Dasana Drain Untapped Drains 40.17 A PFR, amounting Rs. 440.68 cr. has been submitted under Smart City Programme for I&D and STP (60 and 77 MLD) 11-Jul-2024 10:50 AM
446 Lakhimpur Kheri Sarayan Vishnubeher Drain Untapped Drains 0.74 DPR has been prepared by U.P. Jal Nigam (Urban) in SBM 2.0 and submmited for approval. 01-Jul-2024 12:00 AM
447 Moradabad Ram ganga Vivekanand Hospital Drain (Left) Untapped Drains 1.08 To be tapped to 25 MLD STP. is under progress. 01-Jul-2024 12:00 AM
448 Moradabad Ram ganga Vivekanand Hospital Drain (Right) Untapped Drains 2.61 To be tapped to 25 MLD STP. work is under progress. 01-Jul-2024 12:00 AM
449 Ghazipur Ganga Ward No. 15 Malhiya Basti Drain Untapped Drains 1.00 City Sanitation action Plan has been submitted under SBM -2.0 by UPJN (Urban), SLTC awaited. 01-Jul-2024 12:00 AM