Project Completion Certificate (Ground Water)
Scheme ID: 20011928 Name of Scheme: TARAI DIH GP WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 8
Total Population Covered: 1957 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 20-Mar-2024 Actual Date of Completion (Capex): 22-Jan-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Depth of Plain Pipe (m) 288.3 TW 26.173561 83.588819
2 Depth of Strainer (m) 18 TW 26.173561 83.588819
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible pump 450/46 TW 26.173561 83.588819
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Zinc Tank 125/12 OHT 26.173563 83.588822
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K7 100 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN6 PE100 63 9.4
2 HDPE PN6 PE100 75 2.59
3 HDPE PN6 PE100 90 0.15
4 HDPE PN6 PE100 110 0.98
HSC Connection
Sno. Total Nos.
1 342
Other Details
2.30
2.16
0.00
22-Jan-2025
25-Jan-2025