Project Completion Certificate (Ground Water)
Scheme ID: 20015269 Name of Scheme: PIDHI WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 9
Total Population Covered: 3650 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 03-Mar-2026 Actual Date of Completion (Capex): 31-May-2026
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 25.13/88.67 Pidhi 26.34075006 82.25254078
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump -1 650 LPM / 45 M Pidhi 26.34075006 82.25254078
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 175 KL / 16 M Pidhi 26.34075006 82.25254078
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI / K9 125 0.0300
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 1.179
2 HDPE 75 2.880
3 HDPE 63 9.519
4 HDPE 160 0.650
5 HDPE 140 1.996
6 HDPE 125 2.256
7 HDPE 110 4.000
HSC Connection
Sno. Total Nos.
1 598
Other Details
2.87
0.00
2.86
18-Mar-2026
31-Mar-2026