Project Completion Certificate (Ground Water)
Scheme ID: 20011939 Name of Scheme: TARKULHEE No. of Villages: 1 No. of Habitation Covered: 12
Total Population Covered: 5830 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 15-Sep-2023 Actual Date of Completion (Capex): 24-Oct-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 27.07/109.87 Tarkulahee 26.649728 83.47316
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 75/43 Tarkulahee 26.649728 83.47316
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 350/16 Tarkulahee 26.6495 83.4730
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 200 0.030 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 15.493 Laying Completed
2 HDPE 75 1.099 Laying Completed
3 HDPE 90 1.460 Laying Completed
4 HDPE 110 0.717 Laying Completed
5 HDPE 140 0.566 Laying Completed
6 HDPE 160 0.853 Laying Completed
HSC Connection
Sno. Total Nos.
1 848
Other Details
2.96
0.00
3.20
23-Oct-2024
10-Jan-2025