S.No District City Project Name Drain Name DrainType Remarks Last Update Date
1 Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow Pata Nala Tapped Drains Tapped to 39 MLD STP at Daulatganj. 39 MLD STP construction work completed and Trial & Run is in progress. 07-Mar-2025 12:21 PM
2 Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow Barikala Drain Untapped Drains Date of start of 3.5 MLD Barikala STP is given on dt. 07.09.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Construction of Boundary wall work is in progress. SBR Basin-2 Selector Zone wall 3rd lift reinforcement, shuttering and casting work is in progress. CCT wall 1st lift reinforcement, shuttering and casting work is in progress. MPS - wall 3rd lift reinforcement, shuttering and casting work is in progress. 21-Jul-2025 11:02 AM