| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20012625 | Name of Scheme: Gurgaon | No. of Villages: 1 | No. of Habitation Covered: 3 |
| Total Population Covered: 5150 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 14-Sep-2021 | Actual Date of Completion (Capex): 31-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well | 30/200 | Gurgaon | 26.165902 | 79.495551 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 38.10/60 | Gurgaon | 26.165902 | 79.495551 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 300/17 | Gurgaon | 26.165902 | 79.495551 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.016 | As per Site |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 10.50 | As per Site |
| 2 | HDPE | 75 | 0.595 | As per Site |
| 3 | HDPE | 90 | 1.450 | As per Site |
| 4 | HDPE | 110 | 0.196 | As per Site |
| 5 | HDPE | 125 | 1.658 | As per Site |
| 6 | HDPE | 140 | 0.154 | As per Site |
| 7 | HDPE | 180 | 0.056 | As per Site |
| 8 | HDPE | 200 | 0.257 | As per Site |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 1030 |