Project Completion Certificate (Ground Water)
Scheme ID: 20012345 Name of Scheme: Gogawan Umray No. of Villages: 4 No. of Habitation Covered: 5
Total Population Covered: 3190 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 26-Jul-2023 Actual Date of Completion (Capex): 20-Oct-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewells 21 Mtr/ 72 Mtr Gogawan Umray 27.10051 80.528137
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 0.72 M³ per Min /45 Mtr Gogawan Umray 27.10051 80.528137
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 225 KL/ 18 Mtr Gogawan Umray 27.100503 80.528252
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. Pipe 150 0.01902
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6, Class PE-100 63 4.795
2 HDPE Pipe PN-6, Class PE-100 75 1.116
3 HDPE Pipe PN-6, Class PE-100 90 0.196
4 HDPE Pipe PN-6, Class PE-100 110 2.516
5 HDPE Pipe PN-6, Class PE-100 125 1.469
6 HDPE Pipe PN-6, Class PE-100 160 0.169
7 HDPE Pipe PN-6, Class PE-100 180 0.168
HSC Connection
Sno. Total Nos.
1 365
Other Details
2.47
0.00
2.26
19-Jan-2024
25-Dec-2024