1 |
Shamli |
Banat |
I&D and STP Work in Banat, Shamli |
Near Muzaffarnagar Road (Drain No. 01) |
Untapped Drains |
BEP, Layout and HFD approved for 05 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:17 PM |
2 |
Shamli |
Banat |
I&D and STP Work in Banat, Shamli |
Near Karaunda Road (Drain No. 02) |
Untapped Drains |
BEP, Layout and HFD approved for 05 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:17 PM |
3 |
Shamli |
Banat |
I&D and STP Work in Banat, Shamli |
Near Shamshanghat (Drain No. 03) |
Untapped Drains |
BEP, Layout and HFD approved for 05 MLD STP. GAD, Structural Design and Dwg. for SBR and Boundary wall approved. GAD for Sludge Handling Unit Submitted, which are clear for Vetting & Structural Design.Project is 4 months behind schedule. Delay in design/drawing submission by Contractor. Contractor need to increase expedite the progress of work and submission of design/drawings. |
09-Jun-2025 05:18 PM |