Project Completion Certificate (Ground Water)
Scheme ID: 20013973 Name of Scheme: SINGHA WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 4097 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 10-Feb-2024 Actual Date of Completion (Capex): 11-Mar-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewells 18.01 MTR /130.07 MTR SINGHA 78.366422 78.366422
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 12.5 HP 600 LMP/44MTR SINGHA 78.366422 78.366422
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175KL/14MTR SINGHA 78.366422 78.366422
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7 DI PIPE 150 0.020
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN-6 CLASS PE-100 110 0.072
2 HDPE PIPE PN-6 CLASS PE-100 90 0.287
3 HDPE PIPE PN-6 CLASS PE-100 75 0.301
4 HDPE PIPE PN-6 CLASS PE-100 63 4.308
5 HDPE PIPE PN-6 CLASS PE-100 160 0.075
HSC Connection
Sno. Total Nos.
1 464
Other Details
1.90
1.78
1.90
10-Sep-2025
11-Sep-2025