| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20011296 | Name of Scheme: KISHANPUR BIRANA | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 3047 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 25-Jan-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 30.29 Mtr / 99.36 Mtr | KISANPUR BIRANA | 29.071345 | 77.906305 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 700 LPM / 52 Mtr | KISANPUR BIRANA | 29.071345 | 77.906305 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 200 Kl / 14 M | KISANPUR BIRANA | 29.071345 | 77.906305 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.0022 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.760 | |
| 2 | HDPE | 90 | 0.0200 | |
| 3 | HDPE | 110 | 0.086 | |
| 4 | HDPE | 125 | 0.098 | |
| 5 | HDPE | 140 | 0.147 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 557 |