Project Completion Certificate (Ground Water)
Scheme ID: 20011272 Name of Scheme: Ajdev No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1525 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 10-Feb-2024 Actual Date of Completion (Capex): 20-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 10.01 MTR / 131.31 MTR AJDEV 29.146376 78.156592
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 325 LPM /42 MTR AJDEV 29.146376 78.156692
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 100 KL / 12 MTR AJDEV 29.146702 78.156596
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 DI PIPE 100 0.025
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN-6 CLASS PE-100 125 0.156
2 HDPE PIPE PN-6 CLASS PE-100 90 0.040
3 HDPE PIPE PN-6 CLASS PE-100 75 0.132
4 HDPE PIPE PN-6 CLASS PE-100 63 2.441
HSC Connection
Sno. Total Nos.
1 181
Other Details
1.27
1.27
1.27
18-Jun-2024
19-Jun-2024