Project Completion Certificate (Ground Water)
Scheme ID: 20012132 Name of Scheme: THATHIYA NARAINMAU No. of Villages: 2 No. of Habitation Covered: 5
Total Population Covered: 3020 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 14-Jun-2023 Actual Date of Completion (Capex): 06-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewells 16.07Mtr/ 49.77Mtr THATHIYA NARAINMAU 27.122451 80.755725
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 0.680 M³ per Min /45Mtr THATHIYA NARAINMAU 27.122451 80.755725
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 200KL/ 14Mtr THATHIYA NARAINMAU 27.122427 80.756028
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. Pipe 150 0.01994
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 1.475
2 HDPE Pipe PN-6, Class PE-100 75 5.264
3 HDPE Pipe PN-6, Class PE-100 90 2.835
4 HDPE Pipe PN-6, Class PE-100 110 0.753
5 HDPE Pipe PN-6, Class PE-100 125 2.297
6 HDPE Pipe PN-6, Class PE-100 160 0.927
7 HDPE Pipe PN-6, Class PE-100 200 0.072
HSC Connection
Sno. Total Nos.
1 330
Other Details
2.70
0.00
2.59
05-Sep-2024
24-Dec-2024