Project Completion Certificate (Ground Water)
Scheme ID: 20000036 Name of Scheme: ATWA ASIGAON 0111 No. of Villages: 1 No. of Habitation Covered: 6
Total Population Covered: 5460 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 29-Apr-2023 Actual Date of Completion (Capex): 02-Oct-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewells 33.07Mtr/ 100.52Mtr ATWA ASIGAON 0111 27.485548 80.078554
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 1.2 M³ per Min /45Mtr ATWA ASIGAON 0111 27.485548 80.078554
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 350 KL/ 16Mtr ATWA ASIGAON 0111 27.485588 80.078465
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. Pipe 200 0.02172
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6 Class PE-100 63 5.389
2 HDPE Pipe PN-6 Class PE-100 75 2.716
3 HDPE Pipe PN-6 Class PE-100 90 2.346
4 HDPE Pipe PN-6 Class PE-100 110 1.143
5 HDPE Pipe PN-6 Class PE-100 125 1.622
6 HDPE Pipe PN-6 Class PE-100 140 0.356
7 HDPE Pipe PN-6 Class PE-100 160 0.777
8 HDPE Pipe PN-6 Class PE-100 200 1.757
HSC Connection
Sno. Total Nos.
1 570
Other Details
2.85
0.00
3.22
01-Jan-2024
30-Nov-2024