Project Completion Certificate (Ground Water)
Scheme ID: 20011343 Name of Scheme: ALAM NAGAR No. of Villages: 1 No. of Habitation Covered: 9
Total Population Covered: 6100 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 26-Jul-2023 Actual Date of Completion (Capex): 13-Dec-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24 M/ 116.8 M ALAM NAGAR 27.739711 80.095918
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 0.55 M³ per Min /43Mtr ALAM NAGAR 27.739711 80.095918
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 200 KL/ 12 Mtr ALAM NAGAR 27.740543 80.097297
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D. I. Pipe 200 0.0208
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 7.335
2 HDPE Pipe PN-6, Class PE-100 75 3.492
3 HDPE Pipe PN-6, Class PE-100 90 6.314
4 HDPE Pipe PN-6, Class PE-100 110 2.342
5 HDPE Pipe PN-6, Class PE-100 125 2.328
6 HDPE Pipe PN-6, Class PE-100 140 0.016
7 HDPE Pipe PN-6, Class PE-100 160 0.582
8 HDPE Pipe PN-6, Class PE-100 200 0.315
HSC Connection
Sno. Total Nos.
1 1007
Other Details
4.30
0.00
3.55
12-Mar-2026
14-Mar-2026