1 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Chaubari Nala |
Tapped Drains |
Drain is tapped and STP is under trail and run |
01-Jul-2024 12:00 AM |
2 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Dhaurera Maffi Barrier Nala |
Tapped Drains |
Tapped under 42 mld STP. STP is in trial and run. |
01-Jul-2024 12:00 AM |
3 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Dhaurera Maffi Village Nala |
Tapped Drains |
Tapped under 42 mld STP. STP is in trial and run. |
01-Jul-2024 12:00 AM |
4 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
100 Foota Road Nala |
Tapped Drains |
Tapped under 42 mld STP. STP is in trial and run. |
01-Jul-2024 12:00 AM |
5 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Jagatpur Police Chauki to Nakatiya River |
Tapped Drains |
Tapped under 42 mld STP. STP is in trial and run. |
01-Jul-2024 12:00 AM |
6 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Super City Nala |
Tapped Drains |
Tapped under 42 mld STP. STP is in trial and run. |
01-Jul-2024 12:00 AM |
7 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Sunrise Colony Nala |
Tapped Drains |
Tapped under 42 mld STP. STP is in trial and run. |
01-Jul-2024 12:00 AM |
8 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Ashish Royal Park Nala |
Not to be Tappd |
removed from project due to negligible discharge. |
01-Jul-2024 12:00 AM |
9 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Rohelkhand College Nala |
Not to be Tappd |
removed from project due to negligible discharge. |
01-Jul-2024 12:00 AM |
10 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Mahanagar Nala - 01 |
Tapped Drains |
Tapped under 42 mld STP. STP is in trial and run. |
01-Jul-2024 12:00 AM |
11 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Mahanagar Nala - 02 |
Tapped Drains |
Tapped under 42 mld STP. STP is in trial and run. |
01-Jul-2024 12:00 AM |
12 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Haru Nagla Nala - 02 |
Tapped Drains |
TP is in trial and run..08.2Tapped under 42 mld STP. STP is in trial and run.022 by NMCG |
01-Jul-2024 12:00 AM |
13 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Green Park Nala |
Tapped Drains |
Tapped under 42 mld STP. STP is in trial and run. |
01-Jul-2024 12:00 AM |
14 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Satellite Bus Stand Nala |
Tapped Drains |
Tapped under 42 mld STP. STP is in trial and run. |
01-Jul-2024 12:00 AM |
15 |
Bareilly |
Bareilly |
Development of Sewage Treatment Plant at Bareilly |
Airforce Nala |
Tapped Drains |
Tapped under 1 mld STP. STP is under trial and run. |
01-Jul-2024 12:00 AM |