Project Completion Certificate (Ground Water)
Scheme ID: 20014861 Name of Scheme: GURA PWS No. of Villages: 2 No. of Habitation Covered: 6
Total Population Covered: 1750 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 08-May-2023 Actual Date of Completion (Capex): 01-Aug-2023
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 15.03 Mtr./117.84 Mtr. GURA 26.860452* 79.506805*
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 33.96(M3/Hr.)/46Mtr. GURA 26.860452* 79.506805*
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 100/16 GURA 26.861843* 79.504308*
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 D.I. 100 33.25
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4534.00
2 HDPE 75 166.00
3 HDPE 90 504.00
4 HDPE 110 435.00
5 HDPE 140 735.00
6 HDPE 160 261
HSC Connection
Sno. Total Nos.
1 300
Other Details
1.54
1.72
1.72
07-Nov-2023
01-Nov-2024