| 1 |
Shamli |
Thanabhawan |
I&D and STP Work in Thanabhawan, Shamli |
Near Bada Buda Talab (Drain No. 01) |
Untapped Drains |
Survey and Soil Investigation works have been completed. BEP, Layout and HFD for the 10 MLD STP have been approved. BEP and P&ID of MPS have been approved. GAD, Structural Design and Drawings for SBR and Boundary Wall, PTU, Fibre Disc Filter, I&D and Sewer Network, MPS, CCT with Tonner Room and SHU have been approved. GAD and Data Sheets for Diffuser and Decanter, Data Sheet, QAP and Curves of Turbo Blower and Centrifuge, and Gate Schedule and Electrical Load List have also been approved. Admin. Building, MPS, Fiber Disc Filter, Tonner Room works are in progress. The contractor shall be instructed to expedite the progress of work and ensure timely submission of all pending designs and drawings to avoid further delay in project completion. |
18-Sep-2026 11:52 AM |
| 2 |
Shamli |
Thanabhawan |
I&D and STP Work in Thanabhawan, Shamli |
Near Shamli Adda (Drain No. 02) |
Untapped Drains |
Survey and Soil Investigation works have been completed. BEP, Layout and HFD for the 10 MLD STP have been approved. BEP and P&ID of MPS have been approved. GAD, Structural Design and Drawings for SBR and Boundary Wall, PTU, Fibre Disc Filter, I&D and Sewer Network, MPS, CCT with Tonner Room and SHU have been approved. GAD and Data Sheets for Diffuser and Decanter, Data Sheet, QAP and Curves of Turbo Blower and Centrifuge, and Gate Schedule and Electrical Load List have also been approved. Admin. Building, MPS, Fiber Disc Filter, Tonner Room works are in progress. The contractor shall be instructed to expedite the progress of work and ensure timely submission of all pending designs and drawings to avoid further delay in project completion. |
18-Sep-2026 11:54 AM |
| 3 |
Shamli |
Thanabhawan |
I&D and STP Work in Thanabhawan, Shamli |
Near Krishni River Overbridge (Drain No. 03) |
Untapped Drains |
Survey and Soil Investigation works have been completed. BEP, Layout and HFD for the 10 MLD STP have been approved. BEP and P&ID of MPS have been approved. GAD, Structural Design and Drawings for SBR and Boundary Wall, PTU, Fibre Disc Filter, I&D and Sewer Network, MPS, CCT with Tonner Room and SHU have been approved. GAD and Data Sheets for Diffuser and Decanter, Data Sheet, QAP and Curves of Turbo Blower and Centrifuge, and Gate Schedule and Electrical Load List have also been approved. Admin. Building, MPS, Fiber Disc Filter, Tonner Room works are in progress. The contractor shall be instructed to expedite the progress of work and ensure timely submission of all pending designs and drawings to avoid further delay in project completion. |
18-Sep-2026 11:52 AM |
| 4 |
Shamli |
Thanabhawan |
I&D and STP Work in Thanabhawan, Shamli |
Near bus stand at Charthawal Road (Drain No. 04) |
Untapped Drains |
Survey and Soil Investigation works have been completed. BEP, Layout and HFD for the 10 MLD STP have been approved. BEP and P&ID of MPS have been approved. GAD, Structural Design and Drawings for SBR and Boundary Wall, PTU, Fibre Disc Filter, I&D and Sewer Network, MPS, CCT with Tonner Room and SHU have been approved. GAD and Data Sheets for Diffuser and Decanter, Data Sheet, QAP and Curves of Turbo Blower and Centrifuge, and Gate Schedule and Electrical Load List have also been approved. Admin. Building, MPS, Fiber Disc Filter, Tonner Room works are in progress. The contractor shall be instructed to expedite the progress of work and ensure timely submission of all pending designs and drawings to avoid further delay in project completion. |
18-Sep-2026 11:53 AM |
| 5 |
Shamli |
Thanabhawan |
I&D and STP Work in Thanabhawan, Shamli |
Near dumping site (Drain No. 05) |
Untapped Drains |
Survey and Soil Investigation works have been completed. BEP, Layout and HFD for the 10 MLD STP have been approved. BEP and P&ID of MPS have been approved. GAD, Structural Design and Drawings for SBR and Boundary Wall, PTU, Fibre Disc Filter, I&D and Sewer Network, MPS, CCT with Tonner Room and SHU have been approved. GAD and Data Sheets for Diffuser and Decanter, Data Sheet, QAP and Curves of Turbo Blower and Centrifuge, and Gate Schedule and Electrical Load List have also been approved. Admin. Building, MPS, Fiber Disc Filter, Tonner Room works are in progress. The contractor shall be instructed to expedite the progress of work and ensure timely submission of all pending designs and drawings to avoid further delay in project completion. |
18-Sep-2026 11:53 AM |