Project Completion Certificate (Ground Water)
Scheme ID: 20010897 Name of Scheme: AHMADPURI URF AMANPURI No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2364 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 11-Feb-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 25.6 Mtr / 96.43 Mtr AHMADPURI URF AMANPURI 28.940618 77.959884
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 500 LPM / 50 Mtr AHMADPURI URF AMANPURI 28.940618 77.959884
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150 Kl / 12 M AHMADPURI URF AMANPURI 28.940618 77.959884
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.019
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 5.014
2 HDPE 90 0.386
3 HDPE 110 0.181
HSC Connection
Sno. Total Nos.
1 439
Other Details
2.34
2.34
1.85
30-Jun-2023
31-Dec-2024