| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20009905 | Name of Scheme: BAIJUPUR | No. of Villages: 1 | No. of Habitation Covered: 8 |
| Total Population Covered: 2080 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 11-Apr-2023 | Actual Date of Completion (Capex): 08-Apr-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 24/60 | BAIJPUR | 26.441848 | 82.454732 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VT PUMP- 1 | 500 | BAIJPUR | 26.441848 | 82.454732 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT - 1 | 150/12 | BAIJPUR | 26.441848 | 82.454732 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K9 | 100 | 30 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PN-6 | 63 | 3.9 | |
| 2 | HDPE PN-6 | 75 | 1.124 | |
| 3 | HDPE PN-6 | 90 | 0.451 | |
| 4 | HDPE PN-6 | 110 | 0.492 | |
| 5 | HDPE PN-6 | 140 | 0.31 | |
| 6 | HDPE PN-6 | 160 | 0.22 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 343 |