S.No District City Project Name Drain Name DrainType Remarks Last Update Date
1 Shamli Bantikhera Banat I&D and STP Work in Bantikhera and Babri village, Shamli Babari - Banti Kheda Nala Untapped Drains Survey and Soil Investigation works have been completed. BEP, Layout and HFD for the 05 MLD STP have been approved. GAD, Structural Design and Drawings of PTU, SBR and Retaining Wall have been approved. Data Sheet, QAP and Curves of Turbo Blower and Centrifuge have been approved. Gate Schedule has been approved. The project is currently 10 months behind schedule. The contractor shall be instructed to expedite the progress of work and submission of pending designs and drawings to avoid further delay in project completion. 18-Sep-2026 11:45 AM