S.No District City Project Name Drain Name DrainType Remarks Last Update Date
1 Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow Pata Nala Tapped Drains Tapped to 39 MLD STP at Daulatganj. 39 MLD STP construction work completed and Trial & Run is in progress. 07-Mar-2025 12:21 PM
2 Lucknow Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow Barikala Drain Untapped Drains Date of start of 3.5 MLD Barikala STP is given on dt. 07.09.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Construction of Boundary wall work is in progress. SBR Basin-2 Selector Zone wall 4th lift and decanter wall 2nd lift reinforcement, shuttering and casting work is in progress. CCT wall 2nd lift reinforcement, shuttering and casting work is in progress. MPS - wall 5th lift reinforcement, shuttering and casting work is in progress. 25-Aug-2025 11:01 AM