| S.No | District | City | Project Name | Drain Name | DrainType | Remarks | Last Update Date |
|---|---|---|---|---|---|---|---|
| 1 | Unnao | Unnao | I&D of Drains and STP works in Unnao (15MLD) | City Jail Drain (Dakari drain) | Tapped Drains | The overall progress of the project is 99.00%. All works of the STP (Civil / E&M) have been completed. Due to the high groundwater level resulting from floods in the Ganga river and rainfall, the construction of 1 remaining manhole near the STP premises and dewatering work remained disrupted from August 2025 to January 2026. Against the dewatering and Desilting work in the 1200 mm RCC pipe, the dewatering work is currently in progress. The joint repairing of 01 manhole (MH 37) and the re-laying work of the 1200 mm RCC pipe over a length of 400 meters from MH 37 to MH-39 are pending. | 06-May-2026 11:47 AM |