| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20014068 | Name of Scheme: Poornpur Nawada W/S Scheme | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 4014 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 14-Mar-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 18/ 102.5 | Poornpur Nawada | 28.8023 | 77.3812 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE PUMP | 550 LPM/ 70 m | Poornpur Nawada | 28.8023 | 77.3812 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 200/ 12 | Poornpur Nawada | 28.795000 | 77.385555 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7 | 100 | 0.0237 | |
| 2 | K-7 | 150 | 0.0109 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 0.417 | |
| 2 | HDPE | 75 | 0.125 | |
| 3 | HDPE | 63 | 3.783 | |
| 4 | HDPE | 125 | 0.088 | |
| 5 | HDPE | 180 | 0.154 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 450 |