| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20012683 | Name of Scheme: Songara Water Supply Scheme | No. of Villages: 2 | No. of Habitation Covered: 6 |
| Total Population Covered: 2571 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 10-Apr-2023 | Actual Date of Completion (Capex): 10-Jan-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 24.9/271.39 | Sogara | 26.194966 | 81.63479 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | VT PUMP-1 | 600 LPM | Sogara | 26.194966 | 81.63479 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 175/12 | Sogara | 26.194966 | 81.63479 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-7 | 150 | 30.00 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PN-6 | 63 | 7.66 | |
| 2 | HDPE PN-6 | 75 | 1.82 | |
| 3 | HDPE PN-6 | 90 | 2.25 | |
| 4 | HDPE PN-6 | 140 | 0.83 | |
| 5 | HDPE PN-6 | 160 | 0.06 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 476 |