| 1 |
Lucknow |
|
Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow |
Pata Nala |
Tapped Drains |
Tapped to 39 MLD STP at Daulatganj. 39 MLD STP construction work completed and Trial & Run is in progress. |
07-Mar-2025 12:21 PM |
| 2 |
Lucknow |
|
Pollution Abatement Of Gomti River (Phase 1 Part 1) Lucknow |
Barikala Drain |
Untapped Drains |
Date of start of 3.5 MLD Barikala STP is given on dt. 07.09.2024 to M/s R.K. Engineers Sales Ltd. - Khilari Infrastructures (JV). Construction of Boundary wall work is in progress. SBR Basin-1&2 wall final lift, Walk way and Inlet Channel shuttering, reinforcement and casting work is in progress. CCT wall 2nd lift casting completed. MPS - wall 5th lift casting completed. |
13-Oct-2025 11:28 AM |