| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20012358 | Name of Scheme: Khanigawan Kalan | No. of Villages: 2 | No. of Habitation Covered: 3 |
| Total Population Covered: 1900 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 26-Jul-2023 | Actual Date of Completion (Capex): 20-Mar-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewells | 18.0 Mtr/ 128.8 Mtr | Khanigawan Kalan | 27.492946 | 79.940757 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 0.2 M³ Per Min /45Mtr | Khanigawan Kalan | 27.492946 | 79.940757 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 75KL/ 16Mtr | Khanigawan Kalan | 27.492913 | 79.940634 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I. Pipe | 80 | 0.018 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe PN-6 | 63 | 3.109 | |
| 2 | HDPE Pipe PN-6 | 75 | 2.519 | |
| 3 | HDPE Pipe PN-6 | 90 | 2.374 | |
| 4 | HDPE Pipe PN-6 | 110 | 0.142 | |
| 5 | HDPE Pipe PN-6 | 125 | 1.624 | |
| 6 | HDPE Pipe PN-6 | 160 | 1.170 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 202 |