Project Completion Certificate (Ground Water)
Scheme ID: 20010922 Name of Scheme: RAHMAPUR No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2701 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 19-Dec-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 36.16 Mtr / 88.5 Mtr RAHMANPUR 29.157927 77.964138
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 550 LPM / 48 Mtr RAHMANPUR 29.157927 77.964138
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150 Kl / 12 M RAHMANPUR 29.157927 77.964138
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.002485
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 5.335
2 HDPE 90 1.034
3 HDPE 110 0.240
4 HDPE 125 0.0604
5 HDPE 160 0.185
HSC Connection
Sno. Total Nos.
1 582
Other Details
2.59
2.29
2.02
05-May-2024
06-Nov-2024