Project Completion Certificate (Ground Water)
Scheme ID: 20011220 Name of Scheme: JANGETHI No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 5364 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 02-Feb-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 31.37 Mtr / 120.91 Mtr JANGETHI 29.043622 77.637362
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 1050 LPM / 52 Mtr JANGETHI 29.043622 77.637362
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 300 Kl / 14 M JANGETHI 29.043622 77.637362
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 200 0.0196
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 8.249
2 HDPE 90 0.173
3 HDPE 110 0.546
4 HDPE 125 0.078
5 HDPE 140 0.105
6 HDPE 160 0.146
7 HDPE 180 0.101
8 HDPE 200 0.223
HSC Connection
Sno. Total Nos.
Other Details
3.58
3.58
2.89
21-Jun-2023
15-Oct-2024