| 1 |
Moradabad |
Moradabad |
Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 |
Vivekanand Hospital Drain (Left) |
Untapped Drains |
To be tapped to 25 MLD STP. is under progress. |
01-Jul-2024 12:00 AM |
| 2 |
Moradabad |
Moradabad |
Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 |
Vivekanand Hospital Drain (Right) |
Untapped Drains |
To be tapped to 25 MLD STP. work is under progress. |
01-Jul-2024 12:00 AM |
| 3 |
Moradabad |
Moradabad |
Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 |
MIT Drain |
Untapped Drains |
To be tapped to 25 MLD STP. work is under progress. |
01-Jul-2024 12:00 AM |
| 4 |
Moradabad |
Moradabad |
Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 |
Moksh Dham Drain |
Untapped Drains |
To be tapped to 25 MLD STP. work is under progress. |
01-Jul-2024 12:00 AM |
| 5 |
Moradabad |
Moradabad |
Interception & Diversion (I&D) of Drains and Sewerage Treatment Plant at Moradabad zone 2 |
TDI City Drain |
Untapped Drains |
To be tapped to 25 MLD STP. work is under progress. |
01-Jul-2024 12:00 AM |