Project Completion Certificate (Ground Water)
Scheme ID: 20012392 Name of Scheme: Kurval Banaras No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 3500 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 28-May-2023 Actual Date of Completion (Capex): 20-Feb-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 36.07 M / 91.78 M Kurval Banaras 28.438434 77.831409
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUMERSIBLE 700 LPM / 48.60 M Kurval Banaras 28.438434 77.831409
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 200 KL / 14 M Kurval Banaras 28.438597 77.831401
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.021
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.05
2 HDPE 75 0.200
3 HDPE 110 0.060
4 HDPE 140 0.448
5 HDPE 160 0.204
6 HDPE 180 0.359
HSC Connection
Sno. Total Nos.
1 596
Other Details
2.82
2.13
2.63
06-Jun-2025
07-Jun-2025