Project Completion Certificate (Ground Water)
Scheme ID: 20010836 Name of Scheme: KARANPUR SCHEME No. of Villages: 1 No. of Habitation Covered: 4
Total Population Covered: 3491 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 09-Apr-2023 Actual Date of Completion (Capex): 28-Jan-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 30M / 222M Karanpur 28.02405 80.581559
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 750 LPM / 45 M Karanpur 28.02405 80.581559
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200 KL / 15 M Karanpur 28.02405 80.581559
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe 125 0.0215
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 160 0.089
2 HDPE Pipe PN-6: Class PE-100 140 0.9967
3 HDPE Pipe PN-6: Class PE-100 110 0.3757
4 HDPE Pipe PN-6: Class PE-100 90 0.660
5 HDPE Pipe PN-6: Class PE-100 63 7.5738
HSC Connection
Sno. Total Nos.
1 529
Other Details
2.35
2.70
2.70
27-Apr-2024
19-Nov-2024