Project Completion Certificate (Ground Water)
Scheme ID: 20011264 Name of Scheme: Bistauli No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 2900 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 27-Feb-2023 Actual Date of Completion (Capex): 26-Feb-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 27/127.73 Bistauli 26.936 83.3596
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 42/40 Bistauli 26.936 83.3596
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 200/12 Bistauli 26.936 83.3596
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.01 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.742 Laying Completed
2 HDPE 75 2.613 Laying Completed
3 HDPE 90 0.313 Laying Completed
4 HDPE 110 0.91 Laying Completed
5 HDPE 140 0.418 Laying Completed
HSC Connection
Sno. Total Nos.
1 491
Other Details
2.58
0.00
2.57
26-Feb-2026
01-Mar-2026