Project Completion Certificate (Ground Water)
Scheme ID: 20008736 Name of Scheme: Jalalpur Sabakpur No. of Villages: 2 No. of Habitation Covered: 4
Total Population Covered: 4808 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 07-Jul-2023 Actual Date of Completion (Capex): 30-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 30/52.62 Jallalpur Sabukpur 26.518661 82.75332824
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump 1000 Jallalpur Sabukpur 26.518661 82.75332824
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-9 200 30 COMPLETED
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN-6 63 19.705
2 HDPE PN-6 75 3.091
3 HDPE PN-6 90 2.334
4 HDPE PN-6 110 1.818
5 HDPE PN-6 140 1.44
6 HDPE PN-6 200 0.19
HSC Connection
Sno. Total Nos.
1 718
Other Details
338.20
389.36
389.36
17-Jun-2025
15-Jul-2025