Project Completion Certificate (Ground Water)
Scheme ID: 20012412 Name of Scheme: Khanauda No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2251 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 28-May-2023 Actual Date of Completion (Capex): 09-Apr-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 21.02 M / 102.01 M KHANAUDA 28.525859 77.914998
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUMERSIBLE 450 LPM / 47 M KHANAUDA 28.525859 77.914998
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 150 KL / 12 M KHANAUDA 28.525946 77.914862
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.0235
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.676
2 HDPE 75 0.513
3 HDPE 90 0.130
4 HDPE 110 0.188
5 HDPE 140 0.287
HSC Connection
Sno. Total Nos.
1 475
Other Details
1.59
1.49
1.59
18-Aug-2025
19-Aug-2025