Project Completion Certificate (Ground Water)
Scheme ID: 20011974 Name of Scheme: SONAYEE KHURD No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 2300 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 20-Jul-2023 Actual Date of Completion (Capex): 19-Aug-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 18.05/116.47 Sonayee Khurd 26.5331 83.4523
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 27/41 Sonayee Khurd 26.5331 83.4523
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Overhead Tank-1 150/14 Sonayee Khurd 26.5331 83.4522
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.030 Laying Completed
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.834 Laying Completed
2 HDPE 75 0.085 Laying Completed
3 HDPE 90 0.053 Laying Completed
4 HDPE 110 0.457 Laying Completed
HSC Connection
Sno. Total Nos.
1 291
Other Details
1.69
0.00
1.69
18-Aug-2024
11-Dec-2024