| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20011362 | Name of Scheme: BAMTA PUR CHILLAUR | No. of Villages: 1 | No. of Habitation Covered: 3 |
| Total Population Covered: 4970 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 26-Jul-2023 | Actual Date of Completion (Capex): 11-Jan-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 24.11 M/ 122.74 M | BAMTA PUR CHILLAUR | 27.341784 | 79.912883 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 1.1 M³ per Min /45Mtr | BAMTA PUR CHILLAUR | 27.341784 | 79.912883 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 300 KL/ 18 Mtr | BAMTA PUR CHILLAUR | 27.341777 | 79.912912 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D. I. Pipe | 200 | 0.02010 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe PN-6, Class PE-100 | 63 | 4.564 | |
| 2 | HDPE Pipe PN-6, Class PE-100 | 75 | 3.071 | |
| 3 | HDPE Pipe PN-6, Class PE-100 | 90 | 1.504 | |
| 4 | HDPE Pipe PN-6, Class PE-100 | 110 | 1.209 | |
| 5 | HDPE Pipe PN-6, Class PE-100 | 125 | 0.272 | |
| 6 | HDPE Pipe PN-6, Class PE-100 | 140 | 0.687 | |
| 7 | HDPE Pipe PN-6, Class PE-100 | 160 | 0.943 | |
| 8 | HDPE Pipe PN-6, Class PE-100 | 200 | 2.279 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 732 |