| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20012502 | Name of Scheme: Mahmoodpur | No. of Villages: 2 | No. of Habitation Covered: 5 |
| Total Population Covered: 2290 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 26-Jul-2023 | Actual Date of Completion (Capex): 15-Oct-2023 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewells | 12 Mtr/ 79.06 Mtr | Mahmoodpur | 27.279037 | 80.475867 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 0.3 M³ per Min /45Mtr | Mahmoodpur | 27.279037 | 80.475867 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 75 KL/ 16 Mtr | Mahmoodpur | 27.279293 | 80.47604 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I. Pipe | 100 | 0.02116 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe PN-6, Class PE-100 | 63 | 2.050 | |
| 2 | HDPE Pipe PN-6, Class PE-100 | 75 | 1.792 | |
| 3 | HDPE Pipe PN-6, Class PE-100 | 90 | 2.802 | |
| 4 | HDPE Pipe PN-6, Class PE-100 | 110 | 1.394 | |
| 5 | HDPE Pipe PN-6, Class PE-100 | 160 | 2.528 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 416 |