| 1 |
Shamli |
Shamli |
I&D and STP Work in Shamli |
Shamli Nala |
Untapped Drains |
GAD, Structural Design and Drawings for SBR, Boundary Wall, SHU, I&D Structures, Admin Building & Lab, Staff Quarters, CCT/Tonner Room, Fiber Disc Filter and MPS have been approved. GAD and Data Sheets for Decanter and Diffuser, Gate Schedule and Electrical Load List, BEP, Layout and HFD for 40 MLD STP, BEP, P&ID and HFD of MPS, and Data Sheets, QAP and Curves for Turbo Blower and Centrifuge have also been approved.Digester, PTU, MPS and HT Building works are in progress. The contractor has been instructed to expedite the progress of work and ensure timely submission of all pending designs and drawings to avoid further delay in project completion. |
18-Sep-2026 11:42 AM |